| Owner | Filings | Most Recent |
|---|---|---|
| BPP St Owner | 281 | 10/16/2026 |
| Tishman/Speyer PCVST Management | 73 | 03/21/2026 |
| Rose Associates Inc Manager | 52 | 03/21/2026 |
| St-Dil | 27 | 03/21/2026 |
| Metropolitan Life Ins Co | 19 | 03/21/2026 |
| St Owner LP by Compass Rock | 10 | 03/21/2026 |
| Met Life Ins Co | 10 | 03/21/2026 |
| MGS Associates | 4 | 03/21/2026 |
| Citibank | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/18/2015 | $4.1B | — | ST-DIL LLC → BPP St Owner | $460/sf building |
| 06/03/2014 | $3.3B | — | — → — | $372/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Andrew Katz Engineers | 2 | 09/14/2026 |
| Building Studio Architects | 26 | 07/16/2026 |
| L. Naoum, P.E., P. C | 2 | 01/27/2026 |
| Tangel Engineering Associates | 9 | 01/07/2025 |
| LMW Engineering Group | 2 | 10/09/2024 |
| Zyscovich Architects | 2 | 05/10/2022 |
| High Line Engineering | 1 | 05/25/2021 |
| Leon Skvirsky PE | 2 | 12/04/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| Beam Living | 36 | 03/21/2026 |
| Municipal Building Consultants | 3 | 03/21/2026 |
| Building Brothers | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Super G Construction | General Contractor | 24 | 07/22/2026 |
| Kama Construction | General Contractor | 8 | 07/08/2026 |
| Kama Construction | Scaffold | 6 | 03/21/2026 |
| Metro Mechanical | specialty_contractor | 3 | 09/18/2026 |
| Duo Plumbing & Heating | Plumbing | 3 | 07/08/2026 |
| Atlas-Acon Electric Service | Electrical | 2 | 03/22/2026 |
| Big City Electrical Solutions | Electrical | 2 | 03/21/2026 |
| Astor & Stone | General Contractor | 2 | 07/08/2026 |
| Paul Signs | Sign hanger | 2 | 07/08/2026 |
| Duo Plumbing & Heating | Fire Protection | 2 | 07/08/2026 |
| Copper Services | Fire Protection | 1 | 07/08/2026 |
| Copper Services | Plumbing | 1 | 07/08/2026 |
| Crown Plumbing | Plumbing | 1 | 07/08/2026 |
| TMS Plumbing & Heating | Fire Protection | 1 | 07/08/2026 |
| Electrical Solutions | Electrical | 1 | 03/21/2026 |
| LT Fire Protection | Fire Protection | 1 | 07/08/2026 |
| New York Plumbing-Heating-Cool | Fire Protection | 1 | 07/08/2026 |
| CPM Builders | General Contractor | 1 | 07/08/2026 |
| New York Plumbing-Heating-Cooling | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| David Katz, P.E | 6087 | 2 | 09/14/2026 |
| Building Studio Architect | 592 | 23 | 07/16/2026 |
| Crosscheck Inspection Services | 544 | 14 | 01/27/2026 |
| Sandeep Gunnala Engineering | 8482 | 5 | 11/12/2024 |
| LMW Engineering Group | 279 | 2 | 10/09/2024 |
| High Line Engineering | 2920 | 1 | 05/25/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | Metro Mechanical | 09/17/2026 |
| DOB NOW | General Construction | Permit Issued | Super G Construction | 07/21/2026 |
| DOB NOW | General Construction | Signed-off | Super G Construction | 04/23/2026 |
| DOB NOW | General Construction | Signed-off | Super G Construction | 04/10/2026 |
| DOB NOW | Mechanical Systems | Signed-off | Super G Construction | 03/02/2026 |
| DOB NOW | Sprinklers | Signed-off | Duo Plumbing & Heating | 03/02/2026 |
| DOB NOW | Plumbing | Signed-off | Duo Plumbing & Heating | 01/27/2026 |
| DOB NOW | Plumbing | Signed-off | Duo Plumbing & Heating | 01/23/2026 |
| DOB NOW | Mechanical Systems | Signed-off | Super G Construction | 12/29/2025 |
| DOB NOW | General Construction | Signed-off | Super G Construction | 04/07/2025 |
| DOB NOW | Sprinklers | Signed-off | Duo Plumbing & Heating | 02/25/2025 |
| DOB NOW | Plumbing | Signed-off | Duo Plumbing & Heating | 01/13/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Super G Construction | 11/22/2024 |
| DOB NOW | Construction Fence | Signed-off | Kama Construction | 10/01/2024 |
| DOB NOW | Structural | Signed-off | Kama Construction | 09/30/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Kama Construction | 09/30/2024 |
| DOB NOW | General Construction | Signed-off | Kama Construction | 09/30/2024 |
| DOB NOW | Sprinklers | Signed-off | LT Fire Protection | 09/19/2024 |
| DOB NOW | Construction Fence | Signed-off | Kama Construction | 08/14/2024 |
| DOB NOW | Plumbing | Signed-off | New York Plumbing-Heating-Cooling | 08/08/2024 |
| DOB NOW | Sprinklers | Signed-off | New York Plumbing-Heating-Cool | 08/08/2024 |
| DOB NOW | General Construction | Signed-off | Super G Construction | 08/02/2024 |
| DOB NOW | General Construction | Signed-off | Super G Construction | 03/06/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Kama Construction | 02/12/2024 |
| DOB NOW | Structural | Signed-off | Kama Construction | 02/09/2024 |
| DOB NOW | General Construction | Signed-off | Kama Construction | 02/09/2024 |
| DOB NOW | General Construction | Signed-off | Super G Construction | 01/05/2024 |
| DOB NOW | General Construction | Signed-off | Super G Construction | 11/15/2023 |
| DOB NOW | General Construction | Signed-off | Super G Construction | 09/07/2023 |
| DOB NOW | General Construction | Signed-off | Super G Construction | 08/30/2023 |
| DOB NOW | General Construction | Signed-off | Super G Construction | 06/30/2023 |
| DOB NOW | General Construction | Signed-off | Super G Construction | 05/22/2023 |
| DOB NOW | General Construction | Signed-off | Super G Construction | 03/10/2023 |
