| Owner | Filings | Most Recent |
|---|---|---|
| JNS REALTY OF NY, INC | 13 | 03/22/2026 |
| SUPREME GENERAL CONTRACTI | 4 | 03/22/2026 |
| JNS REALTY | 17 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ARCHITECTURAL CONCEPT | 7 | 12/27/2023 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SUPREME GENERAL CONTRACTING | General Contractor | 9 | 03/21/2026 |
| ROCK E SMALL PLBG&HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ARCHITECTURAL CONCEPT | 3642 | 7 | 12/27/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | SUPREME GENERAL CONTRACTI | 08/02/2023 |
| DOB NOW | Plumbing | Signed-off | ROCK E SMALL PLBG&HTG INC | 01/17/2023 |
| DOB NOW | Earth Work | Permit Issued | SUPREME GENERAL CONTRACTI | 11/18/2022 |
| DOB NOW | Foundation | Permit Issued | SUPREME GENERAL CONTRACTI | 09/28/2022 |
| BIS | SP | ISSUED | ALL PRO PLBG & HTG INC | 08/28/2018 |
| BIS | PL | ISSUED | JODOM MECHANICAL, INC | 08/22/2018 |
| BIS | EQ | ISSUED | SUPREME GENERAL CONTRACTING | 03/29/2018 |
| BIS | MH | ISSUED | SUPREME GENERAL CONTRACTING | 03/29/2018 |
| BIS | — | ISSUED | SUPREME GENERAL CONTRACTING | 03/29/2018 |
| BIS | SP | ISSUED | ALL PRO PLBG & HTG INC | 03/31/2017 |
| BIS | — | ISSUED | SUPREME GENERAL CONTRACTING | 03/30/2017 |
| BIS | PL | ISSUED | JODOM MECHANICAL, INC | 03/29/2017 |
| BIS | MH | ISSUED | SUPREME GENERAL CONTRACTING | 03/29/2017 |
| BIS | EQ | ISSUED | SUPREME GENERAL CONTRACTING | 03/29/2017 |
| BIS | MH | ISSUED | SUPREME GENERAL CONTRACTING | 02/01/2017 |
| BIS | EQ | ISSUED | SUPREME GENERAL CONTRACTING | 03/30/2016 |
| BIS | — | ISSUED | SUPREME GENERAL CONTRACTING | 03/30/2016 |
| BIS | PL | ISSUED | JODOM MECHANICAL, INC | 02/08/2016 |
| BIS | — | ISSUED | SUPREME GENERAL CONTRACTING | 05/08/2015 |
| BIS | — | ISSUED | SUPREME GENERAL CONTRACTING | 04/17/2015 |
| BIS | — | ISSUED | SUPREME GENERAL CONTRACTING | 04/17/2015 |
| BIS | EQ | ISSUED | SUPREME GENERAL CONTRACTING | 04/16/2015 |
| BIS | BL | ISSUED | TRICO FUEL CORPAORATION | 11/30/1992 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/25/2023 | Complete | MAGIC ELECTRIC INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/27/2023 | Signed-off | SUPREME GENERAL CONTRACTI | 3 scope_items |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/04/2024 | Masonry | MUZAFFAR JAMAL | special |
| 01/04/2024 | HVAC-R and service water piping design and insulation | MUZAFFAR JAMAL | energy_progress |
| 01/04/2024 | Insulation placement and R values | MUZAFFAR JAMAL | energy_progress |
| 01/04/2024 | Air barrier - visual inspection | MUZAFFAR JAMAL | energy_progress |
| 01/04/2024 | Energy Code Compliance Inspections | MUZAFFAR JAMAL | progress |
| 01/04/2024 | Footing and Foundation | MUZAFFAR JAMAL | progress |
| 01/04/2024 | Final | TARIQ SIDDIQUI | progress |
| 01/04/2024 | Fire-Resistance Rated Construction | MUZAFFAR JAMAL | progress |
| 01/04/2024 | Fire-Resistant Penetrations and Joints | MUZAFFAR JAMAL | special |
| 01/04/2024 | Structural Cold-Formed Steel | MUZAFFAR JAMAL | special |
| 12/27/2023 | Fire-Resistant Penetrations and Joints | MUZAFFAR JAMAL | special |
| 12/27/2023 | Masonry | MUZAFFAR JAMAL | special |
| 12/27/2023 | Structural Cold-Formed Steel | MUZAFFAR JAMAL | special |
| 12/27/2023 | Energy Code Compliance Inspections | MUZAFFAR JAMAL | progress |
| 12/27/2023 | Final | TARIQ SIDDIQUI | progress |
| 12/27/2023 | Fire-Resistance Rated Construction | MUZAFFAR JAMAL | progress |
| 12/27/2023 | Footing and Foundation | MUZAFFAR JAMAL | progress |
| 12/27/2023 | Insulation placement and R values | MUZAFFAR JAMAL | energy_progress |
| 12/27/2023 | HVAC-R and service water piping design and insulation | MUZAFFAR JAMAL | energy_progress |
| 12/27/2023 | Air barrier - visual inspection | MUZAFFAR JAMAL | energy_progress |
| 07/24/2023 | Fire-Resistant Penetrations and Joints | MUZAFFAR JAMAL | special |
| 07/18/2023 | Fire-Resistant Penetrations and Joints | MUZAFFAR JAMAL | special |
| 02/09/2023 | Fire-Resistant Penetrations and Joints | MUZAFFAR JAMAL | special |
| 08/24/2022 | Air barrier - visual inspection | MUZAFFAR JAMAL | energy_progress |
| 08/24/2022 | HVAC-R and service water piping design and insulation | MUZAFFAR JAMAL | energy_progress |