| Owner | Filings | Most Recent |
|---|---|---|
| NYC ECONOMIC DEVELOPMENT CORP | 132 | 09/26/2026 |
| NEW YORK CITY ECONOMIC DEVELOPMENT | 27 | 07/08/2026 |
| CONSTRUCTION SVS CON NY | 5 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| A&M CONSULTING | 29 | 06/04/2025 |
| REILLY TARANTINO ENGINEERING | 5 | 09/20/2024 |
| ALEXANDER BADALAMENTI | 7 | 09/17/2024 |
| KEY CIVIL ENGINEERING PC | 4 | 08/09/2022 |
| ARQUITECTURA VARELA | 3 | 02/25/2022 |
| THOMAS D REILLY P.E. | 1 | 06/02/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| CONVERSANO ASSOCIATES, INC. | 92 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ANDRON CONSTRUCTION CORP | General Contractor | 12 | 07/08/2026 |
| CMA PLUMBING & HEATING IN | Fire Protection | 10 | 07/08/2026 |
| AURORA CONTRACTORS INC | General Contractor | 10 | 07/08/2026 |
| V. C. VITANZA SONS INC | Plumbing | 6 | 07/08/2026 |
| BEDROCK PLBG. & HTG., INC | Plumbing | 5 | 07/08/2026 |
| PAR FIRE PROTECTION LLC | Fire Protection | 4 | 07/08/2026 |
| MPC PLUMBING & HEATING INC | Plumbing | 3 | 07/08/2026 |
| EASTERN EXCAVATION INC | General Contractor | 3 | 03/21/2026 |
| AURORA CONTRACTORS INC | General Contractor | 2 | 07/08/2026 |
| TARGET MECHANICAL INC | General Contractor | 1 | 07/08/2026 |
| PAR PLUMBING CO., INC | Plumbing | 1 | 07/08/2026 |
| LAWRENCE J. LEVINE | Fire Protection | 1 | 03/21/2026 |
| C.M. RICHEY ELEC'L CONTR | Electrical | 1 | 03/22/2026 |
| ERIC ROJAS | Electrical | 1 | 03/21/2026 |
| EMPIRE STATE ELEC MAINT & | Electrical | 1 | 03/22/2026 |
| CONSTRUCTION SVS CON NY | General Contractor | 1 | 07/08/2026 |
| TALISEN CONSTRUCTION CORP | General Contractor | 1 | 09/26/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ETI CONSULTANTS LLC | 7694 | 42 | 06/04/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | TALISEN CONSTRUCTION CORP | 09/25/2026 |
| DOB NOW | Sprinklers | Signed-off | BEDROCK PLBG. & HTG., INC | 10/30/2024 |
| DOB NOW | General Construction | Signed-off | ANDRON CONSTRUCTION CORP | 10/03/2024 |
| DOB NOW | Mechanical Systems | Signed-off | ANDRON CONSTRUCTION CORP | 07/16/2024 |
| DOB NOW | Sprinklers | Signed-off | LAWRENCE J. LEVINE | 06/28/2024 |
| DOB NOW | Sprinklers | Signed-off | LAWRENCE J. LEVINE | 06/28/2024 |
| DOB NOW | Plumbing | Signed-off | LAWRENCE J. LEVINE | 06/27/2024 |
| DOB NOW | Boiler Equipment | Signed-off | MPC PLUMBING & HEATING IN | 01/17/2024 |
| DOB NOW | General Construction | Signed-off | ANDRON CONSTRUCTION CORP | 01/09/2024 |
| DOB NOW | Structural | Signed-off | ANDRON CONSTRUCTION CORP | 01/08/2024 |
| DOB NOW | Plumbing | Signed-off | BEDROCK PLBG. & HTG., INC | 09/08/2023 |
| DOB NOW | Mechanical Systems | Signed-off | ANDRON CONSTRUCTION CORP | 06/30/2023 |
| DOB NOW | Sprinklers | Signed-off | LAWRENCE J. LEVINE | 05/03/2023 |
| DOB NOW | Sprinklers | Signed-off | CMA PLUMBING & HEATING IN | 03/23/2023 |
| DOB NOW | Construction Fence | Signed-off | YABOO FENCE CO INC | 03/23/2023 |
| DOB NOW | Boiler Equipment | Signed-off | MPC PLUMBING & HEATING IN | 02/13/2023 |
| DOB NOW | Plumbing | Signed-off | PAR PLUMBING CO., INC | 02/09/2023 |
| DOB NOW | Structural | Signed-off | ANDRON CONSTRUCTION CORP | 01/26/2023 |
| DOB NOW | General Construction | Signed-off | ANDRON CONSTRUCTION CORP | 01/25/2023 |
| DOB NOW | Plumbing | Signed-off | V. C. VITANZA SONS INC | 12/28/2022 |
| DOB NOW | Plumbing | Signed-off | V. C. VITANZA SONS INC | 09/26/2022 |
| DOB NOW | Construction Fence | Signed-off | YABOO FENCE CO INC | 09/21/2022 |
| DOB NOW | Standpipe | Signed-off | BEDROCK PLBG. & HTG., INC | 09/14/2022 |
| DOB NOW | Curb Cut | Signed-off | EASTERN EXCAVATION INC | 08/03/2022 |
| DOB NOW | Plumbing | Signed-off | CMA PLUMBING & HEATING IN | 07/19/2022 |
| DOB NOW | Standpipe | Signed-off | CMA PLUMBING & HEATING IN | 07/19/2022 |
| DOB NOW | Sprinklers | Signed-off | CMA PLUMBING & HEATING IN | 07/19/2022 |
| DOB NOW | Boiler Equipment | Signed-off | JACK PICCINI, INC | 06/22/2022 |
| DOB NOW | Mechanical Systems | Signed-off | TARGET MECHANICAL INC | 04/15/2022 |
| DOB NOW | Standpipe | Signed-off | CMA PLUMBING & HEATING IN | 04/14/2022 |
| DOB NOW | Plumbing | Signed-off | CMA PLUMBING & HEATING IN | 04/14/2022 |
| DOB NOW | Sprinklers | Signed-off | CMA PLUMBING & HEATING IN | 04/14/2022 |
| DOB NOW | Boiler Equipment | Signed-off | MPC PLUMBING & HEATING IN | 03/09/2022 |
| DOB NOW | Construction Fence | Signed-off | YABOO FENCE CO INC | 03/09/2022 |
