| Owner | Filings | Most Recent |
|---|---|---|
| J G CONSTRUCTION SRVCS | 7 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ASHRAF CORP | 1 | 05/10/2024 |
| STUDIO SFW DESIGN ARCHITECTURE DPC | 5 | 04/25/2024 |
| MARTOS ENGINEERING | 1 | 07/03/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| EC BUILDING CONSULTANTS | 12 | 03/21/2026 |
| KMA DESIGNS LLC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| E.L. CONTRACTING INC | General Contractor | 7 | 07/08/2026 |
| J & G CONSTRUCTION SVCS | General Contractor | 6 | 03/21/2026 |
| GRID CITY ELECTRIC, CORP | Electrical | 1 | 03/22/2026 |
| ARCON PLBG SOLUTIONS | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CHRISTIAN L. MARTOS ENGIN | 5965 | 1 | 07/03/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | EL CONTRACTING INC | 07/29/2024 |
| DOB NOW | Structural | Signed-off | EL CONTRACTING INC | 07/10/2024 |
| DOB NOW | Supported Scaffold | Signed-off | J & G CONSTRUCTION SVCS | 05/13/2024 |
| DOB NOW | Supported Scaffold | Signed-off | J & G CONSTRUCTION SVCS | 05/13/2024 |
| DOB NOW | General Construction | Signed-off | EL CONTRACTING INC | 07/29/2023 |
| DOB NOW | Structural | Signed-off | EL CONTRACTING INC | 07/28/2023 |
| DOB NOW | Plumbing | Signed-off | ARCON PLBG SOLUTIONS | 07/27/2023 |
| DOB NOW | General Construction | Signed-off | EL CONTRACTING INC | 07/17/2023 |
| BIS | PL | ISSUED | ALAFOGIANNIS PLBG & HTG | 02/05/2020 |
| BIS | PL | ISSUED | ZARA PLUMBING CORP | 01/04/2019 |
| BIS | MH | ISSUED | E.L. CONTRACTING INC | 03/05/2018 |
| BIS | PL | RE-ISSUED | CLOVERDALE MASTER P&H INC | 02/08/2018 |
| BIS | OT | ISSUED | E.L. CONTRACTING INC | 01/17/2018 |
| BIS | MH | ISSUED | HANK CONSTRUCTION INC | 07/17/2006 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/10/2024 | Complete | RICHARD NEU | — |
| 08/10/2023 | Complete | RIVIERA ELECTRIC CORP | General Wiring |
| 02/28/2018 | Complete | GRID CITY ELECTRIC, CORP | General Wiring, Lighting |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/30/2024 | Insulation placement and R values | Ward Welch | energy_progress |
| 04/30/2024 | Lighting in dwelling units | Ward Welch | energy_progress |
| 04/30/2024 | Fenestration areas | Ward Welch | energy_progress |
| 04/30/2024 | Fenestration and door U-factor and product ratings | Ward Welch | energy_progress |
| 04/30/2024 | Energy Code Compliance Inspections | Ward Welch | progress |
| 04/30/2024 | Fenestration air leakage | Ward Welch | energy_progress |
| 04/30/2024 | Final | Ward Welch | progress |
| 04/30/2024 | Fire-Resistance Rated Construction | Ward Welch | progress |
| 04/23/2024 | Insulation placement and R values | Ward Welch | energy_progress |
| 04/23/2024 | Energy Code Compliance Inspections | Ward Welch | progress |
| 04/23/2024 | Final | Ward Welch | progress |
| 04/23/2024 | Fire-Resistance Rated Construction | Ward Welch | progress |
| 04/23/2024 | Fenestration air leakage | Ward Welch | energy_progress |
| 04/23/2024 | Lighting in dwelling units | Ward Welch | energy_progress |
| 04/23/2024 | Fenestration and door U-factor and product ratings | Ward Welch | energy_progress |
| 04/23/2024 | Fenestration areas | Ward Welch | energy_progress |
| 06/21/2023 | Masonry | Christian Martos | special |
| 06/21/2023 | Structural Steel - Details | Christian Martos | special |
| 06/21/2023 | Post-installed Anchors | Christian Martos | special |
| 06/21/2023 | Structural Wood Frame | Christian Martos | progress |
| 06/21/2023 | Structural Steel - Welding | Christian Martos | special |
| 06/21/2023 | Structural Steel - High Strength Bolting | Christian Martos | special |
| 06/20/2023 | Final | Christian Martos | progress |
| 06/20/2023 | Structural Stability – Alterations of existing buildings | Christian Martos | special |