← Back
BuildNYC
Office only, 1 story
405 91ST STREET
BROOKLYN · Bay Ridge · BIN 3154591
💬 Discuss this project
1964Year Built
1Stories
O1Building Class
C8-2Zoning
10,080 sfGross Floor Area
2Units
0 Active ViolationsFDNY Report ↗
Office only, 1 story · Owner of record: 405 91 LLC · 7,504 sf lot · 1.34 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionEquipmentCivil
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofLenox Hill Radiology, Bay Ridge Imaging Center11p · 2 filings · 20 docs
Floor 1Lenox Hill Radiology, Bay Ridge Imaging Center28p · 3 filings · 20 docs
CellarBay Ridge Imaging Center17p · 2 filings · 20 docs
Site & exteriorAxion Management LLC2p · 2 filings · 4 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
405 91 LLC1103/21/2026
Allied Properties607/08/2026
452-87th103/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Franklyn Estrella Architect103/21/2026
Leder-Luis Building Design203/21/2026
Construction Permit Services403/21/2026
CCBS Consultants203/21/2026
KM Associates of New York103/21/2026
K & M Associates103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BT's Plumbing and HeatingPlumbing407/08/2026
Tyler ConstructionGeneral Contractor407/08/2026
Excalibur GroupGeneral Contractor207/08/2026
Vip Fire SprinklerPlumbing203/22/2026
SJ EmpireScaffold107/08/2026
DPH Plumbing & HeatingPlumbing107/08/2026
All Purpose ElectricElectrical103/22/2026
Vip Fire SprinklerFire Protection107/08/2026
Castle Electric GroupElectrical103/22/2026
Axium ConstructionGeneral Contractor107/08/2026
Empire General ContractingGeneral Contractor104/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF Services5616311/15/2025
Colombo Architectural Stu4930311/14/2025
Crosscheck Inspection Services544107/09/2025
Charles Schmitt Architect3719202/24/2020
Metric Consulting and Ins1803101/16/2020
Ans Consultants1768112/03/2019
Building Lifecycle
All (114)Filed (13)Permit Issued (10)Signed Off (10)Violation (26)Inspection (5)Objection (20)Special Inspection (30)
12/23/2025
Signed off — Alteration
Tenant fit out of existing office space to accommodate medical offices as per plans filed herewith.
B01188684-S1
12/20/2025
Special inspection requirement — HVAC-R and service water heating equipment
SHAHRIAR QUAYYUM
12/20/2025
Special inspection requirement — Mechanical Systems
SHAHRIAR QUAYYUM
12/20/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
SHAHRIAR QUAYYUM
12/20/2025
Special inspection requirement — Final
SHAHRIAR QUAYYUM
12/20/2025
Special inspection requirement — HVAC-R and service water heating system controls
SHAHRIAR QUAYYUM
12/20/2025
Special inspection requirement — Maintenance information
SHAHRIAR QUAYYUM
12/19/2025
Signed off — Alteration
Tenant fit out of existing office space to accommodate medical offices as per plans filed herewith.
B01188684-S2
12/08/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/04/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/26/2025
Signed off — Alteration
Tenant fit out of existing office space to accommodate medical offices as per plans filed herewith.
B01188684-I1
11/26/2025
Permit issued — Plumbing
B01188684-S2-PL
11/15/2025
Filed — Alteration
Tenant fit out of existing office space to accommodate medical offices as per plans filed herewith.
B01188684-P2
11/14/2025
Filed — Alteration
Tenant fit out of existing office space to accommodate medical offices as per plans filed herewith.
B01188684-S2
11/14/2025
Filed — Alteration
Tenant fit out of existing office space to accommodate medical offices as per plans filed herewith.
