| Owner | Filings | Most Recent |
|---|---|---|
| NYCHA | 28 | 08/29/2026 |
| NEW YORK CITY HOUSING AUTHORITY | 10 | 07/08/2026 |
| NYC HOUSING AUTHORITY | 23 | 03/22/2026 |
| DELRIC CONSTRUCITON CO IN | 3 | 03/22/2026 |
| NYCHA 99 | 1 | 03/22/2026 |
| ROBERT YAUCH (NYCHA) | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KZ ENGINEERING, P.C | 1 | 08/03/2026 |
| NYMS CONSULTING, LLC | 1 | 07/29/2026 |
| QUEENS ENGINEERING | 4 | 09/22/2025 |
| AK CONSULTING SERVICES, INC | 1 | 07/24/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| AK CONSULTING SERVICES | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DELRIC CONSTRUCTION CO IN | General Contractor | 12 | 07/08/2026 |
| ROMA SCAFFOLDING INC | General Contractor | 5 | 07/08/2026 |
| BAKER, W | Electrical | 3 | 03/21/2026 |
| AMMITZBOLL, PAUL | Electrical | 3 | 03/21/2026 |
| STANTON, T | Electrical | 1 | 03/21/2026 |
| ADVANCED SCAFFOLD SER.LLC | General Contractor | 1 | 08/26/2026 |
| WDF INC | General Contractor | 1 | 08/26/2026 |
| MULTI-PHASE ELEC'L SVCS | Electrical | 1 | 03/22/2026 |
| RIVERA, EDWARD | Electrical | 1 | 03/21/2026 |
| RUSS FLAUM | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| KS ENGINEERS, P.C. | 7715 | 1 | 07/29/2026 |
| QUEENS ENGINEERING PLLC | 8898 | 2 | 09/22/2025 |
| AK CONSULTING SERVICES, I | 6198 | 1 | 03/27/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | WDF INC | 08/07/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | ADVANCED SCAFFOLD SER.LLC | 08/03/2026 |
| DOB NOW | Suspended Scaffold | Signed-off | D&N CONST & CONSULTNG INC | 03/31/2026 |
| DOB NOW | Suspended Scaffold | Signed-off | D&N CONST & CONSULTNG INC | 02/02/2026 |
| DOB NOW | Suspended Scaffold | Signed-off | D&N CONST & CONSULTNG INC | 09/23/2025 |
| DOB NOW | Supported Scaffold | Signed-off | ROMA SCAFFOLDING INC | 08/13/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | ROMA SCAFFOLDING INC | 07/01/2025 |
| DOB NOW | Construction Fence | Signed-off | ROMA SCAFFOLDING INC | 07/01/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | WALL CONTRACTOR CORP | 03/28/2025 |
| DOB NOW | Construction Fence | Signed-off | DELRIC CONSTRUCTION CO IN | 10/04/2021 |
| DOB NOW | Construction Fence | Signed-off | DELRIC CONSTRUCTION CO IN | 09/14/2021 |
| DOB NOW | Construction Fence | Signed-off | DELRIC CONSTRUCTION CO IN | 04/26/2021 |
| DOB NOW | Construction Fence | Signed-off | DELRIC CONSTRUCTION CO IN | 01/21/2021 |
| DOB NOW | Construction Fence | Signed-off | DELRIC CONSTRUCTION CO IN | 07/17/2020 |
| DOB NOW | Construction Fence | Signed-off | DELRIC CONSTRUCTION CO IN | 07/25/2019 |
| BIS | PL | ISSUED | V. C. VITANZA SONS INC | 08/15/2025 |
| BIS | MH | ISSUED | ACS SYSTEM ASSOCIATES INC. | 04/28/2025 |
| BIS | MH | ISSUED | ACS SYSTEM ASSOCIATES INC. | 04/24/2024 |
