| Owner | Filings | Most Recent |
|---|---|---|
| LIPSITZ PROPERTY GROUP | 15 | 07/08/2026 |
| MA CONDOMINIUM ASSOC. C/O | 2 | 03/22/2026 |
| MA CONDOMUNIUM ASSOC C/O | 1 | 03/22/2026 |
| 43 MURRAYLLC | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| IDA GALEA, ARCHITECT | 8 | 02/18/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| IDA GALEA, ARCHITECT | 12 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TROY CONSTRUCTION OF NY INC. | General Contractor | 4 | 07/08/2026 |
| GSA ELECTRIC CORP. | Electrical | 1 | 03/22/2026 |
| JOSEPH LA VOLPE | Electrical | 1 | 03/21/2026 |
| ?LEONARD SCHIFFMAN | Electrical | 1 | 03/21/2026 |
| S & J INDUSTRIAL CORP | Fire Protection | 1 | 07/08/2026 |
| S & J INDUSTRIAL CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| STEVEN KUO | 4979 | 8 | 02/18/2025 |
| G ENGINEERING PC | 7778 | 2 | 02/17/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | TROY CONSTRUCTION OF NY I | 08/20/2024 |
| DOB NOW | General Construction | Signed-off | TROY CONSTRUCTION OF NY I | 08/20/2024 |
| DOB NOW | Sprinklers | Signed-off | S & J INDUSTRIAL CORP | 06/04/2024 |
| DOB NOW | Plumbing | Permit Issued | S & J INDUSTRIAL CORP | 06/04/2024 |
| DOB NOW | Mechanical Systems | Signed-off | TROY CONSTRUCTION OF NY I | 05/10/2024 |
| DOB NOW | General Construction | Signed-off | TROY CONSTRUCTION OF NY I | 05/07/2024 |
| BIS | PL | ISSUED | TMS PLBG & HEATING CORP | 09/26/2018 |
| BIS | OT | ISSUED | KBRNY, INC | 09/25/2018 |
| BIS | PL | ISSUED | MARCO POLO PLBG & HTG INC | 07/17/2013 |
| BIS | OT | ISSUED | KINGS STAR CONSTRUCTION C | 07/16/2013 |
| BIS | FP | ISSUED | ACTIVE FIRE CONTROL, INC | 01/25/2010 |
| BIS | PL | ISSUED | THE PLUMBING CO., INC. | 07/23/2008 |
| BIS | MH | ISSUED | EFRICOLOR INC | 07/16/2008 |
| BIS | OT | ISSUED | EFRICOLOR INC | 07/16/2008 |
| BIS | FP | ISSUED | RELIABLE FIRE PROTECTION INC. | 04/11/2008 |
| BIS | FP | ISSUED | ACTIVE FIRE EXTING CO., INC | 03/03/2006 |
| BIS | OT | ISSUED | UNITECH DESIGN INC | 11/03/2003 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/18/2025 | Permit Issued | S & J INDUSTRIAL CORP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/26/2024 | Permit Issued | ACCURATE ELEC'L CONSTR & | General Wiring |
| 06/03/2024 | Complete | ACCURATE ELEC'L CONSTR & | General Wiring |
| 01/29/2019 | Complete | GSA ELECTRIC CORP. | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/27/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 01/29/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/27/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/10/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/10/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/19/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/29/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/18/2025 | Fire-Resistant Penetrations and Joints | FENG-BAO LIN | special |
| 02/18/2025 | Post-installed Anchors | XIONGCAI GU | special |
| 02/18/2025 | Sprinkler Systems | FENG-BAO LIN | special |
| 02/18/2025 | Fire-Resistant Penetrations and Joints | FENG-BAO LIN | special |
| 02/13/2025 | HVAC-R and service water heating equipment | FENG-BAO LIN | energy_progress |
| 02/13/2025 | Electrical motors and elevators | FENG-BAO LIN | energy_progress |
| 02/13/2025 | HVAC-R and service water heating system controls | FENG-BAO LIN | energy_progress |
| 02/13/2025 | Maintenance information | FENG-BAO LIN | energy_progress |
| 02/13/2025 | HVAC-R and service water piping design and insulation | FENG-BAO LIN | energy_progress |
| 02/13/2025 | Fire-Resistant Penetrations and Joints | FENG-BAO LIN | special |
| 02/13/2025 | Fire-Resistance Rated Construction | FENG-BAO LIN | progress |
| 02/13/2025 | Energy Code Compliance Inspections | FENG-BAO LIN | progress |
| 02/13/2025 | Final | FENG-BAO LIN | progress |
| 02/13/2025 | Interior lighting power | FENG-BAO LIN | energy_progress |
| 02/13/2025 | Lighting controls | FENG-BAO LIN | energy_progress |
| 02/13/2025 | Metering | FENG-BAO LIN | energy_progress |
| 02/13/2025 | Heating Systems | FENG-BAO LIN | special |
| 02/13/2025 | Mechanical Systems | FENG-BAO LIN | special |
| 02/13/2025 | Final | FENG-BAO LIN | progress |
| 02/12/2025 | Fire-Resistant Penetrations and Joints | FENG-BAO LIN | special |