| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/07/2026 | Signed-off | LTI CONSTRUCTION CORP | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric SUZ-AA18NL 18,000 BTU · Condensing Unit ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/07/2026 | Signed-off | J&M PLBG OF WESTCHESTER I | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/24/2026 | Complete | RIGHT VOLTAGE ELECTRIC CO | — |
| 04/23/2026 | Complete | RIGHT VOLTAGE ELECTRIC CO | — |
| 12/02/2025 | Permit Issued | CENTENNIAL ELEVATOR INDUS | General Wiring |
| 09/24/2024 | Complete | ACCURATE ELEC'L CONTR'S C | General Wiring |
| 12/07/2023 | Permit Issued | CENTENNIAL ELEVATOR INDUS | General Wiring |
| 06/07/2023 | Complete | RICHARD NEU | — |
| 03/03/2023 | Complete | MRD ELEC'L SERVICES, INC | General Wiring |
| 12/22/2022 | Permit Issued | SAFETECH ELECL CONTNG COR | General Wiring |
| 10/24/2022 | Permit Issued | CENTENNIAL ELEVATOR INDUS | General Wiring |
| 06/22/2022 | Complete | BIGMAN BROS., INC. | Lighting |
| 04/02/2022 | Complete | CENTENNIAL ELEVATOR INDUS | General Wiring |
| 02/21/2022 | Complete | COGEN ELEC'L SERVICES,INC | General Wiring |
| 01/26/2022 | Complete | COGEN ELEC'L SERVICES,INC | — |
| 07/19/2021 | Complete | LIMONGELLI ELECTRIC CORP | General Wiring |
| 09/15/2020 | Complete | NY ELECT MAINT & DATA COR | General Wiring, Lighting |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/29/2025 | Signed-off | LEMX CORP | Sidewalk Shed |
| 02/25/2025 | Permit Issued | PHOENIX SUTTON STR INC | Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/25/2025 | Signed-off | PHOENIX SUTTON STR, INC | Suspended Scaffold (SC) |
| Owner | Filings | Most Recent |
|---|---|---|
| GFP REAL ESTATE | 309 | 09/13/2026 |
| J AMP G CONSTRUCTION SRVCS | 12 | 07/08/2026 |
| WEILL CORNELL MEDICAL COLLEGE | 17 | 07/08/2026 |
| LEMX | 15 | 07/08/2026 |
| J & G CONSTRUCTION SVCS | 1 | 03/22/2026 |
| SUMMIT DEVELOPMENT | 3 | 03/22/2026 |
| 40 WORTH ASSOCIATES | 24 | 03/22/2026 |
| SCALPEL CONSTRUCTION | 2 | 03/22/2026 |
| LITTLE 40 WORTH ASSOCIATE | 1 | 03/22/2026 |
| NEWMARK COMPANY REAL ESTATE IN | 61 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| MICHAEL G. FAHEY ARCHITECT P.C. | 6 | 08/07/2026 |
| SURFACE DESIGN | 4 | 06/18/2026 |
| CAMERON ENGINEERING | 1 | 06/17/2026 |
| GENSLER | 10 | 12/09/2025 |
| MSM ENGINEERING SERVICES, PLLC | 3 | 04/29/2025 |
| RIGID STRUCTURAL DESIGN, LLC | 5 | 02/25/2025 |
| ROBERT DERECTOR ASSOCIATES | 19 | 09/19/2024 |
| METHOD ARCHITECTS PLLC | 1 | 09/19/2024 |
| TWIG NJ ENGINEERS | 4 | 08/15/2024 |
| LILKER ASSOCIATES CONSULTING ENGINE | 8 | 03/08/2024 |
| WALTER T. GORMAN, P.E., P.C. | 3 | 03/02/2023 |
| SARGENTI ARCHITECTS | 1 | 02/17/2023 |
| MONTROY ARCHITECTURE PLLC | 2 | 01/11/2023 |
| GILSANZ MURRAY STEFICEK LLP | 3 | 01/26/2022 |
| POLISE CONSULTING ENGINEERS DPC | 4 | 10/07/2021 |
| MATIZ ARCHITECTURE AND DESIGN | 2 | 05/21/2021 |
| AUTOMATED DESIGN ENGINEERING, PLLC | 2 | 04/27/2021 |
| DAVI ARCHITECTURE, PC | 1 | 04/13/2021 |
| BAM ARCHITECTURE STUDIO, DPC | 8 | 12/17/2018 |
| HAIDER ENGINEERING, P.E. | 2 | 02/28/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| WALTER T GORMAN PE | 104 | 03/21/2026 |
| Rigid Structural Design, LLC | 10 | 03/21/2026 |
| MUNICIPAL BUILDING CONSULTANTS | 3 | 03/21/2026 |
| HAIDER ENGINEERING, P.E. | 2 | 03/21/2026 |
| BMB BUILDING CONSULTING | 16 | 03/21/2026 |
| MUNICIPAL EXPEDITING | 8 | 03/21/2026 |
| PEROTTO CONSULTING MANAGEMENT | 2 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 1 | 03/21/2026 |
| HAIDER ENGINEERING P E | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| LEMX CORP | General Contractor | 13 | 07/08/2026 |
| A.W. & S. CONSTRUCTION CO | General Contractor | 12 | 07/08/2026 |
| SPK/LEWIS CONSTRUCTION LL | General Contractor | 11 | 07/08/2026 |
| ELYSIUM CONSTRUCTION INC | General Contractor | 10 | 07/08/2026 |
| PREMIER SANITATION LLC | General Contractor | 10 | 07/08/2026 |
| J & G CONSTRUCTION SVCS | General Contractor | 9 | 07/08/2026 |
| ACTIVE SIGNS | Scaffold | 8 | 07/08/2026 |
