RoofUnder Construction21p · 2 filings · 20 docs
ArchitectureDM
Issued Permit Scope
General Construction · Supported Scaffold
Installation of temporary supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
On file for this project
2 documents
RENOVATION OF EXISTING SINGLE-FAMILY STRUCTURE; VERTICAL ENLARGEMENT. NEW SCHEDULE OF OCCUPANCY TO BE OBTAINED.
On file for this project
25 documents · 3 drawing sheets
Floor 6Under Construction13p · 6 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
INSTALLATION OF TEMPORARY STAIR ACCESS PLATFORM AND STAIRS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
On file for this project
6 documents
INSTALLATION OF TEMPORARY SHAFT ACCESS PLATFORM. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
On file for this project
3 documents
MECHANICAL WORK FILED IN CONJUNCTION WITH RENOVATION AND ENLARGEMENT OF SINGLE-FAMILY HOME. ARCHITECTURAL WORK FILED UNDER M00479971. NEW CERTIFICATE OF OCCUPANCY TO BE OBTAINED.
On file for this project
8 documents
Latest 3 of 6 filings on this floor.
Floor 5Under Construction13p · 7 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Foundation · General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
INSTALLATION OF TEMPORARY STAIR ACCESS PLATFORM AND STAIRS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
On file for this project
6 documents
INSTALLATION OF TEMPORARY SHAFT ACCESS PLATFORM. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
On file for this project
3 documents
MECHANICAL WORK FILED IN CONJUNCTION WITH RENOVATION AND ENLARGEMENT OF SINGLE-FAMILY HOME. ARCHITECTURAL WORK FILED UNDER M00479971. NEW CERTIFICATE OF OCCUPANCY TO BE OBTAINED.
On file for this project
8 documents
Latest 3 of 7 filings on this floor.
Floor 4Under Construction13p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Foundation · General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
INSTALLATION OF TEMPORARY STAIR ACCESS PLATFORM AND STAIRS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
On file for this project
6 documents
INSTALLATION OF TEMPORARY SHAFT ACCESS PLATFORM. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
On file for this project
3 documents
MECHANICAL WORK FILED IN CONJUNCTION WITH RENOVATION AND ENLARGEMENT OF SINGLE-FAMILY HOME. ARCHITECTURAL WORK FILED UNDER M00479971. NEW CERTIFICATE OF OCCUPANCY TO BE OBTAINED.
On file for this project
8 documents
Latest 3 of 7 filings on this floor.
Floor 3Under Construction13p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Foundation · General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
INSTALLATION OF TEMPORARY STAIR ACCESS PLATFORM AND STAIRS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
On file for this project
6 documents
INSTALLATION OF TEMPORARY SHAFT ACCESS PLATFORM. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
On file for this project
3 documents
MECHANICAL WORK FILED IN CONJUNCTION WITH RENOVATION AND ENLARGEMENT OF SINGLE-FAMILY HOME. ARCHITECTURAL WORK FILED UNDER M00479971. NEW CERTIFICATE OF OCCUPANCY TO BE OBTAINED.
On file for this project
8 documents
Latest 3 of 7 filings on this floor.
Floor 2Under Construction13p · 7 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Foundation · General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
INSTALLATION OF TEMPORARY STAIR ACCESS PLATFORM AND STAIRS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
On file for this project
6 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY SHAFT ACCESS PLATFORM. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
On file for this project
3 documents
MECHANICAL WORK FILED IN CONJUNCTION WITH RENOVATION AND ENLARGEMENT OF SINGLE-FAMILY HOME. ARCHITECTURAL WORK FILED UNDER M00479971. NEW CERTIFICATE OF OCCUPANCY TO BE OBTAINED.
On file for this project
8 documents
Latest 3 of 7 filings on this floor.
Floor 1Under Construction13p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Foundation · General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
INSTALLATION OF TEMPORARY STAIR ACCESS PLATFORM AND STAIRS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
On file for this project
6 documents
INSTALLATION OF TEMPORARY SHAFT ACCESS PLATFORM. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
On file for this project
3 documents
MECHANICAL WORK FILED IN CONJUNCTION WITH RENOVATION AND ENLARGEMENT OF SINGLE-FAMILY HOME. ARCHITECTURAL WORK FILED UNDER M00479971. NEW CERTIFICATE OF OCCUPANCY TO BE OBTAINED.
On file for this project
8 documents
Latest 3 of 7 filings on this floor.
CellarUnder Construction13p · 9 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Foundation · General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
INSTALLATION OF TEMPORARY STAIR ACCESS PLATFORM AND STAIRS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
On file for this project
6 documents
MECHANICAL WORK FILED IN CONJUNCTION WITH RENOVATION AND ENLARGEMENT OF SINGLE-FAMILY HOME. ARCHITECTURAL WORK FILED UNDER M00479971. NEW CERTIFICATE OF OCCUPANCY TO BE OBTAINED.
On file for this project
8 documents · 1 drawing sheet
RENOVATION OF EXISTING SINGLE-FAMILY STRUCTURE; VERTICAL ENLARGEMENT. NEW SCHEDULE OF OCCUPANCY TO BE OBTAINED.
On file for this project
25 documents · 3 drawing sheets
Latest 3 of 8 filings on this floor.