B01188684-P1
10/16/2025
Special inspection requirement — HVAC-R and service water heating system controls
SHAHRIAR QUAYYUM
10/16/2025
Special inspection requirement — Maintenance information
SHAHRIAR QUAYYUM
10/16/2025
Special inspection requirement — HVAC-R and service water heating equipment
SHAHRIAR QUAYYUM
10/16/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Yahaira Volquez Colombo
10/16/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
SHAHRIAR QUAYYUM
10/16/2025
Special inspection requirement — Mechanical Systems
SHAHRIAR QUAYYUM
10/16/2025
Special inspection requirement — Final
SHAHRIAR QUAYYUM
10/14/2025
Signed off — Alteration
B01242391-I1
10/02/2025
Permit issued — Mechanical Systems
B01188684-S1-MS
07/24/2025
Signed off — Alteration
MODIFICATION OF EXISTING SPRINKLER SYSTEM designed as per pipe schedule NFPA-13 2007 Section 11.2.2.3. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B00755275-I1
07/18/2025
Permit issued — General Construction
B01242391-I1-GC
07/16/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
07/09/2025
Filed — Alteration
B01242391-I1
06/27/2025
Objection resolved — Addressed
06/24/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
06/19/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
06/09/2025
Objection resolved — Addressed
06/06/2025
Objection resolved — Addressed
06/06/2025
Objection resolved — Addressed
05/09/2025
Special inspection requirement — Lighting controls
Yahaira Volquez Colombo
05/09/2025
Special inspection requirement — Metering
Yahaira Volquez Colombo
05/09/2025
Special inspection requirement — Interior lighting power
Yahaira Volquez Colombo
05/09/2025
Special inspection requirement — Energy Code Compliance Inspections
Yahaira Volquez Colombo
05/09/2025
Special inspection requirement — Final
Yahaira Volquez Colombo
05/09/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Yahaira Volquez Colombo
05/07/2025
Permit issued — Sprinklers
B00755275-I1-EW-SP
04/23/2025
Objection raised — Inspections
04/23/2025
Objection raised — Mechanical
04/23/2025
Objection raised — Scope
04/23/2025
Objection raised — Fire_Protection
04/10/2025
Filed — Alteration
Tenant fit out of existing office space to accommodate medical offices as per plans filed herewith.
B01188684-S1
03/13/2025
Permit issued — General Construction
B01188684-I1-GC
03/07/2025
Filed — Alteration
Tenant fit out of existing office space to accommodate medical offices as per plans filed herewith.
B01188684-I1
02/09/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/09/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/09/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/09/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/30/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/30/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/04/2022
Objection resolved — Addressed
10/04/2022
Objection resolved — Addressed
07/19/2022
Objection resolved — Addressed
07/08/2022
Objection resolved — Addressed
Latest 60 of 114 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offBT's Plumbing and Heating11/26/2025
DOB NOWMechanical SystemsSigned-offTyler Construction10/02/2025
DOB NOWGeneral ConstructionSigned-offEmpire General Contracting07/18/2025
DOB NOWSprinklersSigned-offVip Fire Sprinkler05/07/2025
DOB NOWGeneral ConstructionSigned-offTyler Construction03/13/2025
DOB NOWStructuralSigned-offAxium Construction02/14/2020
DOB NOWStructuralSigned-offExcalibur Group01/13/2020
DOB NOWMechanical SystemsSigned-offExcalibur Group09/24/2019
DOB NOWPlumbingSigned-offDPH Plumbing & Heating09/19/2019
DOB NOWConstruction FenceSigned-offSJ Empire01/29/2019
