← Back
One story retail building
41-42A MAIN STREET
QUEENS · BIN 4533985
💬 Discuss this project
1950Year Built
1Stories
K1Building Class
R6Zoning
3,184 sfGross Floor Area
11Units
0 Open ViolationsFDNY Report ↗
One story retail building · Owner of record: THREE WONG REALTY LLC · 1,662 sf lot · 1.92 FAR built · Flood zone X
Locations of Work
MechanicalPlumbing
Floor 12p · 1 filing · 9 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
LN 1380804/09/2026
968 DIMSUM INC.703/22/2026
THREE WONG REALTY1103/22/2026
TO THE OWNER OF PREMISES103/22/2026
3 WONG REALTY903/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
LAM & LAM DESIGNS DPC207/01/2025
ALPHA HOME DESIGN LLC212/07/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
LAM & LAM ENGINEERING D.P.C.403/21/2026
INDESIGN STUDIO403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
FLUSHING ONE CONSTRUCTIONGeneral Contractor303/21/2026
KYL DESIGNS INCGeneral Contractor303/21/2026
ON GUK TSEElectrical203/21/2026
PROVENZANO, GIOVANNIFire Protection103/21/2026
WATSON'S PLBG, HTG, & BDGPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
LAM&LAM DESIGNS DPC3563207/01/2025
YAN GAO6619212/07/2021
Building Lifecycle
All (38)Filed (4)Permit Issued (3)Signed Off (1)Violation (12)Inspection (2)Special Inspection (16)
02/04/2026
Violation issued (FDNY_ORDER, closed)
02/04/2026
Violation issued (FDNY_ORDER, closed)
02/04/2026
Violation issued (FDNY_ORDER, closed)
10/05/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
07/28/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
07/18/2025
Permit issued — Plumbing
Q01249715-S1-PL
07/09/2025
Permit issued — Mechanical Systems
Q01249715-I1-GC-CX
07/01/2025
Filed — Alteration
INSTALL NEW PLUMBING FIXTURES IN KITCHEN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q01249715-S1
07/01/2025
Filed — Alteration
INSTALL NEW PLUMBING FIXTURES IN KITCHEN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q01249715-I1
07/01/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Benjamin Lam
07/01/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Benjamin Lam
07/01/2025
Special inspection requirement — Mechanical Systems
Benjamin Lam
07/01/2025
Special inspection requirement — Final
Kendrick Lam
12/15/2021
Signed off — Alteration
MECHANICAL WORK OF EXISTING COMMERCIAL STORE ST01 ON 1ST FLOOR & ROOF AS PER PLAN FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00590681-I1
12/08/2021
Special inspection requirement — Fire-Resistance Rated Construction
YAN GAO
12/08/2021
Special inspection requirement — Duct leakage testing, insulation and design
YAN GAO
12/08/2021
Special inspection requirement — Mechanical Systems
YAN GAO
12/08/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
YAN GAO
12/08/2021
Special inspection requirement — Energy Code Compliance Inspections
YAN GAO
12/08/2021
Special inspection requirement — Final
YAN GAO
12/07/2021
Filed — Alteration
MECHANICAL WORK OF EXISTING COMMERCIAL STORE ST01 ON 1ST FLOOR & ROOF AS PER PLAN FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00590681-P1
12/07/2021
Special inspection requirement — Duct leakage testing, insulation and design
YAN GAO
12/07/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
YAN GAO
12/07/2021
Special inspection requirement — Mechanical Systems
