Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofUnder Construction8p · 1 filing · 20 docs
AtticUnder Construction6p · 1 filing · 20 docs
Floor 2Under Construction6p · 1 filing · 20 docs
Floor 1Under Construction6p · 1 filing · 20 docs
CellarUnder Construction7p · 1 filing · 20 docs
Site & exteriorUnder Construction27p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Solhjou Engineering106/19/2026
Sion Consulting Engineering406/09/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Sion Consulting Engineering203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
J&J DesignsGeneral Contractor209/18/2026
J&J DesignsScaffold209/18/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Sion Consulting Engineering1108102/04/2026
Building Lifecycle
All (78)Filed (4)Permit Issued (4)Objection (40)Special Inspection (30)
09/17/2026
Permit issued — Foundation
X01331194-I1-GC-CX
09/17/2026
Permit issued — Construction Fence
X01331194-S4-FN
08/17/2026
Objection resolved — Addressed
08/17/2026
Objection resolved — Addressed
08/13/2026
Objection raised — Other
08/13/2026
Objection raised — Other
07/28/2026
Permit issued — Foundation
X01331194-I1-GC-CX
07/28/2026
Permit issued — Construction Fence
X01331194-S4-FN
07/21/2026
Objection resolved — Addressed
07/21/2026
Objection resolved — Addressed
07/21/2026
Objection resolved — Addressed
07/17/2026
Objection resolved — Addressed
07/13/2026
Objection raised — Fire_Protection
07/13/2026
Objection raised — Fire_Protection
07/13/2026
Objection raised — Scope
07/13/2026
Objection raised — Other
06/19/2026
Filed — New Building
SPRINKLER APPLICATION IN CONJUNCTION WITH GCJOB # X01331194-I1 AND PLUMBING SYSTEMS WORK INCLUDES INSTALLATION OF NEW SPRINKLER SYSTEM, PIPING VALVES BACKFLOW PREVENTER AND RELATED EQUIPMENT FOR PROPOSED NEW TWO STORY AND TWO FAMILY BUILDING.
X01331194-S2
06/15/2026
Special inspection requirement — Sprinkler Systems
06/09/2026
Filed — New Building
SPRINKLER APPLICATION IN CONJUNCTION WITH GCJOB # X01331194-I1 AND PLUMBING SYSTEMS WORK INCLUDES INSTALLATION OF NEW SPRINKLER SYSTEM, PIPING VALVES BACKFLOW PREVENTER AND RELATED EQUIPMENT FOR PROPOSED NEW TWO STORY AND TWO FAMILY BUILDING.
X01331194-S1
05/18/2026
Objection resolved — Resolved
05/18/2026
Objection resolved — Resolved
05/18/2026
Objection resolved — Resolved
05/18/2026
Objection resolved — Resolved
05/18/2026
Objection resolved — Resolved
05/11/2026
Filed — New Building
SPRINKLER APPLICATION IN CONJUNCTION WITH GCJOB # X01331194-I1 AND PLUMBING SYSTEMS WORK INCLUDES INSTALLATION OF NEW SPRINKLER SYSTEM, PIPING VALVES BACKFLOW PREVENTER AND RELATED EQUIPMENT FOR PROPOSED NEW TWO STORY AND TWO FAMILY BUILDING.
X01331194-S4
05/11/2026
Objection resolved — Addressed
05/11/2026
Objection resolved — Addressed
05/11/2026
Objection resolved — Addressed
05/11/2026
Objection resolved — Addressed
05/11/2026
Objection resolved — Addressed
05/11/2026
Objection resolved — Addressed
05/11/2026
Objection resolved — Addressed
05/11/2026
Objection resolved — Addressed
05/11/2026
Objection resolved — Addressed
03/16/2026
Special inspection requirement — HVAC-R and service water heating equipment
03/16/2026
Special inspection requirement — HVAC-R and service water heating system controls
03/16/2026
Special inspection requirement — Permanent certificate
03/16/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
03/16/2026
Special inspection requirement — Maintenance information
03/16/2026
Special inspection requirement — Energy Code Compliance Inspections
03/16/2026
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
03/16/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
03/16/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
02/20/2026
Objection raised — Admin
02/20/2026
Objection raised — Admin
02/20/2026
Objection raised — Zoning
02/20/2026
Objection raised — Fire_Protection
02/20/2026
Objection raised — Zoning
02/20/2026
Objection raised — Plumbing
02/20/2026
Objection raised — Energy
02/20/2026
Objection raised — Scope
02/20/2026
Objection raised — Zoning
02/20/2026
Objection raised — Zoning
02/20/2026
Objection raised — Scope
02/20/2026
Objection raised — Structural
02/20/2026
Objection raised — Structural
02/20/2026
Objection raised — Energy
02/04/2026
Filed — New Building
SPRINKLER APPLICATION IN CONJUNCTION WITH GCJOB # X01331194-I1 AND PLUMBING SYSTEMS WORK INCLUDES INSTALLATION OF NEW SPRINKLER SYSTEM, PIPING VALVES BACKFLOW PREVENTER AND RELATED EQUIPMENT FOR PROPOSED NEW TWO STORY AND TWO FAMILY BUILDING.
