| Owner | Filings | Most Recent |
|---|---|---|
| 41 NORTH MOORE ST CONDO | 13 | 07/08/2026 |
| 77 HUDSON | 5 | 03/22/2026 |
| 77 HUDSIN INC. | 1 | 03/22/2026 |
| HUDSON | 1 | 03/22/2026 |
| NORTH MOORE CONDO ASSOCIATIO | 9 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ACCARDO ENGINEERING, PLLC | 2 | 04/30/2026 |
| ENTHINK ENGINEERING LLC | 1 | 04/17/2026 |
| POLISE CONSULTING ENGINEERS DPC | 2 | 09/09/2024 |
| MOLONEY CONSULTING ENGINEERING PLLC | 1 | 08/15/2024 |
| STUDIO DB ARCHITECTURE DPC | 1 | 08/08/2024 |
| TODD ZWIGARD ARCHITECTS | 2 | 12/14/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| JAM CONSULTANTS, INC. | 4 | 03/21/2026 |
| WILLIAM VITACCO ASSOCIATES | 4 | 03/21/2026 |
| D D EXPEDITORS | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| OBRA CONSTRUCTION CORP | General Contractor | 8 | 07/08/2026 |
| POLER CONSTRUCTION INC | General Contractor | 4 | 07/08/2026 |
| SIMONSAYS CORP | General Contractor | 3 | 07/08/2026 |
| ABR PLBG&HTG CONTR INC | Plumbing | 3 | 09/02/2026 |
| A.MIRANDA CONTRACTING COR | Electrical | 1 | 03/21/2026 |
| A.M.N. CORPORATION | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ACCARDO ENGINEERING, PLLC | 1247 | 2 | 04/30/2026 |
| SAG ENGINEERING & CONSULT | 608 | 2 | 04/30/2026 |
| CATALPA SPECIAL INSPECTIO | 2004 | 4 | 09/09/2024 |
| STUDIO DB LLC | 7533 | 1 | 08/08/2024 |
| CROSSCHECK INSPECTION SER | 544 | 1 | 12/14/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | ABR PLBG&HTG CONTR INC | 09/01/2026 |
| DOB NOW | General Construction | Permit Issued | POLER CONSTRUCTION INC | 06/04/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | POLER CONSTRUCTION INC | 06/03/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | POLER CONSTRUCTION INC | 05/08/2026 |
| DOB NOW | General Construction | Permit Issued | OBRA CONSTRUCTION CORP | 05/08/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | OBRA CONSTRUCTION CORP | 05/08/2026 |
| DOB NOW | General Construction | Permit Issued | POLER CONSTRUCTION INC | 02/20/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | OBRA CONSTRUCTION | 02/11/2026 |
| DOB NOW | General Construction | Permit Issued | OBRA CONSTRUCTION | 02/11/2026 |
| DOB NOW | General Construction | Permit Issued | OBRA CONSTRUCTION | 12/30/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | OBRA CONSTRUCTION | 12/30/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | OBRA CONSTRUCTION | 10/01/2025 |
| DOB NOW | Plumbing | Permit Issued | ABR PLBG&HTG CONTR INC | 10/01/2025 |
| DOB NOW | Plumbing | Permit Issued | ABR PLBG&HTG CONTR INC | 05/13/2025 |
| DOB NOW | General Construction | Permit Issued | OBRA CONSTRUCTION | 05/13/2025 |
| DOB NOW | General Construction | Signed-off | SIMONSAYS CORP | 02/28/2022 |
| DOB NOW | Plumbing | Signed-off | A.M.N. CORPORATION | 01/25/2022 |
| DOB NOW | General Construction | Signed-off | SIMONSAYS CORP | 01/24/2022 |
| BIS | EQ | ISSUED | SPRING SCAFFOLDING LLC | 12/31/2014 |
| BIS | OT | ISSUED | WEST NEW YORK RESTORATION OF CT | 08/22/2014 |
| BIS | EQ | ISSUED | WEST NEW YORK RESTORATION OF CT | 08/19/2014 |
| BIS | EQ | ISSUED | WEST NEW YORK RESTORATION OF CT | 07/21/2014 |
| BIS | PL | ISSUED | ORBIT PLBG & HTG INC | 06/11/2014 |
| BIS | OT | ISSUED | JEPOL CONSTRUCTION INC | 03/13/2014 |
| BIS | EQ | ISSUED | SPRING SCAFFOLDING LLC | 12/23/2013 |
| BIS | EQ | ISSUED | SPRING SCAFFOLDING LLC | 09/26/2013 |
| BIS | OT | ISSUED | JEPOL CONSTRUCTION INC | 04/02/2013 |
| BIS | EQ | ISSUED | JEPOL CONSTRUCTION INC | 04/02/2013 |