BISOTISSUEDAxium Construction12/24/2021
BIS—ISSUEDAxium Construction07/07/2021
BISPLISSUEDPlumbing Plumbing & Plumbing03/11/2021
BISPLISSUEDPlumbing Plumbing & Plumbing03/11/2021
BIS—ISSUEDAxium Construction07/24/2020
BISOTISSUEDAxium Construction06/26/2020
BISOTISSUEDAxium Construction06/26/2020
BIS—ISSUEDAxium Construction06/26/2020
BISMHISSUEDAxium Construction06/26/2020
BISPLISSUEDPlumbing Plumbing & Plumbing02/10/2020
BISPLISSUEDPlumbing Plumbing & Plumbing01/27/2020
BISMHISSUEDAxium Construction01/23/2020
BISSPISSUEDUniversal Fire Sprinkler01/21/2020
BISOTISSUEDSJ Empire12/31/2018
BISOTISSUEDAxium Construction07/26/2018
BISOTISSUEDAxium Construction08/25/2017
BISOTISSUEDAxium Construction07/14/2016
BISOTISSUEDAxium Construction11/12/2015
BISOTISSUEDAxium Construction08/04/2014
BISOTISSUEDAxium Construction07/05/2013
BISMHISSUEDBee Cool HVAC02/22/2002
BIS—ISSUEDPaul Signs Ins09/22/1994
BISMHISSUEDVictory Brothers04/07/1994
BISPLISSUEDWolf Plumbing & Heating12/29/1993
BIS—ISSUEDBudimex Gen Contracting12/15/1993
5 projects · most recent 04/15/2025
General Wiring
FiledStatusContractorScope
04/15/2025Permit IssuedNewland ElectricalGeneral Wiring
11/30/2022Permit IssuedAll Purpose ElectricGeneral Wiring
02/11/2020CompleteHexagon Construction & Electrical GroupGeneral Wiring
01/28/2020CompleteAll Purpose Electric3 meters, 3 new_meters
11/26/2019CompleteCastle Electric Group—
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
12/08/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/04/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/16/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
06/24/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/19/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 39
DateRequirementInspectorRole
12/20/2025HVAC-R and service water heating equipmentSHAHRIAR QUAYYUMenergy_progress
12/20/2025Mechanical SystemsSHAHRIAR QUAYYUMspecial
12/20/2025Fire-Resistant Penetrations and JointsSHAHRIAR QUAYYUMspecial
12/20/2025FinalSHAHRIAR QUAYYUMprogress
12/20/2025HVAC-R and service water heating system controlsSHAHRIAR QUAYYUMenergy_progress
12/20/2025Maintenance informationSHAHRIAR QUAYYUMenergy_progress
10/16/2025HVAC-R and service water heating system controlsSHAHRIAR QUAYYUMenergy_progress
10/16/2025Maintenance informationSHAHRIAR QUAYYUMenergy_progress
10/16/2025HVAC-R and service water heating equipmentSHAHRIAR QUAYYUMenergy_progress
10/16/2025Fire-Resistant Penetrations and JointsYahaira Volquez Colombospecial
10/16/2025Fire-Resistant Penetrations and JointsSHAHRIAR QUAYYUMspecial
10/16/2025Mechanical SystemsSHAHRIAR QUAYYUMspecial
10/16/2025FinalSHAHRIAR QUAYYUMprogress
05/09/2025Lighting controlsYahaira Volquez Colomboenergy_progress
05/09/2025MeteringYahaira Volquez Colomboenergy_progress
05/09/2025Interior lighting powerYahaira Volquez Colomboenergy_progress
05/09/2025Energy Code Compliance InspectionsYahaira Volquez Colomboprogress
05/09/2025FinalYahaira Volquez Colomboprogress
05/09/2025Fire-Resistant Penetrations and JointsYahaira Volquez Colombospecial
06/10/2022Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
06/10/2022Sprinkler SystemsFAHAD FATEHspecial
02/07/2020HVAC insulation and sealing SCOTT FERTIGenergy_progress
02/07/2020Fire-Resistant Penetrations and JointsCHARLES SCHMITTspecial
02/07/2020Mechanical SystemsCHARLES SCHMITTspecial
02/07/2020Smoke Control Systems TestingCHARLES SCHMITTspecial
Latest 25 of 39.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Lenox Hill RadiologyMedical / HealthcareFloor 1, Roof
Project B01188684 Alteration · LOC Issued · 03/07/2025
Project B00755275 Alteration · LOC Issued · 06/10/2022
