| Owner | Filings | Most Recent |
|---|---|---|
| George Comfort & Sons | 15 | 07/08/2026 |
| 40 West 20th Street Condominium | 4 | 03/21/2026 |
| Altpower | 1 | 03/21/2026 |
| Majestic Midtown | 1 | 03/21/2026 |
| Dormitory Authority of the State | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KZ Engineering | 6 | 10/02/2023 |
| Robert Germain Jr. PE | 4 | 10/04/2021 |
| Murray Engineering | 1 | 04/26/2021 |
| Format Architecture Office | 1 | 03/17/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| Synergy Building Consultants | 7 | 03/21/2026 |
| EC Building Consultants | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Ceprine Construction | Scaffold | 26 | 07/08/2026 |
| Ics Builders | General Contractor | 2 | 07/08/2026 |
| Cerina General Contracting | Scaffold | 2 | 03/21/2026 |
| CC Controlled Plumbing Co | Plumbing | 2 | 07/08/2026 |
| Hirsch Barry | Electrical | 1 | 03/21/2026 |
| The Metro Group Electric | Electrical | 1 | 03/21/2026 |
| Rico Electric | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Robert F. Germain Jr. PE | 5100 | 4 | 10/04/2021 |
| Ace Structural Engineering | 496 | 2 | 04/26/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Signed-off | Ceprine Construction | 09/05/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | Cerina General Contracting | 05/10/2024 |
| DOB NOW | Supported Scaffold | Signed-off | Ceprine Construction | 02/08/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | Ceprine Construction | 09/06/2023 |
| DOB NOW | Supported Scaffold | Signed-off | Ceprine Construction | 02/16/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | Ceprine Construction | 09/16/2022 |
| DOB NOW | Supported Scaffold | Signed-off | Ceprine Construction | 02/16/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | Ceprine Construction | 09/20/2021 |
| DOB NOW | Structural | Signed-off | Ics Builders | 05/02/2021 |
| DOB NOW | General Construction | Signed-off | Ics Builders | 04/27/2021 |
| DOB NOW | Supported Scaffold | Signed-off | Ceprine Construction | 02/18/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | Ceprine Construction | 09/25/2020 |
| DOB NOW | Supported Scaffold | Signed-off | Ceprine Construction | 09/24/2020 |
| DOB NOW | Supported Scaffold | Signed-off | Ceprine Construction | 08/04/2020 |
| DOB NOW | Boiler Equipment | Signed-off | CC Controlled Plumbing Co | 03/03/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | Ceprine Construction | 02/20/2020 |
| DOB NOW | Plumbing | Signed-off | CC Controlled Plumbing Co | 02/20/2020 |
| DOB NOW | Supported Scaffold | Signed-off | Ceprine Construction | 08/12/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | Ceprine Construction | 02/25/2019 |
| BIS | OT | ISSUED | Cerina General Contracting | 09/19/2023 |
| BIS | OT | ISSUED | Cerina General Contracting | 09/16/2022 |
| BIS | OT | ISSUED | Cerina General Contracting | 09/20/2021 |
| BIS | OT | ISSUED | Cerina General Contracting | 09/22/2020 |
| BIS | OT | ISSUED | C C Controlled Combustion | 09/09/2020 |
| BIS | OT | ISSUED | Kilroy Architectural Wind | 01/16/2020 |
| BIS | OT | ISSUED | Cerina General Contracting | 09/23/2019 |
| BIS | PL | ISSUED | Pace Plumbing | 11/01/2017 |
| BIS | OT | ISSUED | Structure Tone | 10/25/2017 |
| BIS | SP | ISSUED | Full Capacity Fire | 08/06/2012 |
| BIS | PL | ISSUED | Maxwell Plumbing Mechanical | 06/19/2012 |
| BIS | BL | ISSUED | Maxwell Plumbing Mechanical | 06/19/2012 |
| BIS | PL | ISSUED | Paramount Plumbing Co of NY.i | 06/06/2012 |
| BIS | OT | ISSUED | Ics Builders | 06/01/2012 |
| BIS | OT | ISSUED | Altpower | 10/17/2011 |
| BIS | PL | ISSUED | Maxwell Plumbing Mechanical | 05/25/2011 |
| BIS | BL | ISSUED | Maxwell Plumbing Mechanical | 05/25/2011 |
| BIS | OT | ISSUED | Ics Builders | 05/10/2011 |
| BIS | OT | ISSUED | Ics Builders | 04/27/2011 |
| BIS | PL | ISSUED | Paramount Plumbing Co of NY.i | 12/06/2010 |
| BIS | OT | ISSUED | JT Magen & Company | 05/25/2010 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/31/2023 | Complete | The Metro Group Electric | General Wiring |
| 11/06/2019 | Complete | Kraft Electric | — |
| 02/22/2019 | Complete | V. Vass Electric | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/16/2021 | Final | ANTHONY UGBEBOR | progress |
| 04/16/2021 | Concrete - Cast-In-Place | ANTHONY UGBEBOR | special |
| 04/16/2021 | Structural Stability – Alterations of existing buildings | ANTHONY UGBEBOR | special |
| 04/16/2021 | Structural Steel - Details | ANTHONY UGBEBOR | special |
| 04/16/2021 | Structural Steel - Welding | ANTHONY UGBEBOR | special |
| 11/17/2020 | Maintenance information | Robert Germain Jr. | energy_progress |
| 11/17/2020 | HVAC and service water heating system controls | Robert Germain Jr. | energy_progress |
| 11/17/2020 | HVAC and service water heating equipment | Robert Germain Jr. | energy_progress |
| 11/17/2020 | Fire-Resistant Penetrations and Joints | Robert Germain Jr. | special |