| DOB NOW | Plumbing | Signed-off | V. C. VITANZA SONS INC | 01/26/2022 |
| DOB NOW | Supported Scaffold | Signed-off | CONSTRUCTION SVS CON NY | 01/26/2022 |
| DOB NOW | Sprinklers | Signed-off | CMA PLUMBING & HEATING IN | 01/24/2022 |
| DOB NOW | Construction Fence | Signed-off | YABOO FENCE CO INC | 01/11/2022 |
| DOB NOW | Standpipe | Signed-off | CMA PLUMBING & HEATING IN | 12/17/2021 |
| DOB NOW | Structural | Signed-off | AURORA CONTRACTORS INC | 12/06/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/13/2026 | Permit Issued | EMPIRE STATE ELEC MAINT & | General Wiring |
| 04/15/2026 | Complete | ECNY ELEC'L CONTR'S, INC | — |
| 03/16/2026 | Complete | HORSEPOWER ELECTRIC.& | General Wiring |
| 08/25/2025 | Cancelled | EMPIRE STATE ELEC MAINT & | General Wiring |
| 01/16/2025 | Complete | CORE ELEC & COMMUNICATION | General Wiring |
| 02/19/2021 | Complete | HORSEPOWER ELECTRIC.& | 1 meters, 1 new_meters |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/26/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/18/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/21/2024 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 10/01/2024 | Fail-Final SD - Fire Pump | Fail | View ↗ |
| 08/21/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/14/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/08/2024 | Fail-Final SD - Fire Pump | Fail | View ↗ |
| 11/20/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 11/06/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 09/18/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/11/2023 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 07/06/2023 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 06/30/2023 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 04/19/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/20/2023 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 03/17/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 09/06/2022 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 02/08/2022 | Pass-Final PL - Underground | Pass | View ↗ |
| 01/31/2022 | Pass-Final PL - Underground | Pass | View ↗ |
| 01/20/2022 | Pass-Final PL - Underground | Pass | View ↗ |
| 01/12/2022 | Pass-Final PL - Underground | Pass | View ↗ |
| 11/18/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 11/10/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 10/13/2021 | Pass-Final PL - Underground | Pass | View ↗ |
| 09/22/2021 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/29/2025 | Fire-Resistant Penetrations and Joints | ANTHONY MUSUMECI | special |
| 05/29/2025 | Sprinkler Systems | ANTHONY MUSUMECI | special |
| 05/29/2025 | Standpipe Systems | ANTHONY MUSUMECI | special |
| 01/17/2025 | HVAC-R and service water heating system controls | ANTHONY MUSUMECI | energy_progress |
| 01/17/2025 | Fire-Resistant Penetrations and Joints | ANTHONY MUSUMECI | special |
| 01/17/2025 | Final | ANTHONY MUSUMECI | progress |
| 01/17/2025 | Maintenance information | ANTHONY MUSUMECI | energy_progress |
| 01/17/2025 | HVAC-R and service water heating equipment | ANTHONY MUSUMECI | energy_progress |
| 01/17/2025 | HVAC-R and service water piping design and insulation | ANTHONY MUSUMECI | energy_progress |
| 01/17/2025 | Mechanical Systems | ANTHONY MUSUMECI | special |
| 01/17/2025 | Heating Systems | ANTHONY MUSUMECI | special |
| 01/17/2025 | Smoke Control Systems Testing | ANTHONY MUSUMECI | special |
| 01/07/2025 | Final | ANTHONY MUSUMECI | progress |
| 01/07/2025 | HVAC-R and service water heating equipment | ANTHONY MUSUMECI | energy_progress |
| 01/07/2025 | HVAC-R and service water piping design and insulation | ANTHONY MUSUMECI | energy_progress |
| 01/07/2025 | HVAC-R and service water heating system controls | ANTHONY MUSUMECI | energy_progress |
| 01/07/2025 | Maintenance information | ANTHONY MUSUMECI | energy_progress |
| 01/07/2025 | Mechanical Systems | ANTHONY MUSUMECI | special |
| 01/07/2025 | Heating Systems | ANTHONY MUSUMECI | special |
| 01/07/2025 | Fire-Resistant Penetrations and Joints | ANTHONY MUSUMECI | special |
| 01/07/2025 | Smoke Control Systems Testing | ANTHONY MUSUMECI | special |
| 12/18/2024 | Smoke Control Systems Testing | ANTHONY MUSUMECI | special |
| 12/18/2024 | Maintenance information | ANTHONY MUSUMECI | energy_progress |
| 11/08/2024 | Shutoff dampers | ANTHONY MUSUMECI | energy_progress |
| 11/08/2024 | Emergency and Standby Power Systems (Generator) | ANTHONY MUSUMECI | special |