← Back
Large suburban residence
41 CENTER STREET
STATEN ISLAND · BIN 5175156
💬 Discuss this project
2022Year Built
2Stories
A3Building Class
R1-2Zoning
3,223 sfGross Floor Area
1Units
Large suburban residence · 6,300 sf lot · 0.51 FAR built · Flood zone X
Locations of Work
Structural
Floor 21 filing · 20 docs
Floor 11 filing · 20 docs
Basement1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
CSIII2007/08/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TONY SAYAD ARCHITECT510/03/2023
C&P DESIGN CONSULTANTS107/02/2023
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NIRO INCGeneral Contractor707/08/2026
FLOW-RIGHT PLBG & HTG CORPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SRA PLANNING & EXPEDITING5677410/03/2023
C&P DESIGN CONSULTANT8472107/02/2023
Building Lifecycle
All (54)Filed (6)Permit Issued (5)Signed Off (3)Inspection (8)Objection (2)Special Inspection (30)
10/25/2023
Signed off — New Building
Installation of New HVAC System
S00744406-S2
10/20/2023
Signed off — New Building
Installation of New HVAC System
S00744406-S3
10/17/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
10/11/2023
Signed off — New Building
Installation of New HVAC System
S00744406-S1
10/11/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/10/2023
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
10/10/2023
Special inspection requirement — Subgrade Inspections
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Duct leakage testing, insulation and design
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Structural Wood Frame
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Energy Code Compliance Inspections
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Fire-Resistance Rated Construction
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Final
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Footing and Foundation
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Permanent certificate
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Concrete - Cast-In-Place
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Fenestration air leakage
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Maintenance information
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Air barrier — testing
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Interior lighting power
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — HVAC-R and service water heating system controls
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Fenestration areas
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Electric vehicle service equipment requirements
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Insulation placement and R values
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Fireplaces
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — HVAC-R and service water heating equipment
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Air barrier - visual inspection
WILLIAM MONTAGUE
10/10/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
WILLIAM MONTAGUE
10/03/2023
Filed — New Building
Installation of New HVAC System
S00744406-P2
10/03/2023
Permit issued — Plumbing
S00744406-S2-PL
10/03/2023
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
10/03/2023
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
WILLIAM MONTAGUE
10/03/2023
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
WILLIAM MONTAGUE
10/03/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
WILLIAM MONTAGUE
10/03/2023
Special inspection requirement — Energy Code Compliance Inspections
WILLIAM MONTAGUE
10/02/2023
Filed — New Building
Installation of New HVAC System
S00744406-P1
10/02/2023
Permit issued — Curb Cut
S00744406-S1-CC
10/02/2023
Permit issued — Mechanical Systems
S00744406-S3-MS
07/02/2023
Filed — New Building
Installation of New HVAC System
S00744406-S3
05/12/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
05/08/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/16/2022
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
10/31/2022
Permit issued — Foundation
S00744406-I1-GC-CX
10/06/2022
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
09/19/2022
Permit issued — Plumbing
S00744406-S2-PL
08/01/2022
Objection raised — Scope
08/01/2022
Objection resolved — Addressed
07/11/2022
Filed — New Building
Installation of New HVAC System
S00744406-S2
07/11/2022
Filed — New Building
Installation of New HVAC System
S00744406-S1
07/11/2022
Filed — New Building
Installation of New HVAC System
S00744406-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offFLOW-RIGHT PLBG & HTG COR10/03/2023
DOB NOWCurb CutSigned-offNIRO INC10/02/2023
DOB NOWMechanical SystemsSigned-offNIRO INC10/02/2023
DOB NOWFoundationPermit IssuedNIRO INC10/31/2022
DOB NOWPlumbingSigned-offFLOW-RIGHT PLBG & HTG COR09/19/2022
BISOTISSUEDJ.B.I. CONSTRUCTION GROUP09/01/2023
1 project · most recent 10/03/2023
Air Conditioning Systems Associated Ducts and Piping Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
10/03/2023Signed-offNIRO INCAir Conditioning Systems, Associated Ducts and Piping, Heating Systems, Ventilation Systems
Cooling
Luxaire AP36BX21C 35,600 BTU · Split System ×1
AP42CX21C 41,500 BTU · Split System ×1
Heating
Triangle Tube IN199 161,000 BTU · Boiler ×1
Ventilation
Fantech N/A 170 CFM · Erv ×1
Ducts & Piping
N/A N/A 1 BTU · Ductwork ×1
1 project · most recent 10/03/2023
Gas Storm Water/Sanitary
FiledStatusContractorScope
10/03/2023Signed-offFLOW-RIGHT PLBG & HTG CORGas, Storm, Water/Sanitary
2 projects · most recent 09/11/2023
General Wiring
FiledStatusContractorScope
09/11/2023CompleteJSP ELECTL CNTNG CORP—
03/10/2023CompleteD AND H ELECTRICAL CONSTGeneral Wiring
1 project · most recent 10/03/2023
Wood
FiledStatusContractorScope
10/03/2023Signed-offFLOW-RIGHT PLBG & HTG CORWood
1 project · most recent 10/03/2023
Earthwork
FiledStatusContractorScope