| BIS | BL | ISSUED | L.R.P. CORP | 03/23/2004 |
| BIS | PL | ISSUED | L.R.P. CORP | 03/23/2004 |
| BIS | PL | ISSUED | NEW YORK STANDARD MECH CORP | 05/13/2002 |
| BIS | PL | ISSUED | NEW YORK STANDARD MECH CORP | 05/13/2002 |
| BIS | SP | ISSUED | S.M. PIPING AND HEATING | 04/09/2002 |
| BIS | OT | ISSUED | TRIARCH ARCH SERVICES PC3 | 08/31/1999 |
| BIS | MH | ISSUED | TRIARCH ARCH SERVICES PC | 08/31/1999 |
| BIS | PL | ISSUED | PRONTO PLUMBING | 07/22/1999 |
| BIS | — | ISSUED | TRIARCH ARCHITECTURAL SERVICES | 04/22/1999 |
| BIS | MH | ISSUED | TRIARCH ARCH SERVICES PC | 05/21/1998 |
| BIS | PL | ISSUED | PRONTO PLG & HTG CORP | 08/27/1997 |
| BIS | OT | ISSUED | TRIARCH ARCH SERVICES PC3 | 08/07/1997 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/09/2024 | Permit Issued | ABR PLBG&HTG CONTR INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/29/2025 | Permit Issued | WMS ELECTRICAL CONTNG LTD | General Wiring |
| 12/05/2023 | Complete | DECECK & LEONARD,INC | General Wiring |
| 11/07/2022 | Complete | BERGER QUALITY ELEC'L CON | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/30/2026 | Permit Issued | POLER CONSTRUCTION INC | Steel, Wood |
| 09/09/2024 | Permit Issued | ABR PLBG&HTG CONTR INC | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/30/2026 | Permit Issued | POLER CONSTRUCTION INC | Scaffold |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/26/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/22/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/02/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 10/02/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/04/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/08/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/08/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/27/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/28/2026 | Post-installed Anchors | Chester Kowalski | special |
| 04/28/2026 | Final | Anthony Accardo | progress |
| 04/28/2026 | Wood – Seismic Resistance | — | special |
| 04/28/2026 | Structural Steel - Details | Anthony Accardo | special |
| 04/28/2026 | Tenant Protection Plan Compliance | Chester Kowalski | special |
| 04/28/2026 | Structural Steel - Welding | Anthony Accardo | special |
| 04/28/2026 | Structural Steel - High Strength Bolting | Anthony Accardo | special |
| 05/06/2024 | Structural Stability – Alterations of existing buildings | — | special |
| 05/06/2024 | Masonry | — | special |
| 05/06/2024 | Post-installed Anchors | ERIC BERLENT | special |
| 05/06/2024 | Fire-Resistant Penetrations and Joints | ERIC BERLENT | special |
| 05/06/2024 | Structural Steel - High Strength Bolting | — | special |
| 04/18/2024 | Structural Steel - Details | — | special |
| 04/18/2024 | Tenant Protection Plan Compliance | ERIC BERLENT | special |
| 04/12/2024 | Final | — | progress |
| 04/12/2024 | Tenant Protection Plan Compliance | — | special |
| 04/11/2024 | Tenant Protection Plan Compliance | ERIC BERLENT | special |
| 04/11/2024 | Tenant Protection Plan Compliance | ERIC BERLENT | special |
| 03/27/2024 | Fire-Resistant Penetrations and Joints | DAMIAN ZUNINO | special |
| 03/27/2024 | Fire-Resistance Rated Construction | DAMIAN ZUNINO | progress |
| 03/27/2024 | Energy Code Compliance Inspections | DAMIAN ZUNINO | progress |
| 12/22/2023 | Mechanical Systems | ERIC BERLENT | special |
| 12/22/2023 | Final | DAMIAN ZUNINO | progress |
| 12/22/2023 | Final | ERIC BERLENT | progress |
| 11/15/2021 | Fire-Resistance Rated Construction | EUGENE BIFULCO | progress |