YAN GAO
12/07/2021
Special inspection requirement — Energy Code Compliance Inspections
YAN GAO
12/07/2021
Special inspection requirement — Final
YAN GAO
12/07/2021
Special inspection requirement — Fire-Resistance Rated Construction
YAN GAO
09/13/2021
Permit issued — Mechanical Systems
Q00590681-I1-MS
09/09/2021
Filed — Alteration
MECHANICAL WORK OF EXISTING COMMERCIAL STORE ST01 ON 1ST FLOOR & ROOF AS PER PLAN FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q00590681-I1
12/15/2010
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/21/2010
Violation issued (ECB, closed)
Plumbing
09/17/2010
Violation issued (ECB, closed)
Construction
09/14/2009
Violation issued (ECB, closed)
Unknown
09/04/2009
Violation issued (ECB, closed)
Construction
11/21/2008
Violation issued (ECB, closed)
Construction
11/10/2007
Violation issued (ECB, closed)
Quality of Life
10/22/2007
Violation issued (ECB, closed)
Construction
10/16/2007
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offWATSON'S PLBG, HTG, & BDG07/18/2025
DOB NOWMechanical SystemsPermit IssuedKYL DESIGNS INC07/09/2025
DOB NOWMechanical SystemsSigned-offFLUSHING ONE CONSTRUCTION09/13/2021
BISMHISSUEDSMVP MGMT INC06/12/2019
BISPLISSUEDPIPESTYLISTS, INC05/29/2019
BISPLISSUEDTOP PLUMBING GROUP,INC05/16/2017
BISOTISSUEDNIC DESIGN MGMT INC05/16/2017
BISOTISSUEDBARMOR REHAB INC08/17/2015
BISPLISSUEDK & BH PLUMBING & HTG INC11/21/2014
BISOTISSUEDBARMOR REHAB INC10/16/2014
BISPLISSUEDARISTA PLBG & HTG CORP12/28/2011
BISPLISSUEDPETER MICELI PLUMBING08/31/2011
BISOTISSUEDHONG KONG STYLE CONSTRUCT01/24/2011
BISPLISSUEDPETER MICELI PLUMBING08/18/2010
BISMHISSUEDD & B BROTHERS CONSTRUCT*04/27/2010
BISFPISSUEDMEGA FIRE PROTECTION INC12/21/2009
BISFPISSUEDMEGA FIRE PROTECTION INC09/15/2009
BISOTISSUEDHONG KONG STYLE CONSTRUCT09/03/2009
BISPLISSUEDTRI CITY WATER INC05/20/2009
BISPLISSUEDTRI CITY WATER INC04/21/2009
BISOTISSUEDHONG KONG STYLE CONSTRUCT03/24/2009
BISOTISSUEDHONG KONG STYLE CONSTRUCT12/05/2008
BISPLISSUEDPROVENZANO PLUMBING INC04/14/2008
BISMHISSUEDAMG PACIFIC CONSTRUCTION03/03/2008
BISOTISSUEDAMG PACIFIC CONSTRUTION INC01/30/2008
BISOTISSUEDAMG PACIFIC CONSTRUTION INC01/30/2008
BISMHISSUEDHSU & ASSOCIATE INC11/21/2006
BISEQISSUEDHSU & ASSOC INC03/02/2006
BIS—ISSUEDHSU & ASSOC INC03/02/2006
1 project · most recent 07/01/2025
Ventilation Systems
FiledStatusContractorScope
07/01/2025Permit IssuedKYL DESIGNS INCVentilation Systems
1 project · most recent 07/01/2025
Water/Sanitary
FiledStatusContractorScope
07/01/2025Signed-offWATSON'S PLBG, HTG, & BDGWater/Sanitary
3 projects · most recent 07/24/2026
General Wiring
FiledStatusContractorScope
07/24/2026Permit IssuedKWONG MING ELECTRIC INC6 meters, 2 new_meters
09/14/2021Permit IssuedHI-RITE ELECTRIC CORPGeneral Wiring
12/17/2018Permit IssuedW 8 ELECTRIC CORPGeneral Wiring
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
10/05/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
07/28/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 16
DateRequirementInspectorRole
07/01/2025Fire-Resistant Penetrations and JointsBenjamin Lamspecial
07/01/2025Fire-Resistant Penetrations and JointsBenjamin Lamspecial
07/01/2025Mechanical SystemsBenjamin Lamspecial
07/01/2025FinalKendrick Lamprogress
