Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 5Sprinkler work, cellar through 5th floor3p · 1 filing · 4 docs
Fire Protection
Issued Permit Scope
Sprinklers
SPRINKLER WORK IN THE CELLAR THROUGH 5th FLOOR AS PER PLANS. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents
Floor 4Sprinkler work, cellar through 5th floor15p · 2 filings · 20 docs
ArchitectureFire Protection
Issued Permit Scope
General Construction · Sprinklers
SPRINKLER WORK IN THE CELLAR THROUGH 5th FLOOR AS PER PLANS. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents
FILING ALTERATION 1 APPLICATION TO ESTABLISH THE CERTIFICATE OF OCCUPANCY FOR RESIDENTIAL BUILDING.
On file for this project
24 documents
Floor 3Sprinkler work, cellar through 5th floor21p · 3 filings · 20 docs
ArchitectureFire ProtectionPlumbing
Issued Permit Scope
General Construction · Plumbing · Sprinklers
SPRINKLER WORK IN THE CELLAR THROUGH 5th FLOOR AS PER PLANS. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents
PLUMBING WORK AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
8 documents
FILING ALTERATION 1 APPLICATION TO ESTABLISH THE CERTIFICATE OF OCCUPANCY FOR RESIDENTIAL BUILDING.
On file for this project
24 documents
Floor 2Sprinkler work, cellar through 5th floor22p · 3 filings · 20 docs
ArchitectureFire ProtectionPlumbing
Issued Permit Scope
General Construction · Plumbing · Sprinklers
SPRINKLER WORK IN THE CELLAR THROUGH 5th FLOOR AS PER PLANS. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents
PLUMBING WORK AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
8 documents
FILING ALTERATION 1 APPLICATION TO ESTABLISH THE CERTIFICATE OF OCCUPANCY FOR RESIDENTIAL BUILDING.
On file for this project
24 documents · 1 drawing sheet
Floor 1Sprinkler work, cellar through 5th floor21p · 3 filings · 20 docs
ArchitectureFire ProtectionPlumbing
Issued Permit Scope
General Construction · Plumbing · Sprinklers
SPRINKLER WORK IN THE CELLAR THROUGH 5th FLOOR AS PER PLANS. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents
PLUMBING WORK AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
8 documents
FILING ALTERATION 1 APPLICATION TO ESTABLISH THE CERTIFICATE OF OCCUPANCY FOR RESIDENTIAL BUILDING.
On file for this project
24 documents
CellarSprinkler work, cellar through 5th floor22p · 3 filings · 20 docs
ArchitectureDMFire ProtectionPlumbing
Issued Permit Scope
General Construction · Plumbing · Sprinklers
SPRINKLER WORK IN THE CELLAR THROUGH 5th FLOOR AS PER PLANS. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents
PLUMBING WORK AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
8 documents · 1 drawing sheet
FILING ALTERATION 1 APPLICATION TO ESTABLISH THE CERTIFICATE OF OCCUPANCY FOR RESIDENTIAL BUILDING.
On file for this project
24 documents · 1 drawing sheet
Basement13p · 1 filing · 20 docs
Architecture
Issued Permit Scope
General Construction
FILING ALTERATION 1 APPLICATION TO ESTABLISH THE CERTIFICATE OF OCCUPANCY FOR RESIDENTIAL BUILDING.
On file for this project
24 documents · 1 drawing sheet
Sub-BasementSprinkler work, cellar through 5th floor9p · 2 filings · 12 docs
Fire ProtectionPlumbing
Issued Permit Scope
Plumbing · Sprinklers
SPRINKLER WORK IN THE CELLAR THROUGH 5th FLOOR AS PER PLANS. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
4 documents
PLUMBING WORK AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
8 documents
Site & exteriorInstallation of sidewalk shed8p · 2 filings · 4 docs
ArchitectureElectricalGeneralMechanical
Issued Permit Scope
Sidewalk Shed · Supported Scaffold
Installation of sidewalk shed as indicated on the attcahed drawings. There are no changes in use, egress or occupancy.
On file for this project
2 documents · 4 drawing sheets
INSTALLATION OF SUPPORT SCAFFOLDING AS INDICATED ON THE ATTACHED DRAWINGS. THERE ARE NO CHANGES IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents · 4 drawing sheets