← Back
Miscellaneous two family
40 MANDY COURT
STATEN ISLAND · Annadale-Huguenot-Prince's Bay-Woodrow · BIN 5132050
💬 Discuss this project
1998Year Built
2Stories
B9Building Class
R3-2Zoning
1,760 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Miscellaneous two family · 2,330 sf lot · 0.76 FAR built · Flood zone X
Locations of Work
Electrical
Roof1 filing · 6 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR102/05/2024
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281102/05/2024
Building Lifecycle
All (9)Filed (1)Permit Issued (1)Signed Off (1)Violation (1)Special Inspection (5)
05/14/2026
Signed off — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 14 Panels, 5.11 kW
S00997472-I1
02/21/2024
Permit issued — Solar
S00997472-I1-SL
02/05/2024
Filed — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 14 Panels, 5.11 kW
S00997472-I1
01/29/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
01/29/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
01/29/2024
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
01/29/2024
Special inspection requirement — Final
Mina Makar
01/29/2024
Special inspection requirement — Air barrier - visual inspection
Mina Makar
06/05/2006
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR02/21/2024
BISPLISSUEDDUO PLUMBING & HTG CORP.12/31/1997
BIS—ISSUEDL & E DEVELOPMENT CORP.05/13/1997
1 project · most recent 01/29/2024
FiledStatusContractorScope
01/29/2024CompleteISLAND ELECTRIC CORP—
1 project · most recent 02/05/2024
FiledStatusContractorScope
02/05/2024Signed-offMOMENTUM SOLAR14 panels, 5.11 kw, 247 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
01/29/2024Fire-Resistant Penetrations and JointsMina Makarspecial
01/29/2024Structural Stability – Alterations of existing buildingsMina Makarspecial
01/29/2024Energy Code Compliance InspectionsMina Makarprogress
01/29/2024FinalMina Makarprogress
01/29/2024Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 6 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/21/2026S00997472-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/27/2026S00997472-I1Open ↗
08/27/2026S00997472-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026S00997472-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/27/2026S00997472-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026S00997472-I1Open ↗