| BIS | MH | ISSUED | ACS SYSTEM ASSOCIATES INC. | 04/24/2023 |
| BIS | PL | ISSUED | V. C. VITANZA SONS INC | 08/08/2022 |
| BIS | MH | ISSUED | ACS SYSTEM ASSOCIATES INC. | 05/04/2022 |
| BIS | PL | ISSUED | BORIS MECHANICAL INC | 09/24/2021 |
| BIS | PL | ISSUED | BORIS MECHANICAL INC | 09/24/2021 |
| BIS | PL | ISSUED | BORIS MECHANICAL INC | 09/24/2021 |
| BIS | PL | ISSUED | V. C. VITANZA SONS INC | 08/25/2021 |
| BIS | OT | ISSUED | DELRIC CONSTRUCTION CO IN | 04/26/2021 |
| BIS | OT | ISSUED | DELRIC CONSTRUCTION CO IN | 04/26/2021 |
| BIS | OT | ISSUED | DELRIC CONSTRUCTION CO IN | 04/26/2021 |
| BIS | OT | ISSUED | DELRIC CONSTRUCTION CO IN | 04/26/2021 |
| BIS | PL | ISSUED | V. C. VITANZA SONS INC | 09/11/2020 |
| BIS | OT | ISSUED | DELRIC CONSTRUCTION CO IN | 05/06/2020 |
| BIS | OT | ISSUED | DELRIC CONSTRUCTION CO IN | 05/06/2020 |
| BIS | OT | ISSUED | DELRIC CONSTRUCTION CO IN | 05/06/2020 |
| BIS | OT | ISSUED | DELRIC CONSTRUCTION CO IN | 05/06/2020 |
| BIS | MH | ISSUED | ACS SYSTEM ASSOCIATES INC. | 05/01/2020 |
| BIS | OT | ISSUED | DELRIC CONSTRUCTION CO IN | 06/25/2019 |
| BIS | OT | ISSUED | ROMA SCAFFOLDING INC | 02/11/2015 |
| BIS | EQ | ISSUED | ROMA SCAFFOLDING INC | 10/21/2014 |
| BIS | EQ | ISSUED | ROMA SCAFFOLDING INC | 08/01/2014 |
| BIS | OT | ISSUED | ROMA SCAFFOLDING INC | 07/30/2014 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/18/2025 | Complete | AUJLA ELECTRIC CORP | — |
| 03/10/2023 | Complete | CSI SEC & ELECTRIC INC | — |
| 05/01/2021 | Permit Issued | N.Y.C. HOUSING AUTHORITY | General Wiring |
| 05/01/2021 | Permit Issued | N.Y.C. HOUSING AUTHORITY | General Wiring |
| 05/01/2021 | Permit Issued | N.Y.C. HOUSING AUTHORITY | General Wiring |
| 11/18/2019 | Complete | MULTI-PHASE ELEC'L SVCS | — |
| 10/21/2019 | Complete | MULTI-PHASE ELEC'L SVCS | General Wiring |
| 05/08/2018 | Complete | JEMCO ELECT. CONTRS INC | General Wiring |
| 05/08/2018 | Complete | JEMCO ELECT. CONTRS INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/03/2026 | Permit Issued | ADVANCED SCAFFOLD SER.LLC | Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/27/2025 | Permit Issued | WALL CONTRACTOR CORP | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/20/2026 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/22/2026 | Mechanical Systems | LEOVIGILDO FONTANA | special |
| 06/22/2026 | Chimneys and vents | LEOVIGILDO FONTANA | special |
| 06/22/2026 | Tenant Protection Plan Compliance | LEOVIGILDO FONTANA | special |
| 06/22/2026 | Final | LEOVIGILDO FONTANA | progress |
| 09/19/2025 | Post-installed Anchors | ANDREAS CHRISTOFOROU | special |
| 09/19/2025 | Alternative Materials - OTCR Buildings Bulletin Number | ANDREAS CHRISTOFOROU | special |
| 08/07/2025 | Post-installed Anchors | ANDREAS CHRISTOFOROU | special |
| 06/14/2019 | Final | QAISAR KHAN | progress |