← Back
Condo, residential tower (mixed-use, multi-family elevator) [derived]
The Alexander Court Condominium
4102 13 AVENUE · BIN 3412923
💬 Discuss this project
2007Year Built
6Stories
RMBuilding Class
R6Zoning
38,043 sfGross Floor Area
37Units
LL97 CoveredRent Stabilized11 Open Violations ▸FISP: No Report FiledFDNY Report ↗
Condo, residential tower (mixed-use, multi-family elevator) [derived] · Owner of record: THE ALEXANDER COURT CONDOMINIUM · 8,115 sf lot · 4.69 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalMechanicalPlumbingGeneral
Roof12p · 5 filings · 20 docs
Floor 61p · 1 filing · 15 docs
Floor 51p · 1 filing · 15 docs
Floor 41p · 1 filing · 15 docs
Floor 31p · 1 filing · 15 docs
Floor 22p · 2 filings · 20 docs
Floor 11p · 1 filing · 15 docs
Cellar3p · 1 filing · 15 docs
Sub-Basement2 filings · 7 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
4102 13TH AVENUE DEVELOPMENT3809/13/2026
DISH WIRELESS307/08/2026
13TH AVE DEVELOPMENT C303/22/2026
4102 13TH AV DEV LLC203/22/2026
4102 13TH AVENUE LLC103/22/2026
TO THE OWNER OF403/22/2026
4102 13TH AVENUE DEVELOPEMENTLLC203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
COHEN ENTERPRISES405/11/2026
NEW AGE ENGINEERING PLLC109/04/2024
TECTON ARCHITECTS103/13/2024
KMB DESIGN GROUP, LLC106/20/2022
AZIMUTH ENGINEERING203/22/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
RIZZO GROUP403/21/2026
CONSTRUCTION PERMIT SERVICES103/21/2026
JENNY FLORES EXPEDITING103/21/2026
BOHLER ENGINEERING103/21/2026
CCM CONSULTING GROUP, INC.303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DIGITAL CONSTRUCTION TECHGeneral Contractor404/09/2026
RAMAPO COMMUNICATION CORPGeneral Contractor303/21/2026
SWEET & LOWE LLCGeneral Contractor303/21/2026
HYDRO MECHANICAL INCPlumbing207/30/2026
SPECTRUM CONNECTIONS CORPGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
COHEN ENTERPRISES & E9511405/11/2026
NEW AGE ENGINEERING PLLC7746109/04/2024
KMB DESIGN GROUP, LLC513106/20/2022
JEREMY K MCKEON, P.E.7263203/22/2021
Building Lifecycle
All (90)Filed (9)Permit Issued (7)Signed Off (2)Violation (48)Inspection (3)Objection (8)Special Inspection (13)
08/11/2026
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
07/29/2026
Permit issued — Plumbing
B01172100-S2-PL
05/14/2026
Special inspection requirement — Tenant Protection Plan Compliance
ALLAN COHEN
05/14/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALLAN COHEN
05/11/2026
Filed — Alteration
Installation of gas meter and gas piping as per plans. No change to occupancy, use, or egress.
B01172100-P1
05/08/2026
Violation issued (HPD, open)
A
03/03/2026
Special inspection requirement — Tenant Protection Plan Compliance
03/03/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALLAN COHEN
09/17/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
09/17/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
06/13/2025
Violation issued (HPD, open)
A
06/12/2025
Permit issued — Plumbing
B01172100-S2-PL
06/11/2025
Permit issued — Mechanical Systems
B01172100-S1-MS
06/11/2025
Permit issued — Antenna
B01172100-I1-AN
05/16/2025
Objection resolved — Addressed
05/09/2025
Objection raised — Structural
04/23/2025
Filed — Alteration
Installation of gas meter and gas piping as per plans. No change to occupancy, use, or egress.
B01172100-S1
04/23/2025
Filed — Alteration
Installation of gas meter and gas piping as per plans. No change to occupancy, use, or egress.
B01172100-I1
04/23/2025
Filed — Alteration
Installation of gas meter and gas piping as per plans. No change to occupancy, use, or egress.