| J.A. JENNINGS, INC | General Contractor | 8 | 07/08/2026 |
| LTI CONSTRUCTION CORP | General Contractor | 6 | 07/08/2026 |
| DLS MECHANICAL CORP | General Contractor | 4 | 04/09/2026 |
| PSI PARTNERS, LLC | Fire Protection | 4 | 07/08/2026 |
| A PLUS PLUMBING CORP | Plumbing | 3 | 07/08/2026 |
| AGGRESSIVE FIRE PROT LLC | Fire Protection | 3 | 07/08/2026 |
| COOL BREEZE AIR CON INC | General Contractor | 2 | 03/21/2026 |
| FREDERICK LEE | Electrical | 2 | 03/21/2026 |
| ADVANCED PLBG, MECH & SPR | Fire Protection | 2 | 07/08/2026 |
| DENKO MECHANICAL INC | Fire Protection | 2 | 07/08/2026 |
| J&M PLBG OF WESTCHESTER I | Fire Protection | 2 | 07/08/2026 |
| WARD PIPING COMPANY INC | Fire Protection | 2 | 07/08/2026 |
| PHOENIX SUTTON STR INC | General Contractor | 2 | 03/21/2026 |
| T.PERICIC CONSTRUCTION* | General Contractor | 2 | 03/21/2026 |
| A&A PLUMBING CORP | Plumbing | 2 | 07/08/2026 |
| M&T PLBG AND HTG CO., INC | Plumbing | 2 | 07/08/2026 |
| ROBERT SALINGER | Electrical | 1 | 03/21/2026 |
| RADOS MILOJKOVIC | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| RYAN SPECIAL ENGINEERING | 2018 | 9 | 08/07/2026 |
| SURFACE DESIGN PROFESSION | 3968 | 4 | 06/18/2026 |
| WALTER T. GORMAN, P.E., P | 268 | 24 | 06/17/2026 |
| ALAN MARGOLIN & ASSOC | 423 | 19 | 12/09/2025 |
| URBAN INTEGRATIONS LLC | 7993 | 3 | 02/25/2025 |
| KZ ENGINEERING, P.C. | 4665 | 1 | 03/21/2024 |
| SKYLINE ENGINEERING, PLLC | 267 | 8 | 07/14/2023 |
| AUTOMATED DESIGN CONSULTA | 895 | 2 | 04/27/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Suspended Scaffold | Signed-off | PHOENIX SUTTON STR, INC | 08/28/2026 |
| DOB NOW | Suspended Scaffold | Signed-off | PHOENIX SUTTON STR, INC | 08/05/2026 |
| DOB NOW | Sidewalk Shed | Signed-off | LEMX CORP | 06/02/2026 |
| DOB NOW | Sprinklers | Signed-off | J&M PLBG OF WESTCHESTER I | 04/21/2026 |
| DOB NOW | General Construction | Signed-off | LTI CONSTRUCTION CORP | 04/13/2026 |
| DOB NOW | Mechanical Systems | Signed-off | ECONO AIR HEATING/COOLING | 04/13/2026 |
| DOB NOW | General Construction | Permit Issued | LEMX CORP | 08/01/2025 |
| DOB NOW | Suspended Scaffold | Signed-off | PHOENIX SUTTON STR, INC | 08/01/2025 |
| DOB NOW | Suspended Scaffold | Signed-off | PHOENIX SUTTON STR, INC | 07/31/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | LEMX CORP | 06/02/2025 |
| DOB NOW | General Construction | Signed-off | SPK/LEWIS CONSTRUCTION LL | 11/22/2024 |
| DOB NOW | General Construction | Signed-off | SPK/LEWIS CONSTRUCTION LL | 11/13/2024 |
| DOB NOW | Mechanical Systems | Signed-off | SPK/LEWIS CONSTRUCTION LL | 11/13/2024 |
| DOB NOW | Mechanical Systems | Signed-off | DLS MECHANICAL CORP | 10/01/2024 |
| DOB NOW | Plumbing | Signed-off | ABCO-PEERLESS SPRKLR CORP | 09/26/2024 |
| DOB NOW | Plumbing | Signed-off | LAB PLBG & HTG CO INC | 09/24/2024 |
| DOB NOW | Supported Scaffold | Permit Issued | PHOENIX SUTTON STR INC | 09/23/2024 |
| DOB NOW | General Construction | Signed-off | SPK/LEWIS CONSTRUCTION LL | 09/23/2024 |
| DOB NOW | Mechanical Systems | Signed-off | SPK/LEWIS CONSTRUCTION LL | 09/20/2024 |
| DOB NOW | Mechanical Systems | Signed-off | LTI CONSTRUCTION CORP | 08/17/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | PHOENIX SUTTON STR, INC | 07/22/2024 |
| DOB NOW | General Construction | Permit Issued | LEMX CORP | 07/09/2024 |
| DOB NOW | Sprinklers | Signed-off | J&M PLBG OF WESTCHESTER I | 06/13/2024 |
| DOB NOW | General Construction | Signed-off | LTI CONSTRUCTION CORP | 06/11/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | LEMX CORP | 06/05/2024 |
| DOB NOW | Sprinklers | Signed-off | DEEM PLUMBING INC | 04/19/2024 |
| DOB NOW | Plumbing | Signed-off | ADVANCED PLBG, MECH & SPR | 04/12/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | PHOENIX SUTTON STR, INC | 04/02/2024 |
| DOB NOW | General Construction | Signed-off | WHITESTAR CONSLT. & CONT | 03/19/2024 |
| DOB NOW | General Construction | Permit Issued | LEMX CORP | 06/30/2023 |