Bay Ridge Imaging CenterMedical / HealthcareCellar, Floor 1, Roof
Project B00191425 Alteration · LOC Issued · 08/06/2019
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 306 on file (BIS + DOB NOW)
▸Plans & Drawings13
▸DOB NOWPlans/Sketch8
09/02/2026B00095912-I1Request digital key ↗
08/21/2026B01242391-I1Request digital key ↗
08/19/2026B01188684-I1Request digital key ↗
Showing 3 of 8 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems2
09/02/2026B00191425-I1Request digital key ↗
08/15/2026B00191425-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Structural2
09/02/2026B00191425-S2Request digital key ↗
09/02/2026B00245882-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
09/02/2026B00191425-S1Request digital key ↗
▸Applications & Permits55
▸BISPLAN / WORK APPROVAL APPLICATION36
07/23/2024321615374Open ↗
05/28/2024321996630Open ↗
05/23/2024321996630Open ↗
Showing 3 of 36 on file for this type
▸BISWORK PERMIT APPLICATION15
10/05/2020340635272Open ↗
01/27/2020340634193Open ↗
01/23/2020340634193Open ↗
Showing 3 of 15 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION3
02/29/2020321967323Open ↗
03/14/2019321762320Open ↗
10/12/2018321762320Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
03/04/2020321615374Open ↗
▸Zoning, Tax Lot & Property Records6
▸BISADDRESS: NEW HOUSE NUMBER APPROVED2
06/03/2019321615374Open ↗
02/13/2019321615374Open ↗
▸BISZONING DIAGRAM2
06/05/2019321615374Open ↗
06/05/2019321615374Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
02/13/2019321615374Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
02/13/2019321615374Open ↗
▸Seals & Professional Certifications73
▸DOB NOWProgress Inspector Seal & Signature17
09/01/2026B00191425-P1Open ↗
09/01/2026B00191425-P1Open ↗
09/01/2026B00191425-P1Open ↗
Showing 3 of 17 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION15
03/27/2020321967323Open ↗
03/27/2020321967323Open ↗
03/06/2020321967323Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature13
09/02/2026B00095912-I1Open ↗
08/21/2026B01242391-I1Open ↗
08/19/2026B01188684-P2Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature12
09/01/2026B00191425-P1Open ↗
09/01/2026B00191425-P1Open ↗
09/01/2026B00191425-P1Open ↗
Showing 3 of 12 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT6
10/24/2019321996630Open ↗
07/29/2019321967323Open ↗
09/26/2018340635272Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST5
10/24/2019321996630Open ↗
07/29/2019321967323Open ↗
05/24/2018321762320Open ↗
Showing 3 of 5 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
09/26/2018340635272Open ↗
09/24/2018340634193Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
09/26/2018340635272Open ↗
09/21/2018340634193Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment14
▸BISSCHEDULE B - PLUMBING7
03/12/2020340634193Open ↗
01/14/2020340635272Open ↗
01/14/2020340634193Open ↗
Showing 3 of 7 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE5
03/18/2020340634193Open ↗
01/21/2020340635272Open ↗
01/21/2020340634193Open ↗
Showing 3 of 5 on file for this type
▸BISPLUMBING (PL) SIGNOFF1
01/20/2023340634193Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA1
07/18/2020321844091Open ↗
▸Safety & Tenant Protection3
▸BISSTREET TREE CHECKLIST2
01/15/2019321615374Open ↗
Showing 1 of 2 on file for this type
▸BISTenant Protection Plan and Notes1
10/24/2019321996630Open ↗
▸Environmental & Asbestos17
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/21/2026B01242391-I1Open ↗
08/19/2026B01188684-P1Open ↗
08/19/2026B01188684-P2Open ↗
Showing 3 of 7 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)6
10/10/2018321844091Open ↗
09/26/2018340635272Open ↗
