| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/11/2024 | Permit Issued | F.S. SITE CORP | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/24/2025 | Permit Issued | HIGH QUALITY ELEC.OF NYC | — |
| 05/29/2024 | Permit Issued | SOLO ENERGY & ELECTRICAL | General Wiring |
| 07/25/2023 | Complete | BOROWIDE ELECT'L CONTR'S | — |
| 12/29/2021 | Complete | DELCO ELECTRICAL CORP. | 3 meters, 1 new_meters |
| 03/19/2021 | Complete | JAVELIN ELECTRIC INC | General Wiring |
| 04/04/2019 | Complete | DELCO ELECTRICAL CORP. | — |
| 03/20/2019 | Complete | DELCO ELECTRICAL CORP. | General Wiring |
| 12/13/2018 | Complete | THYSSENKRUPP ELEVATOR CO | — |
| 04/23/2018 | Complete | TOP SHELF ELECTRIC CORP | — |
| 02/22/2018 | Complete | DELCO ELECTRICAL CORP. | 1 meters, 1 new_meters |
| 02/21/2018 | Complete | DELCO ELECTRICAL CORP. | — |
| 01/23/2018 | Complete | DELCO ELECTRICAL CORP. | — |
| 01/23/2018 | Complete | DELCO ELECTRICAL CORP. | — |
| 01/18/2018 | Complete | DELCO ELECTRICAL CORP. | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/22/2025 | Signed-off | KINGS GROUP NY CORP | Sidewalk Shed |
| Owner | Filings | Most Recent |
|---|---|---|
| DAMICO 365 COFFEE | 14 | 07/08/2026 |
| BROOKFIELD PROPERTIES | 11 | 07/08/2026 |
| KINGS GROUP NY | 6 | 07/08/2026 |
| F OWNER | 6 | 03/21/2026 |
| OWNERS REP | 1 | 03/21/2026 |
| BROOKFIELD PROPERTY PARTNERS | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KN3 ENGINEERING LLC | 2 | 08/06/2025 |
| KMA DESIGNS LLC | 1 | 07/22/2025 |
| PARADIGM ARCHITECTURE | 1 | 04/28/2025 |
| COLLECTIF ENGINEERING PLLC | 2 | 04/11/2024 |
| ENTHINK ENGINEERS LLC | 1 | 07/21/2023 |
| SAUL DAVID HAYUTIN ARCHITECTS | 2 | 05/21/2023 |
| PAUL PERDEK, PROF. ENG. PLLC | 3 | 11/15/2022 |
| HOWARD I SHAPIRO & ASSOCIATES | 1 | 10/17/2022 |
| COSENTINI ASSOCIATES | 4 | 05/28/2021 |
| BAILEYS ENGINEERING PC | 1 | 05/17/2019 |
| STRUCTURETECH NEW YORK, INC | 1 | 07/19/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| A1 EXPEDITING SERVICE | 8 | 03/21/2026 |
| DVA Advisors | 4 | 03/21/2026 |
| AE DESIGN SOLUTION | 6 | 03/21/2026 |
| HOWARD I SHAPIRO ASSOCIATES | 2 | 03/21/2026 |
| WSCONSULTANT & EXPEDITING SERVICES | 8 | 03/21/2026 |
| KMA DESIGNS LLC | 2 | 03/21/2026 |
| MUNICIPAL BUILDING CONSULTANTS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SOLO ENERGY ELECTRICAL 004984 | General Contractor | 5 | 03/22/2026 |
| AD LINE NYC INC | General Contractor | 3 | 07/08/2026 |
| DELCO ELECTRICAL CORP. | Electrical | 3 | 03/22/2026 |
| GENERAL INSTALLERS CORP | General Contractor | 3 | 03/21/2026 |
| F.S. SITE CORP | Plumbing | 2 | 07/08/2026 |
| CITILINE RESTORATION LLC | General Contractor | 2 | 07/08/2026 |
| POFI CONSTRUCTION CORP | General Contractor | 2 | 03/21/2026 |
| JAVELIN ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| HARMON, INC | General Contractor | 1 | 07/08/2026 |
| KINGS GROUP NY CORP | General Contractor | 1 | 07/08/2026 |
| ALEXANDER EUGENE | Electrical | 1 | 03/21/2026 |
| ANDAMIO SCAFFOLDING LLC | General Contractor | 1 | 07/08/2026 |
| HIGH QUALITY ELEC.OF NYC | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| LEO Y LEE ASSOCIATES | 2481 | 2 | 08/06/2025 |
| PARADIGM ARCHITECTURE | 5931 | 1 | 04/28/2025 |
| COLLECTIF ENGINEERING, PL | 7799 | 3 | 04/11/2024 |
| CLARKE ENGINEERING SERVIC | 3795 | 2 | 02/02/2022 |
| ATLANTIC ENGINEERINGLABOR | 1381 | 3 | 05/28/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | CITILINE RESTORATION LLC | 12/04/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | KINGS GROUP NY CORP | 07/23/2025 |
| DOB NOW | General Construction | Signed-off | CITILINE RESTORATION LLC | 07/22/2025 |
| DOB NOW | Suspended Scaffold | Signed-off | CITILINE RESTORATION LLC | 07/01/2025 |
| DOB NOW | Plumbing | Permit Issued | ALAN J BRUTOSKY PLBR CONT | 06/13/2025 |
| DOB NOW | General Construction | Permit Issued | AD LINE NYC INC | 09/30/2024 |
| DOB NOW | General Construction | Permit Issued | AD LINE NYC INC | 08/14/2024 |
| DOB NOW | Plumbing | Signed-off | ALAN J BRUTOSKY PLBR CONT | 09/12/2023 |