12/08/2021Fire-Resistance Rated ConstructionYAN GAOprogress
12/08/2021Duct leakage testing, insulation and designYAN GAOenergy_progress
12/08/2021Mechanical SystemsYAN GAOspecial
12/08/2021Fire-Resistant Penetrations and JointsYAN GAOspecial
12/08/2021Energy Code Compliance InspectionsYAN GAOprogress
12/08/2021FinalYAN GAOprogress
12/07/2021Duct leakage testing, insulation and designYAN GAOenergy_progress
12/07/2021Fire-Resistant Penetrations and JointsYAN GAOspecial
12/07/2021Mechanical SystemsYAN GAOspecial
12/07/2021Energy Code Compliance InspectionsYAN GAOprogress
12/07/2021FinalYAN GAOprogress
12/07/2021Fire-Resistance Rated ConstructionYAN GAOprogress
▾Documents — 232 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/27/2026Q00590681-P1Request digital key ↗
08/27/2026Q00590681-I1Request digital key ↗
08/19/2026Q01249715-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits39
▸BISWORK PERMIT APPLICATION22
05/30/2019421476361Open ↗
05/24/2017421476361Open ↗
05/24/2017421476361Open ↗
Showing 3 of 22 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION15
07/18/2019421921013Open ↗
05/18/2017421476361Open ↗
03/19/2014420804044Open ↗
Showing 3 of 15 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications2
08/06/2019421476361Open ↗
08/20/2012410234508Open ↗
▸Zoning, Tax Lot & Property Records1
▸BISZONING DIAGRAM1
04/01/2013420804044Open ↗
▸Seals & Professional Certifications53
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION22
08/06/2019421476361Open ↗
07/31/2019421921013Open ↗
07/19/2019421476361Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWProgress Inspector Seal & Signature9
09/23/2026Q00590681-I1Open ↗
09/23/2026Q00590681-I1Open ↗
09/23/2026Q00590681-I1Open ↗
Showing 3 of 9 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST6
07/18/2019421921013Open ↗
05/18/2017421476361Open ↗
12/05/2008410026476Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM4
03/03/2008410072264Open ↗
01/23/2008410054300Open ↗
01/22/2008410054006Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/27/2026Q00590681-I1Open ↗
08/19/2026Q01249715-S1Open ↗
08/19/2026Q01249715-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/23/2026Q00590681-I1Open ↗
09/23/2026Q00590681-I1Open ↗
08/31/2026Q01249715-I1Open ↗
Showing 3 of 4 on file for this type
▸BISPC FULL REPORT3
01/23/2008410054300Open ↗
01/22/2008410054006Open ↗
Showing 2 of 3 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
05/18/2017421476361Open ↗
▸Trade Schedules & Equipment31
▸BISSELF-CERT PLUMBING NOTICE11
11/23/2015420804044Open ↗
11/18/2015420804044Open ↗
08/23/2012410234508Open ↗
Showing 3 of 11 on file for this type
▸BISSCHEDULE B - PLUMBING10
08/17/2013420111015Open ↗
03/27/2013420804044Open ↗
09/30/2011410234508Open ↗
Showing 3 of 10 on file for this type
▸BISSEWER CONNECTION: DEP SD1 & SD23
08/01/2014420804044Open ↗
08/01/2014420804044Open ↗
07/29/2014420804044Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
05/18/2017421476361Open ↗
03/19/2014420804044Open ↗
▸BISWATER METER PERMIT : DEP-METER2
08/23/2012410234508Open ↗
07/30/2012410234508Open ↗
▸BISEQUIPMENT USE APPLICATION/PERMIT1
07/31/2019421921013Open ↗
▸BISFIRE PROTECTION PLAN(FPP): FDNY APPROVAL1
09/10/2013420111015Open ↗
▸BISEQUIPMENT USE PERMITS1
07/31/2019421921013Open ↗
▸Safety & Tenant Protection7