09/21/2018340634193Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
08/13/2026B00191425-S1Open ↗
08/13/2026B00191425-I1Open ↗
08/13/2026B00191425-S2Open ↗
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)1
07/29/2019321967323Open ↗
▸Energy Compliance28
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS8
03/27/2020321967323Open ↗
10/24/2019321996630Open ↗
07/31/2019321615374Open ↗
Showing 3 of 8 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY7
07/23/2024321615374Open ↗
07/23/2024321615374Open ↗
11/02/2022321615374Open ↗
Showing 3 of 7 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS2
12/14/2021321996630Open ↗
03/27/2020321967323Open ↗
▸BISFENESTRATION U-FACTOR & PRODUCT RATING1
08/04/2022321615374Open ↗
▸BISFENESTRATION AREAS1
08/04/2022321615374Open ↗
▸BISAIR SEALING AND INSULATION - VISUAL1
08/04/2022321615374Open ↗
▸BISTR8: Energy Code Progress Inspections1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISFENESTRATION AIR LEAKAGE1
08/04/2022321615374Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
09/21/2018340634193Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
08/04/2022321615374Open ↗
▸BISEXTERIOR LIGHTING POWER1
08/04/2022321615374Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
08/04/2022321615374Open ↗
▸BISLIGHTING CONTROLS1
08/04/2022321615374Open ↗
▸BISINTERIOR LIGHTING POWER1
08/04/2022321615374Open ↗
▸Inspections & Test Reports15
▸BISTECHNICAL REPORT: RESPONSIBILITY11
07/23/2024321615374Open ↗
07/23/2024321615374Open ↗
12/17/2021321996630Open ↗
Showing 3 of 11 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
03/19/2019321762320Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
03/19/2019321762320Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
08/04/2022321615374Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
08/04/2022321615374Open ↗
▸Approvals, Objections & Sign-offs19
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST8
05/18/2022340635272Open ↗
11/05/2020321615374Open ↗
09/10/2020321844091Open ↗
Showing 3 of 8 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
05/14/2020321615374Open ↗
06/14/2019321615374Open ↗
02/13/2019321615374Open ↗
Showing 3 of 5 on file for this type
▸BISADMINISTRATIVE OBJECTIONS4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE2
10/02/2018321615374Open ↗
Showing 1 of 2 on file for this type
▸Cost, Insurance & Ownership20
▸BISCOST AFFIDAVIT13
03/25/2022340635272Open ↗
12/16/2021340635272Open ↗
12/14/2021321996630Open ↗
Showing 3 of 13 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE3
08/25/2020321615374Open ↗
07/31/2019321615374Open ↗
01/10/2019321762320Open ↗
▸BISAcord 25 (Acord Certificate of Liability Insurance)3
08/25/2020321615374Open ↗
07/31/2019321615374Open ↗
01/10/2019321762320Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
05/17/2022340635272Open ↗
▸Filing & Intake Forms36
▸BISADDITIONAL INFORMATION15
07/24/2024321615374Open ↗
04/13/2020321615374Open ↗
03/05/2020321967323Open ↗
Showing 3 of 15 on file for this type
▸BISBOROUGH INTAKE FORM11
04/24/2020321615374Open ↗
04/03/2020321615374Open ↗
03/27/2020321967323Open ↗
Showing 3 of 11 on file for this type
▸BISEFILING COVER SHEET8
10/23/2019321996630Open ↗
07/29/2019321967323Open ↗
10/10/2018321844091Open ↗
Showing 3 of 8 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET2
09/26/2018340635272Open ↗
09/21/2018340634193Open ↗
▸Other Documents7
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION3
02/04/2026321615374Open ↗
02/04/2026321615374Open ↗
09/10/2020321844091Open ↗
▸BISPLOT DIAGRAM3
02/13/2019321615374Open ↗
Showing 1 of 3 on file for this type
▸BISPROTECTION OF EXPOSED FOUNDATION INSULATION1
08/04/2022321615374Open ↗