| DOB NOW | General Construction | Permit Issued | AD LINE NYC INC | 08/11/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 07/21/2023 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | GENERAL INSTALLERS CORP | 11/15/2022 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | POFI CONSTRUCTION CORP | 10/18/2022 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | HARMON, INC | 10/14/2021 |
| BIS | EQ | ISSUED | CONSIGLI & ASSOCIATES LLC | 01/28/2021 |
| BIS | EQ | ISSUED | CONSIGLI & ASSOCIATES LLC | 12/30/2020 |
| BIS | OT | ISSUED | TALISEN CONSTRUCTION CORP | 10/19/2020 |
| BIS | PL | ISSUED | PARKVIEW P&H INC | 09/08/2020 |
| BIS | SP | ISSUED | NEPTUNE MECHANICAL INC | 06/02/2020 |
| BIS | EQ | ISSUED | SPRING SCAFFOLDING LLC | 04/28/2020 |
| BIS | OT | ISSUED | CONSIGLI & ASSOCIATES LLC | 12/16/2019 |
| BIS | PL | ISSUED | PARKVIEW P&H INC | 09/13/2019 |
| BIS | EQ | ISSUED | SPRING SCAFFOLDING LLC | 07/12/2019 |
| BIS | EQ | ISSUED | CONSIGLI & ASSOCIATES LLC | 07/01/2019 |
| BIS | EQ | ISSUED | WALSH GLASS & METAL INC | 06/10/2019 |
| BIS | EQ | ISSUED | SPRING SCAFFOLDING LLC | 05/30/2019 |
| BIS | EQ | ISSUED | SPRING SCAFFOLDING LLC | 04/29/2019 |
| BIS | EQ | ISSUED | SPRING SCAFFOLDING LLC | 03/18/2019 |
| BIS | EQ | ISSUED | SPRING SCAFFOLDING LLC | 03/18/2019 |
| BIS | EQ | ISSUED | CONSIGLI & ASSOCIATES LLC | 03/14/2019 |
| BIS | — | RE-ISSUED | CONSIGLI & ASSOCIATES LLC | 12/21/2018 |
| BIS | SP | ISSUED | NEPTUNE MECHANICAL INC | 12/14/2018 |
| BIS | PL | ISSUED | PARKVIEW P&H INC | 10/11/2018 |
| BIS | EQ | ISSUED | STRUCTURETECH NEW YORK IN | 07/24/2018 |
| BIS | EQ | ISSUED | SPRING SCAFFOLDING LLC | 07/12/2018 |
| BIS | EQ | ISSUED | CASINO DEVELOPMENT GROUP | 06/28/2018 |
| BIS | EQ | ISSUED | SPRING SCAFFOLDING LLC | 06/01/2018 |
| BIS | SD | ISSUED | NEPTUNE MECHANICAL INC | 05/16/2018 |
| BIS | EQ | ISSUED | SPRING SCAFFOLDING LLC | 04/27/2018 |
| BIS | — | RE-ISSUED | CONSIGLI & ASSOCIATES LLC | 04/11/2018 |
| BIS | EQ | ISSUED | CASINO DEVELOPMENT GROUP | 04/10/2018 |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/16/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/04/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/03/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 11/19/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/25/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/17/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/19/2025 | Alternative Materials - OTCR Buildings Bulletin Number | Leo Lee | special |
| 08/19/2025 | Post-installed Anchors | Leo Lee | special |
| 04/23/2025 | Post-installed Anchors | Anthony Addesso | special |
| 04/23/2025 | Masonry | Anthony Addesso | special |
| 04/23/2025 | Energy Code Compliance Inspections | Anthony Addesso | progress |
| 04/23/2025 | Structural Stability – Alterations of existing buildings | Anthony Addesso | special |
| 04/21/2025 | Tenant Protection Plan Compliance | Anthony Addesso | special |
| 04/21/2025 | Final | Anthony Addesso | progress |
| 04/15/2024 | Fire-Resistant Penetrations and Joints | RAFAEL FIGUEROA | special |
| 04/15/2024 | HVAC-R and service water piping design and insulation | RAFAEL FIGUEROA | energy_progress |
| 04/04/2024 | HVAC-R and service water piping design and insulation | RAFAEL FIGUEROA | energy_progress |
| 04/04/2024 | Fire-Resistant Penetrations and Joints | RAFAEL FIGUEROA | special |
| 05/23/2023 | Lighting controls | Saul Hayutin | energy_progress |
| 05/23/2023 | Final | Saul Hayutin | progress |
| 05/23/2023 | Fire-Resistant Penetrations and Joints | RAFAEL FIGUEROA | special |
| 05/23/2023 | Interior lighting power | Saul Hayutin | energy_progress |
| 05/02/2023 | Lighting controls | Saul Hayutin | energy_progress |
| 05/02/2023 | Interior lighting power | Saul Hayutin | energy_progress |
| 05/02/2023 | Final | Saul Hayutin | progress |
| 05/02/2023 | Fire-Resistant Penetrations and Joints | — | special |
| 02/02/2022 | Post-installed Anchors | Brian Clarke | special |
| 01/25/2022 | Post-installed Anchors | Brian Clarke | special |
| 06/01/2021 | Maintenance information | FAWZY SALIB | energy_progress |
| 06/01/2021 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | Christopher O'Malley | special |
| 06/01/2021 | Mechanical Systems | FAWZY SALIB | special |