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE5
10/28/2014420804044Open ↗
10/28/2014420804044Open ↗
10/28/2014420804044Open ↗
Showing 3 of 5 on file for this type
▸BISSTREET TREE CHECKLIST2
02/08/2013420804044Open ↗
03/18/2009410234508Open ↗
▸Environmental & Asbestos14
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'6
01/13/2010420127570Open ↗
12/02/2009420111015Open ↗
08/28/2009420073075Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/27/2026Q00590681-I1Open ↗
08/19/2026Q01249715-S1Open ↗
08/19/2026Q01249715-I1Open ↗
Showing 3 of 4 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
02/26/2013420804044Open ↗
03/18/2009410234508Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
05/18/2017421476361Open ↗
03/11/2013420804044Open ↗
▸Energy Compliance11
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS7
08/06/2019421476361Open ↗
06/27/2019421921013Open ↗
06/27/2019421476361Open ↗
Showing 3 of 7 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
08/06/2019421476361Open ↗
07/19/2019421476361Open ↗
06/27/2019421921013Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026Q00590681-I1Open ↗
▸Inspections & Test Reports3
▸BISINSPECTION REPORT - SUPPORTING DOCUMENTATION1
06/27/2019421476361Open ↗
▸BISMANUFACTURE STATEMENT: QUALITY OF MASONRY UNITS-REQUIRED PRIOR TO CONSTRUCTION OF MASONRY (B FORM 10H)1
10/28/2014420804044Open ↗
▸BISMASONRY MANUFACTURER'S STATEMENT-FORM 10H1
04/21/2016420804044Open ↗
▸Approvals, Objections & Sign-offs26
▸BISADMINISTRATIVE OBJECTIONS9
05/18/2017421476361Open ↗
01/13/2010420127570Open ↗
12/02/2009420111015Open ↗
Showing 3 of 9 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST9
08/05/2019421476361Open ↗
07/31/2019421921013Open ↗
07/29/2019421921013Open ↗
Showing 3 of 9 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
09/10/2013420111015Open ↗
08/23/2012410234508Open ↗
08/20/2012410234508Open ↗
Showing 3 of 5 on file for this type
▸BISSUPERSEDING LETTER3
05/30/2019421476361Open ↗
12/29/2011410234508Open ↗
08/18/2010410234508Open ↗
▸Cost, Insurance & Ownership24
▸BISCOST AFFIDAVIT19
08/06/2019421476361Open ↗
07/19/2019421476361Open ↗
06/27/2019421921013Open ↗
Showing 3 of 19 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE2
09/04/2015420804044Open ↗
10/28/2014420804044Open ↗
▸BISLL58/88-CIVIL PENALTY AFFIDAVIT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISAcord 25 (Acord Certificate of Liability Insurance)1
09/04/2015420804044Open ↗
▸BISPROJECT SPECIFIC GENERAL LIABILITY INSURANCE (PGLI)1
10/28/2014420804044Open ↗
▸Filing & Intake Forms12
▸BISEFILING COVER SHEET6
05/18/2017421476361Open ↗
01/13/2010420127570Open ↗
12/02/2009420111015Open ↗
Showing 3 of 6 on file for this type
▸BISBOROUGH INTAKE FORM3
07/29/2019421921013Open ↗
07/25/2019421921013Open ↗
06/27/2019421476361Open ↗
▸BISADDITIONAL INFORMATION3
06/08/2019421476361Open ↗
07/06/2015420804044Open ↗
08/23/2012410234508Open ↗
▸Other Documents7
▸BISFIRE SUPP ANSUL APPROVL- FD-FSS4
09/28/2010410234508Open ↗
09/20/2010410234508Open ↗
09/20/2010410234508Open ↗
Showing 3 of 4 on file for this type
▸BISSTREET: UNMAPPED-NOTIFY EMERG. AGENCIES1
12/05/2008410026476Open ↗
▸BISSITE CONNECTION: DEP1
07/25/2014420804044Open ↗
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
04/21/2016420804044Open ↗