| Owner | Filings | Most Recent |
|---|---|---|
| S R K CONSTRUCTION | 5 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/21/2021 | $2.1M | — | NEWPORT REALTY VENTURES, LLC → LUCKNAUTH PROPERTIES, LLC | $264/sf building |
| 07/27/2017 | $700K | — | — → — | $88/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| SELF EMPLOYED | 1 | 03/28/2025 |
| TABRIZ DESIGN GROUP | 12 | 05/10/2024 |
| TABRIZ GROUP ENTERPRISES | 2 | 02/14/2024 |
| ARQUITECTURA VARELA | 1 | 08/04/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| Younes Abouyaala PE | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| J&J DESIGNS INC | General Contractor | 12 | 07/08/2026 |
| MULTANI CONSTRUCTION USA | General Contractor | 3 | 03/21/2026 |
| S.R.K CONTRUCTION INC | General Contractor | 3 | 03/21/2026 |
| PRIME PIPING & HEATING IN | Fire Protection | 1 | 07/08/2026 |
| GO SOLAR/GREEN NY LLC | General Contractor | 1 | 07/08/2026 |
| AYYUB ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| ZONE PLUMBING & HEATING C | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AA BUILDING & INSPECTION | 1519 | 1 | 03/28/2025 |
| TABRIZ GROUP ENTERPRISES | 3275 | 7 | 02/22/2024 |
| IP CONCRETE TESTING AND I | 6252 | 2 | 12/20/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | GO SOLAR/GREEN NY LLC | 04/01/2025 |
| DOB NOW | Structural | Permit Issued | J&J DESIGNS INC | 09/16/2024 |
| DOB NOW | Curb Cut | Signed-off | MULTANI CONSTRUCTION USA | 05/16/2024 |
| DOB NOW | Mechanical Systems | Signed-off | J&J DESIGNS INC | 09/14/2023 |
| DOB NOW | General Construction | Permit Issued | J&J DESIGNS INC | 09/14/2023 |
| DOB NOW | Construction Fence | Signed-off | J&J DESIGNS INC | 07/07/2023 |
| DOB NOW | Sprinklers | Signed-off | A M B MECHANICAL INC | 05/20/2023 |
| DOB NOW | Plumbing | Signed-off | ZONE PLUMBING & HEATING C | 04/27/2023 |
| DOB NOW | General Construction | Permit Issued | J&J DESIGNS INC | 09/16/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | S.R.K CONTRUCTION INC | 08/05/2022 |
| DOB NOW | General Construction | Permit Issued | J&J DESIGNS INC | 07/25/2022 |
| BIS | OT | ISSUED | GEM TOOL INC | 06/28/2007 |
| BIS | PL | ISSUED | CK PLUMBING & MECH INC | 11/05/1997 |
| BIS | MH | ISSUED | GEM TOOL INC | 10/15/1997 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/26/2025 | Complete | JOE ELECTRICAL INC | — |
| 01/29/2024 | Complete | VILLAGE ELECTL CONTRS INC | General Wiring |
| 12/19/2023 | Complete | AYYUB ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/14/2024 | Permit Issued | J&J DESIGNS INC | Steel, Concrete |
| 11/02/2022 | — | — | Steel |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/20/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/25/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 05/10/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/11/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/17/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 01/11/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/08/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/21/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 07/21/2023 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 07/21/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/21/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/27/2025 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 03/27/2025 | Air barrier - visual inspection | Younes Abouyaala | energy_progress |
| 03/27/2025 | Final | NAVEEN KUMAR | progress |
| 03/27/2025 | Energy Code Compliance Inspections | Younes Abouyaala | progress |
| 03/27/2025 | Structural Stability – Alterations of existing buildings | Younes Abouyaala | special |
| 04/08/2024 | Metering | BAKHTIAR SHAMLOO | energy_progress |
| 04/08/2024 | Interior lighting power | BAKHTIAR SHAMLOO | energy_progress |
| 04/08/2024 | Insulation placement and R values | BAKHTIAR SHAMLOO | energy_progress |
| 04/08/2024 | Fenestration areas | BAKHTIAR SHAMLOO | energy_progress |
| 04/08/2024 | Electrical motors and elevators | BAKHTIAR SHAMLOO | energy_progress |
| 04/08/2024 | Air barrier - visual inspection | BAKHTIAR SHAMLOO | energy_progress |
| 04/08/2024 | Lighting controls | BAKHTIAR SHAMLOO | energy_progress |
| 04/08/2024 | Final | BAKHTIAR SHAMLOO | progress |
| 04/08/2024 | Fire-Resistance Rated Construction | BAKHTIAR SHAMLOO | progress |
| 04/08/2024 | Energy Code Compliance Inspections | BAKHTIAR SHAMLOO | progress |
| 04/08/2024 | Fire-Resistant Penetrations and Joints | BAKHTIAR SHAMLOO | special |
| 04/08/2024 | Structural Steel - Details | BAKHTIAR SHAMLOO | special |
| 04/08/2024 | Structural Cold-Formed Steel | BAKHTIAR SHAMLOO | special |
| 04/08/2024 | Concrete - Cast-In-Place | BAKHTIAR SHAMLOO | special |
| 04/08/2024 | Masonry | BAKHTIAR SHAMLOO | special |
| 04/08/2024 | Structural Stability – Alterations of existing buildings | BAKHTIAR SHAMLOO | special |
| 04/08/2024 | Fenestration air leakage | BAKHTIAR SHAMLOO | energy_progress |
| 04/08/2024 | Exterior lighting power | BAKHTIAR SHAMLOO | energy_progress |
| 04/08/2024 | Maintenance information | BAKHTIAR SHAMLOO | energy_progress |
| 04/08/2024 | Fenestration and door U-factor and product ratings | BAKHTIAR SHAMLOO | energy_progress |