X01331194-I1
01/26/2026
Special inspection requirement — Structural Cold-Formed Steel
sion hourizadeh
12/09/2025
Special inspection requirement — Energy Code Compliance Inspections
sion hourizadeh
Latest 60 of 78 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWFoundationPermit IssuedJ&J Designs09/17/2026
DOB NOWConstruction FencePermit IssuedJ&J Designs09/17/2026
DOB NOWFoundationPermit IssuedJ&J Designs07/28/2026
DOB NOWConstruction FencePermit IssuedJ&J Designs07/28/2026
1 project · most recent 06/19/2026
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
06/19/2026Permit IssuedJ&J DesignsHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Mitsubishi Electric MXZ-SM48NAM-U1 48,000 BTU · Split System ×2
Ventilation
Delta Breeze 7114-01 50 CFM ×5
SMT150 150 CFM ×2
Clean Comfort VE30100 86 CFM · Erv ×1
VE30160 162 CFM · Erv ×1
1 project · most recent 06/19/2026
Wood
FiledStatusContractorScope
06/19/2026Permit IssuedJ&J DesignsWood
1 project · most recent 06/19/2026
Fence
FiledStatusContractorScope
06/19/2026Permit IssuedJ&J DesignsFence
▾Special Inspection Requirements (DOB NOW) — 40
DateRequirementInspectorRole
06/15/2026Sprinkler Systems—special
03/16/2026HVAC-R and service water heating equipment—energy_progress
03/16/2026HVAC-R and service water heating system controls—energy_progress
03/16/2026Permanent certificate—energy_progress
03/16/2026HVAC-R and service water piping design and insulation—energy_progress
03/16/2026Maintenance information—energy_progress
03/16/2026Energy Code Compliance Inspections—progress
03/16/2026Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities—special
03/16/2026Fire-Resistant Penetrations and Joints—special
03/16/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation—special
01/26/2026Structural Cold-Formed Steelsion hourizadehspecial
12/09/2025Energy Code Compliance Inspectionssion hourizadehprogress
12/09/2025Fire-Resistance Rated Constructionsion hourizadehprogress
12/09/2025Preliminarysion hourizadehprogress
12/09/2025Structural Wood Framesion hourizadehprogress
12/09/2025Meteringsion hourizadehenergy_progress
12/09/2025Fenestration air leakagesion hourizadehenergy_progress
12/09/2025Permanent certificatesion hourizadehenergy_progress
12/09/2025HVAC-R and service water piping design and insulationsion hourizadehenergy_progress
12/09/2025HVAC-R and service water heating system controlssion hourizadehenergy_progress
12/09/2025Ventilation and air distribution systemsion hourizadehenergy_progress
12/09/2025Fenestration and door U-factor and product ratingssion hourizadehenergy_progress
12/09/2025Fenestration areassion hourizadehenergy_progress
12/09/2025HVAC-R and service water heating equipmentsion hourizadehenergy_progress
12/09/2025Insulation placement and R valuession hourizadehenergy_progress
Latest 25 of 40.
▾Documents — 25 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/16/2026X01331194-S1Request digital key ↗
08/16/2026X01331194-S3Request digital key ↗
08/16/2026X01331194-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸Zoning, Tax Lot & Property Records3
▸DOB NOWZD1: DOB Zoning Diagram1
08/16/2026X01331194-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/16/2026X01331194-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/16/2026X01331194-I1Open ↗
▸Seals & Professional Certifications8
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/16/2026X01331194-S4Open ↗
08/16/2026X01331194-S2Open ↗
08/16/2026X01331194-S1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature2
09/07/2026X01331194-I1Open ↗
09/07/2026X01331194-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/07/2026X01331194-I1Open ↗
09/07/2026X01331194-I1Open ↗
▸Trade Schedules & Equipment1
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/16/2026X01331194-I1Open ↗
▸Safety & Tenant Protection2
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/16/2026X01331194-I1Open ↗
▸DOB NOWStreet Tree Checklist1
08/16/2026X01331194-I1Open ↗
▸Inspections & Test Reports2
▸DOB NOWTR4 Test Report and Plot Diagram1
08/16/2026X01331194-I1Open ↗
▸DOB NOWSOIL REPORT1
08/16/2026X01331194-I1Open ↗
▸Other Documents4
▸DOB NOWProperty Ownership Certification1
08/16/2026X01331194-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/16/2026X01331194-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/16/2026X01331194-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/16/2026X01331194-I1Open ↗