| Owner | Filings | Most Recent |
|---|---|---|
| NKG CORP 1 | 5 | 03/22/2026 |
| NKG | 7 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| BECALL ENGINEERING SERVICES INC. | 2 | 01/29/2025 |
| BADALY ARCHITECTS | 3 | 09/25/2024 |
| BADALY ENGINEERING PLLC | 1 | 10/07/2020 |
| MAX DISLA ARCHITECT | 1 | 03/18/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| BADALY ENGINEERING | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NKG CORP | General Contractor | 7 | 07/08/2026 |
| INFINITI ESC PLUMBING COR | Plumbing | 5 | 07/08/2026 |
| MAMC CONSULTING REPS LLC | General Contractor | 3 | 03/21/2026 |
| VILLAGE P & H NY INC | Fire Protection | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BADALY ARCHITECT PLLC | 7137 | 4 | 09/25/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Signed-off | VILLAGE P & H NY INC | 10/25/2024 |
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 04/12/2024 |
| DOB NOW | Mechanical Systems | Signed-off | MAMC CONSULTING REPS LLC | 12/15/2023 |
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 10/25/2022 |
| DOB NOW | Sprinklers | Signed-off | VILLAGE P & H NY INC | 12/13/2021 |
| DOB NOW | Construction Fence | Signed-off | NKG CORP | 10/01/2021 |
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 05/28/2021 |
| DOB NOW | Construction Fence | Signed-off | NKG CORP | 04/21/2021 |
| DOB NOW | Construction Fence | Signed-off | NKG CORP | 11/20/2020 |
| BIS | — | ISSUED | AUGUST CONSTRUCTION GROUP | 10/25/2024 |
| BIS | — | ISSUED | AUGUST CONSTRUCTION GROUP | 11/02/2023 |
| BIS | OT | ISSUED | KAMTECH RESTORATION CORP | 02/24/2023 |
| BIS | — | ISSUED | AUGUST CONSTRUCTION GROUP | 08/11/2022 |
| BIS | — | ISSUED | AUGUST CONSTRUCTION GROUP | 04/12/2022 |
| BIS | — | ISSUED | NKG CORP | 12/02/2021 |
| BIS | — | ISSUED | NKG CORP | 09/29/2021 |
| BIS | — | ISSUED | NKG CORP | 06/17/2021 |
| BIS | — | ISSUED | NKG CORP | 12/11/2020 |
| BIS | — | ISSUED | NKG CORP | 12/04/2020 |
| BIS | — | ISSUED | NKG CORP | 11/23/2020 |
| BIS | OT | ISSUED | BLACK HAMMER CONSTRUCTION | 06/24/2020 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/18/2024 | Complete | C & A ELECTRICAL CORP | General Wiring |
| 03/28/2023 | Complete | BERGER QUALITY ELEC'L CON | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/02/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/01/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/23/2021 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 12/23/2021 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 12/23/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/26/2024 | Sprinkler Systems | SHAHIN BADALY | special |
| 09/26/2024 | Fire-Resistant Penetrations and Joints | SHAHIN BADALY | special |
| 09/24/2024 | Fire-Resistant Penetrations and Joints | SHAHIN BADALY | special |
| 09/24/2024 | Sprinkler Systems | SHAHIN BADALY | special |
| 07/22/2024 | Energy Code Compliance Inspections | SHAHIN BADALY | progress |
| 07/22/2024 | Fire-Resistance Rated Construction | SHAHIN BADALY | progress |
| 07/22/2024 | Fire-Resistant Penetrations and Joints | SHAHIN BADALY | special |
| 07/22/2024 | Sprinkler Systems | SHAHIN BADALY | special |
| 10/07/2020 | Mechanical Systems | SHAHIN BADALY | special |
| 10/07/2020 | Final | SHAHIN BADALY | progress |
| 10/07/2020 | HVAC and service water heating equipment | SHAHIN BADALY | energy_progress |
| 10/07/2020 | HVAC insulation and sealing | SHAHIN BADALY | energy_progress |
| 10/07/2020 | HVAC and service water heating system controls | SHAHIN BADALY | energy_progress |