| DOB NOW | Sprinklers | Signed-off | Copper Services | 01/10/2023 |
| DOB NOW | Plumbing | Signed-off | Copper Services | 11/22/2022 |
| DOB NOW | General Construction | Signed-off | Super G Construction | 09/21/2022 |
| DOB NOW | Plumbing | Signed-off | Crown Plumbing | 09/06/2022 |
| DOB NOW | General Construction | Signed-off | Astor & Stone | 08/23/2022 |
| DOB NOW | Mechanical Systems | Signed-off | Astor & Stone | 08/23/2022 |
| DOB NOW | General Construction | Signed-off | Super G Construction | 05/27/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/14/2026 | Signed-off | Metro Mechanical | Heating and Air Conditioning Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/27/2026 | Signed-off | Duo Plumbing & Heating | 111 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/27/2026 | — | — | — |
| 05/28/2025 | Signed-off | Duo Plumbing & Heating | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/04/2026 | Permit Issued | Electrical Solutions | General Wiring |
| 07/30/2026 | Permit Issued | Electrical Solutions | General Wiring |
| 05/22/2026 | Permit Issued | Electrical Solutions | General Wiring |
| 05/18/2026 | Complete | Electrical Solutions | General Wiring |
| 04/19/2026 | Permit Issued | Electrical Solutions | General Wiring |
| 02/18/2026 | Complete | Big City Electrical Solutions | General Wiring |
| 01/19/2026 | Cancelled | Big City Electrical Solutions | General Wiring |
| 11/24/2025 | Complete | Atlas-Acon Electric Service | General Wiring |
| 11/24/2025 | Complete | Atlas-Acon Electric Service | General Wiring |
| 11/13/2025 | Complete | Electrical Solutions | General Wiring |
| 04/19/2025 | Complete | Electrical Solutions | General Wiring |
| 04/03/2025 | Permit Issued | Electrical Solutions | General Wiring |
| 04/01/2025 | Complete | Electrical Solutions | — |
| 01/21/2025 | Complete | GRX Euro Electric | — |
| 12/04/2024 | Cancelled | Electrical Solutions | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/15/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/21/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/17/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/13/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/17/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/16/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 06/04/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/16/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/04/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/29/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 10/08/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/24/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 09/24/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/02/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/02/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/27/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/20/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/13/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/14/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 01/31/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/26/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/26/2022 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/09/2026 | Tenant Protection Plan Compliance | David Katz | special |
| 09/08/2026 | Energy Code Compliance Inspections | David Katz | progress |
| 09/03/2026 | Mechanical Systems | David Katz | special |
| 09/03/2026 | Maintenance information | David Katz | energy_progress |
| 09/03/2026 | Final | David Katz | progress |
| 09/03/2026 | HVAC-R and service water heating system controls | David Katz | energy_progress |
| 09/03/2026 | HVAC-R and service water piping design and insulation | David Katz | energy_progress |
| 09/03/2026 | HVAC-R and service water heating equipment | David Katz | energy_progress |
| 07/10/2026 | Energy Code Compliance Inspections | John Field | progress |
| 07/10/2026 | Lighting in dwelling units | John Field | energy_progress |
| 07/07/2026 | Tenant Protection Plan Compliance | John Field | special |
| 06/15/2026 | Final | John Field | progress |
| 04/08/2026 | Lighting in dwelling units | John Field | energy_progress |
| 04/08/2026 | Energy Code Compliance Inspections | John Field | progress |
| 04/08/2026 | Tenant Protection Plan Compliance | John Field | special |
| 04/08/2026 | Final | John Field | progress |
| 04/02/2026 | Tenant Protection Plan Compliance | John Field | special |
| 04/02/2026 | Energy Code Compliance Inspections | John Field | progress |
| 04/02/2026 | Lighting in dwelling units | John Field | energy_progress |
| 03/27/2026 | Final | John Field | progress |
| 05/29/2025 | HVAC-R and service water piping design and insulation | John Field | energy_progress |
| 05/29/2025 | Tenant Protection Plan Compliance | John Field | special |
| 05/29/2025 | Fire-Resistant Penetrations and Joints | John Field | special |
| 05/29/2025 | Energy Code Compliance Inspections | John Field | progress |
| 05/27/2025 | Tenant Protection Plan Compliance | — | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Citibank | Bank / Financial branch | Floor 1 | Project M00675433 |