| Owner | Filings | Most Recent |
|---|---|---|
| SK DEVELOPMENT | 85 | 10/01/2026 |
| PLATINUM SERVICES NY | 7 | 03/22/2026 |
| ALBA SERVICES INC | 5 | 03/22/2026 |
| CM & ASSOCIATES CONSTRUCTION MANAGE | 5 | 03/22/2026 |
| ACEF-CBSKI 360 BOWERY | 5 | 03/21/2026 |
| 4TH ST REALTY HOLDING CORP | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| CAPRON DESIGN LLC | 1 | 11/03/2025 |
| ROBERT DERECTOR ASSOCIATES | 3 | 10/30/2025 |
| ARCHITECTURE BY DOMANI | 3 | 05/14/2024 |
| ICOR ASSOCIATES | 19 | 04/18/2024 |
| PAUL PERDEK, PROF. ENG. PLLC | 6 | 02/12/2024 |
| LOMBARDO PROFESSIONAL ENGINEERING | 1 | 05/23/2023 |
| TOHFAZ UDDIN PE PC | 2 | 02/02/2023 |
| ANCORA ENGINEERING, PLLC | 5 | 09/23/2022 |
| GACE DPC | 5 | 08/05/2022 |
| HM LOKE CONSULTING ENGINEERING PC | 1 | 05/05/2022 |
| ASHRAF CORP | 2 | 02/23/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| A1 EXPEDITING SERVICE | 16 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 58 | 03/21/2026 |
| RIZZO GROUP | 4 | 03/21/2026 |
| LOMBARDO BUILDING CONSULTANTS | 1 | 03/21/2026 |
| HS DESIGN STUDIO | 2 | 03/21/2026 |
| KD DESIGNS | 1 | 03/21/2026 |
| DOMANI CONSULTING | 3 | 03/21/2026 |
| HM LOKE CONSULTING ENGINEERING PC | 1 | 03/21/2026 |
| GREEN STUDIO | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CM AND ASSOCIATES CONST | General Contractor | 33 | 07/08/2026 |
| ROCKLEDGE SCAFFOLD CORP | General Contractor | 10 | 07/08/2026 |
| SOURCE CONSTRUCTION INC | General Contractor | 7 | 07/08/2026 |
| PLATINUM SERVICES NY LLC | General Contractor | 6 | 03/21/2026 |
| S & J INDUSTRIAL CORP | Fire Protection | 4 | 07/08/2026 |
| S & J INDUSTRIAL CORP | Plumbing | 4 | 07/08/2026 |
| CENTRIFUGAL ELECTRIC LLC | Electrical | 2 | 03/22/2026 |
| ADVANCED FACADE SOLUTION* | General Contractor | 2 | 03/21/2026 |
| ALBA SERVICES INC | General Contractor | 2 | 03/21/2026 |
| JT MAGEN & COMPANY INC | General Contractor | 2 | 09/16/2026 |
| JMD CONTRACTING OF NY INC | General Contractor | 1 | 07/08/2026 |
| PAR FIRE PROTECTION LLC | Fire Protection | 1 | 10/01/2026 |
| PAR PLUMBING CO., INC | Plumbing | 1 | 09/12/2026 |
| LION ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AK ENGINEERING PC | 678 | 1 | 10/30/2025 |
| DOMANI INSPECTION SERVICE | 843 | 21 | 04/18/2024 |
| ANCORA ENGINEERING, PLLC | 6818 | 4 | 09/23/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Permit Issued | PAR FIRE PROTECTION LLC | 09/15/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | JT MAGEN & COMPANY INC | 09/15/2026 |
| DOB NOW | Plumbing | Permit Issued | RCM GROUP INC | 09/11/2026 |
| DOB NOW | General Construction | Permit Issued | JT MAGEN & COMPANY INC | 09/11/2026 |
| DOB NOW | Supported Scaffold | Signed-off | PLATINUM SERVICES NY LLC | 10/22/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | OSMANI NYC INC | 10/02/2024 |
| DOB NOW | Plumbing | Signed-off | S & J INDUSTRIAL CORP | 07/09/2024 |
| DOB NOW | Boiler Equipment | Signed-off | PACIFIC ENERGY CORP | 04/24/2024 |
| DOB NOW | Boiler Equipment | Signed-off | PACIFIC ENERGY CORP | 04/24/2024 |
| DOB NOW | Boiler Equipment | Signed-off | DMT PLUMBING&HEATING CORP | 04/23/2024 |
| DOB NOW | General Construction | Signed-off | CHRISTOPHER B. MESBAH | 03/26/2024 |
| DOB NOW | Boiler Equipment | Signed-off | PACIFIC ENERGY CORP | 02/13/2024 |
| DOB NOW | Supported Scaffold | Signed-off | JMD CONTRACTING OF NY INC | 02/08/2024 |
| DOB NOW | Mechanical Systems | Signed-off | CHRISTOPHER B. MESBAH | 01/26/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ROCKLEDGE SCAFFOLD CORP | 01/23/2024 |
| DOB NOW | Construction Fence | Signed-off | ROCKLEDGE SCAFFOLD CORP | 01/23/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | ROCKLEDGE SCAFFOLD CORP | 01/23/2024 |
| DOB NOW | Plumbing | Signed-off | S & J INDUSTRIAL CORP | 11/06/2023 |
| DOB NOW | Sprinklers | Signed-off | S & J INDUSTRIAL CORP | 11/01/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ROCKLEDGE SCAFFOLD CORP | 08/04/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ADVANCED FACADE SOLUTION* | 05/23/2023 |
| DOB NOW | Structural | Signed-off | CHRISTOPHER B. MESBAH | 03/22/2023 |
| DOB NOW | Structural | Signed-off | CHRISTOPHER B. MESBAH | 03/22/2023 |
| DOB NOW | Mechanical Systems | Signed-off | CHRISTOPHER B. MESBAH | 01/27/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ROCKLEDGE SCAFFOLD CORP | 01/25/2023 |
| DOB NOW | Construction Fence | Signed-off | ROCKLEDGE SCAFFOLD CORP | 01/24/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | ROCKLEDGE SCAFFOLD CORP | 01/24/2023 |
| DOB NOW | Structural | Signed-off | CHRISTOPHER B. MESBAH | 12/15/2022 |
| DOB NOW | Plumbing | Signed-off | S & J INDUSTRIAL CORP | 11/10/2022 |
| DOB NOW | Plumbing | Signed-off | S & J INDUSTRIAL CORP | 11/02/2022 |