| DOB NOW | Plumbing | Signed-off | A&A PLUMBING CORP | 06/28/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | LEMX CORP | 06/07/2023 |
| DOB NOW | General Construction | Signed-off | A.W. & S. CONSTRUCTION CO | 05/08/2023 |
| DOB NOW | Standpipe | Signed-off | A PLUS PLUMBING CORP | 04/17/2023 |
| DOB NOW | General Construction | Signed-off | A.W. & S. CONSTRUCTION CO | 03/29/2023 |
| DOB NOW | General Construction | Permit Issued | LTI CONSTRUCTION CORP | 02/24/2023 |
| DOB NOW | Plumbing | Signed-off | MORA FIRE PROTECTION LLC | 02/08/2023 |
| DOB NOW | Sprinklers | Signed-off | MORA FIRE PROTECTION LLC | 02/08/2023 |
| DOB NOW | Plumbing | Signed-off | S. TIEGER PLBG. CO., INC | 01/24/2023 |
| DOB NOW | Sprinklers | Signed-off | A&A PLUMBING CORP | 01/23/2023 |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/14/2026 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 03/31/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/14/2025 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 01/22/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/22/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/14/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/19/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/19/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/04/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/29/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/28/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/02/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/27/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/07/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/17/2024 | Certified Sprinkler (PL)-SP-Fixtures (PL)-Finish | Certified | View ↗ |
| 05/17/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/13/2024 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 05/01/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/01/2024 | Certified Sprinkler (PL)-Sprinkler-Hydro | Certified | View ↗ |
| 02/02/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/02/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/04/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/04/2023 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 11/08/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 11/08/2023 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/07/2026 | Heating Systems | William Ryan | special |
| 08/07/2026 | Post-installed Anchors | William Ryan | special |
| 08/07/2026 | Final | William Ryan | progress |
| 08/07/2026 | Sprinkler Systems | William Ryan | special |
| 08/07/2026 | Post-installed Anchors | William Ryan | special |
| 08/07/2026 | Maintenance information | William Ryan | energy_progress |
| 08/07/2026 | HVAC-R and service water piping design and insulation | William Ryan | energy_progress |
| 08/07/2026 | Mechanical Systems | William Ryan | special |
| 08/07/2026 | HVAC-R and service water heating system controls | William Ryan | energy_progress |
| 08/07/2026 | Fire-Resistant Penetrations and Joints | William Ryan | special |
| 06/30/2026 | Post-installed Anchors | William Ryan | special |
| 06/30/2026 | HVAC-R and service water heating system controls | William Ryan | energy_progress |
| 06/30/2026 | HVAC-R and service water piping design and insulation | William Ryan | energy_progress |
| 06/30/2026 | Fire-Resistant Penetrations and Joints | William Ryan | special |
| 06/30/2026 | Heating Systems | William Ryan | special |
| 06/30/2026 | Mechanical Systems | William Ryan | special |
| 06/30/2026 | Maintenance information | William Ryan | energy_progress |
| 06/30/2026 | Final | William Ryan | progress |
| 06/25/2026 | Final | Benson Gillespie | progress |
| 06/25/2026 | Energy Code Compliance Inspections | Benson Gillespie | progress |
| 06/25/2026 | Air barrier - visual inspection | Benson Gillespie | energy_progress |
| 06/25/2026 | Masonry | MOLLY FORR | special |
| 06/25/2026 | Tenant Protection Plan Compliance | Walter Gorman | special |
| 03/09/2026 | Fire-Resistant Penetrations and Joints | William Ryan | special |
| 02/27/2026 | Final | William Ryan | progress |