10/03/2023Signed-offFLOW-RIGHT PLBG & HTG COREarthwork
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
10/17/2023Pass-Final CND-Occupancy InspectionPassView ↗
10/11/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/10/2023Pass-Final Curb Cut Non-Directive 14PassView ↗
10/03/2023Fail-Final PL - Up to 3 Requested FloorsFailView ↗
05/12/2023Pass-Final CND-Occupancy InspectionPassView ↗
05/08/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/16/2022Pass-Final PL - UndergroundPassView ↗
10/06/2022Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 83
DateRequirementInspectorRole
10/10/2023Footing and FoundationWILLIAM MONTAGUEprogress
10/10/2023Subgrade InspectionsWILLIAM MONTAGUEspecial
10/10/2023Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationWILLIAM MONTAGUEspecial
10/10/2023Fire-Resistant Penetrations and JointsWILLIAM MONTAGUEspecial
10/10/2023Subsurface Investigations (Borings/Test Pits)WILLIAM MONTAGUEspecial
10/10/2023Exterior Insulation and Finish Systems (EIFS)WILLIAM MONTAGUEspecial
10/10/2023Structural Wood FrameWILLIAM MONTAGUEprogress
10/10/2023Energy Code Compliance InspectionsWILLIAM MONTAGUEprogress
10/10/2023Fire-Resistance Rated ConstructionWILLIAM MONTAGUEprogress
10/10/2023FinalWILLIAM MONTAGUEprogress
10/10/2023Permanent certificateWILLIAM MONTAGUEenergy_progress
10/10/2023Fenestration and door U-factor and product ratingsWILLIAM MONTAGUEenergy_progress
10/10/2023Duct leakage testing, insulation and designWILLIAM MONTAGUEenergy_progress
10/10/2023Fenestration air leakageWILLIAM MONTAGUEenergy_progress
10/10/2023Maintenance informationWILLIAM MONTAGUEenergy_progress
10/10/2023Air barrier — testing WILLIAM MONTAGUEenergy_progress
10/10/2023Interior lighting powerWILLIAM MONTAGUEenergy_progress
10/10/2023HVAC-R and service water heating system controlsWILLIAM MONTAGUEenergy_progress
10/10/2023HVAC-R and service water piping design and insulationWILLIAM MONTAGUEenergy_progress
10/10/2023Fenestration areasWILLIAM MONTAGUEenergy_progress
10/10/2023Electric vehicle service equipment requirementsWILLIAM MONTAGUEenergy_progress
10/10/2023Insulation placement and R valuesWILLIAM MONTAGUEenergy_progress
10/10/2023FireplacesWILLIAM MONTAGUEenergy_progress
10/10/2023HVAC-R and service water heating equipmentWILLIAM MONTAGUEenergy_progress
10/10/2023Air barrier - visual inspectionWILLIAM MONTAGUEenergy_progress
Latest 25 of 83.
▾Documents — 74 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
08/22/2026S00744406-S3Request digital key ↗
08/22/2026S00744406-S2Request digital key ↗
08/22/2026S00744406-S2Request digital key ↗
Showing 3 of 7 on file for this type
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
08/31/2023540257158Open ↗
▸BISWORK PERMIT APPLICATION1
09/01/2023540257158Open ↗
▸Zoning, Tax Lot & Property Records5
▸DOB NOWZD1: DOB Zoning Diagram2
08/22/2026S00744406-P1Open ↗
08/22/2026S00744406-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/22/2026S00744406-P1Open ↗
08/22/2026S00744406-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/22/2026S00744406-I1Open ↗
▸Seals & Professional Certifications26
▸DOB NOWProgress Inspector Seal & Signature10
09/02/2026S00744406-P2Open ↗
09/02/2026S00744406-P2Open ↗
09/01/2026S00744406-S2Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
09/02/2026S00744406-P2Open ↗
09/01/2026S00744406-S2Open ↗
08/30/2026S00744406-S3Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/22/2026S00744406-S3Open ↗
08/22/2026S00744406-S2Open ↗
08/22/2026S00744406-S1Open ↗
Showing 3 of 5 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
08/31/2023540257158Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
08/31/2023540257158Open ↗
▸Trade Schedules & Equipment2
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/22/2026S00744406-I1Open ↗
08/22/2026S00744406-P1Open ↗
▸Safety & Tenant Protection6
▸DOB NOWStreet Tree Checklist2
08/22/2026S00744406-P1Open ↗
08/22/2026S00744406-I1Open ↗
▸BISTPP1: TENANT PROTECTION PLAN1
09/01/2023540257158Open ↗
▸DOB NOWStreet Trees Site Plan1
08/22/2026S00744406-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/22/2026S00744406-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/22/2026S00744406-I1Open ↗
▸Energy Compliance7
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
09/26/2023540257158Open ↗
08/31/2023540257158Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
08/31/2023540257158Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
08/31/2023540257158Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
09/28/2023540257158Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
09/26/2023540257158Open ↗
▸DOB NOWEN2: As Built Energy Analysis1
08/22/2026S00744406-I1Open ↗
▸Inspections & Test Reports6
▸BISTECHNICAL REPORT: RESPONSIBILITY2
09/26/2023540257158Open ↗
08/31/2023540257158Open ↗
▸DOB NOWSOIL REPORT2
08/22/2026S00744406-I1Open ↗
08/22/2026S00744406-P1Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/22/2026S00744406-I1Open ↗
▸DOB NOWTR4 Plot Diagram1
08/22/2026S00744406-I1Open ↗
▸Approvals, Objections & Sign-offs2
▸BISLETTERS - SUPPORTING DOCUMENTATION1
09/27/2023540257158Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
10/05/2023540257158Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT1
08/31/2023540257158Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
09/26/2023540257158Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
08/31/2023540257158Open ↗
▸Other Documents8
▸DOB NOWSite Survey: Initial2
08/22/2026S00744406-I1Open ↗
08/22/2026S00744406-P1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/22/2026S00744406-P1Open ↗
08/22/2026S00744406-I1Open ↗
▸DOB NOWProperty Ownership Certification2
08/22/2026S00744406-P1Open ↗
08/22/2026S00744406-I1Open ↗
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
09/27/2023540257158Open ↗
▸DOB NOWFinal Survey1
08/22/2026S00744406-I1Open ↗