| DOB NOW | Standpipe | Signed-off | S & J INDUSTRIAL CORP | 11/02/2022 |
| DOB NOW | Standpipe | Signed-off | S & J INDUSTRIAL CORP | 11/02/2022 |
| DOB NOW | Standpipe | Signed-off | S & J INDUSTRIAL CORP | 11/02/2022 |
| DOB NOW | Construction Fence | Signed-off | SOURCE CONSTRUCTION INC | 08/19/2022 |
| DOB NOW | Foundation | Signed-off | CHRISTOPHER B. MESBAH | 07/12/2022 |
| DOB NOW | Construction Fence | Signed-off | SOURCE CONSTRUCTION INC | 06/30/2022 |
| DOB NOW | Foundation | Signed-off | CHRISTOPHER B. MESBAH | 06/29/2022 |
| DOB NOW | Support of Excavation | Signed-off | CHRISTOPHER B. MESBAH | 06/03/2022 |
| DOB NOW | Construction Fence | Signed-off | SOURCE CONSTRUCTION INC | 05/05/2022 |
| DOB NOW | Structural | Signed-off | CHRISTOPHER B. MESBAH | 03/23/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/30/2025 | Permit Issued | JT MAGEN & COMPANY INC | Air Conditioning Systems | Cooling Above Air XPX-018S1-3-0-VF-AA 62 BTU ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/30/2025 | Permit Issued | PAR FIRE PROTECTION LLC | 662 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/30/2025 | — | — | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/24/2025 | Complete | CENTRIFUGAL ELECTRIC LLC | General Wiring |
| 01/24/2025 | Complete | CENTRIFUGAL ELECTRIC LLC | 2 meters, 2 new_meters |
| 04/24/2024 | Complete | JAM ELECTRICAL CORP | — |
| 01/05/2024 | Complete | LION ELECTRIC INC | General Wiring |
| 01/13/2023 | Complete | LION ELECTRIC INC | — |
| 11/10/2022 | Complete | LION ELECTRIC INC | General Wiring |
| 08/26/2022 | Complete | Z & Z ELECTRIC INC | General Wiring |
| 02/15/2022 | Complete | ILLUMINOUS ELECTRIC CORP. | General Wiring |
| 01/28/2022 | Complete | ANTHONY G FERRY INC | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/13/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 05/30/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 04/30/2024 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 04/26/2024 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 04/25/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/23/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/23/2024 | Certified StandPipe-Fire Pump (SD)-Fire Pump Test | Certified | View ↗ |
| 04/23/2024 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 04/09/2024 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 04/08/2024 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 04/05/2024 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 07/21/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/13/2023 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 01/10/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 01/10/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 12/02/2022 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 12/02/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/10/2025 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 10/10/2025 | Interior lighting power | — | energy_progress |
| 10/10/2025 | Lighting controls | — | energy_progress |
| 10/10/2025 | Heating Systems | — | special |
| 10/10/2025 | Post-installed Anchors | — | special |
| 10/10/2025 | HVAC-R and service water heating system controls | — | energy_progress |
| 10/10/2025 | Exterior lighting power | — | energy_progress |
| 10/10/2025 | HVAC-R and service water heating equipment | — | energy_progress |
| 10/10/2025 | Duct leakage testing, insulation and design | — | energy_progress |
| 10/07/2025 | Mechanical Systems | — | special |
| 10/07/2025 | Final | — | progress |
| 04/23/2024 | HVAC-R and service water heating equipment | JOHN MCMONAGLE | energy_progress |
| 04/23/2024 | Smoke Control Systems Testing | JOHN MCMONAGLE | special |
| 04/23/2024 | Heating Systems | JOHN MCMONAGLE | special |
| 04/23/2024 | Emergency and Standby Power Systems (Generator) | JOHN MCMONAGLE | special |
| 04/23/2024 | Mechanical Systems | JOHN MCMONAGLE | special |
| 04/23/2024 | Final | JOHN MCMONAGLE | progress |
| 04/23/2024 | Electrical motors and elevators | JOHN MCMONAGLE | energy_progress |
| 04/23/2024 | HVAC-R and service water piping design and insulation | JOHN MCMONAGLE | energy_progress |
| 04/23/2024 | Shutoff dampers | JOHN MCMONAGLE | energy_progress |
| 04/23/2024 | Maintenance information | JOHN MCMONAGLE | energy_progress |
| 04/23/2024 | Duct leakage testing, insulation and design | JOHN MCMONAGLE | energy_progress |
| 04/23/2024 | HVAC-R and service water heating system controls | JOHN MCMONAGLE | energy_progress |
| 04/23/2024 | Lighting controls | JOHN MCMONAGLE | energy_progress |
| 04/23/2024 | Exterior lighting power | JOHN MCMONAGLE | energy_progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Chobani House | Office | Floors 1, 3–5, 9–16 | Project M01299130 Project M01299136 Project M01299140 |