B01172100-S2
04/08/2025
Violation issued (ECB, open)
Local Law
11/27/2024
Violation issued (HPD, closed)
I
10/23/2024
Signed off — Alteration
INSTALL NEW CONDENSERS AND AIR HANDLER UNITS AS PER PLANS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS
B01081545-I1
10/21/2024
Permit issued — Mechanical Systems
B01081545-I1-MS
09/04/2024
Filed — Alteration
INSTALL NEW CONDENSERS AND AIR HANDLER UNITS AS PER PLANS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS
B01081545-I1
09/04/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Stephen Shishko
09/04/2024
Special inspection requirement — HVAC-R and service water heating equipment
Stephen Shishko
08/02/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
07/16/2024
Special inspection requirement — Maintenance information
Stephen Shishko
07/16/2024
Special inspection requirement — Mechanical Systems
Stephen Shishko
07/16/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Stephen Shishko
07/16/2024
Special inspection requirement — Final
Stephen Shishko
07/16/2024
Special inspection requirement — Tenant Protection Plan Compliance
Stephen Shishko
06/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
05/02/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
04/17/2024
Violation issued (HPD, open)
A
03/13/2024
Filed — Alteration
B00989107-I1
02/22/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
01/11/2024
Special inspection requirement — Final
01/11/2024
Special inspection requirement — Tenant Protection Plan Compliance
12/01/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/21/2023
Violation issued (HPD, closed)
I
05/02/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
03/31/2023
Violation issued (HPD, open)
A
12/02/2022
Signed off — Alteration
B00511066-I1
08/02/2022
Permit issued — Antenna
B00511066-I1-AN
06/20/2022
Filed — Alteration
B00511066-I1
05/17/2022
Permit issued — Antenna
B00407185-I1-AN
03/22/2021
Filed — Alteration
B00464310-I1
12/23/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/02/2020
Objection raised — 1998-AN AC 28-103.14.1-Adminis
11/02/2020
Objection resolved — Addressed
11/02/2020
Objection raised — 2014-AN BC 1704-Building Code-
11/02/2020
Objection resolved — Addressed
11/02/2020
Objection raised — 2014-AN AC 28-104.7.1-Administ
11/02/2020
Objection resolved — Addressed
10/30/2020
Filed — Alteration
INSTALLATION OF (4) NEW ANTENNA SECTORS AND (1) EQUIPMENT CABINET ON THE ROOFTOP (STARRY - S-NYCBRK0045-C) AS PER PLANS. ALL WORK IS IN COMPLIANCE WITH TPPN 5/98. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
B00407185-I1
09/28/2020
Violation issued (ECB, closed)
Elevators
12/18/2019
Violation issued (ECB, closed)
Elevators
11/02/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/02/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Latest 60 of 90 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offHYDRO MECHANICAL INC07/29/2026
DOB NOWPlumbingSigned-offHYDRO MECHANICAL INC06/12/2025
DOB NOWMechanical SystemsPermit IssuedDIGITAL CONSTRUCTION TECH06/11/2025
DOB NOWAntennaPermit IssuedDIGITAL CONSTRUCTION TECH06/11/2025
DOB NOWMechanical SystemsSigned-offSWEET & LOWE LLC10/21/2024
DOB NOWAntennaPermit IssuedSPECTRUM CONNECTIONS CORP08/02/2022
DOB NOWAntennaPermit IssuedRAMAPO COMMUNICATION CORP05/17/2022
BISOTISSUEDPARKER SVC INDUSTRIES COR09/18/2017
BISOTISSUEDPARKER SVC INDUSTRIES COR09/18/2017
BISOTISSUEDPARKER SVC INDUSTRIES COR09/15/2017
BISOTISSUEDCONSTRUCTION RESOURCES12/09/2016
BISOTISSUEDCONSTRUCTION RESOURCES08/10/2016
BISPLISSUEDALESSANDRO PLUMBING, INC08/10/2016
BISPLISSUEDACCURATE MECHANICAL INC10/01/2009
BISPLISSUEDACCURATE MECHANICAL INC08/05/2008
BISEQISSUEDOCEAN AVE CONST INC04/08/2008
BIS—ISSUEDOCEAN AVE CONST INC04/08/2008
BISEQISSUEDOCEAN AVE CONST INC01/09/2008
BISEQISSUEDOCEAN AVE CONST INC03/16/2007
BIS—ISSUEDOCEAN AVE CONST INC03/16/2007
BISEQISSUEDOCEAN AVE CONST INC01/04/2007
BIS—ISSUEDOCEAN AVE CONST INC10/24/2006
BISEQISSUEDOCEAN AVE CONST INC10/24/2006
1 project · most recent 05/11/2026
Generators
FiledStatusContractorScopeMake / Model / Capacity
05/11/2026Permit IssuedDIGITAL CONSTRUCTION TECHGenerators
Generators
Accardi Companies MD101-1/4 REG-48V-ODE-AT&T Pump ×1
Polar Power 8220-100-NG/LPG-20-03 Generator ×1
1 project · most recent 05/11/2026
Gas
FiledStatusContractorScope
05/11/2026Signed-offHYDRO MECHANICAL INCGas
6 projects · most recent 09/24/2026
General Wiring Lighting
FiledStatusContractorScope
09/24/2026Permit IssuedJ.H. ELEC. OF NEW YORK INGeneral Wiring
11/19/2025Permit IssuedCITI-WIDE ELECTRIC INCGeneral Wiring
11/29/2022Permit IssuedSTAR ELEC'L CONTRACTORS C—
08/29/2022Permit IssuedTIMOTHY COLEMAN LICENSEDGeneral Wiring
06/25/2021CompleteCANDELA SYSTEMS CORP DBALighting
01/23/2020Permit IssuedCONTACT PLUS ELEC'L CORPGeneral Wiring
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
08/11/2026Pass-Final PL - Up to 9 Requested FloorsPassView ↗
09/17/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
09/17/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 13
DateRequirementInspectorRole
05/14/2026Tenant Protection Plan ComplianceALLAN COHENspecial
05/14/2026Fire-Resistant Penetrations and JointsALLAN COHENspecial
03/03/2026Tenant Protection Plan Compliance—special
03/03/2026Fire-Resistant Penetrations and JointsALLAN COHENspecial
09/04/2024HVAC-R and service water piping design and insulationStephen Shishkoenergy_progress
09/04/2024HVAC-R and service water heating equipmentStephen Shishkoenergy_progress
07/16/2024Maintenance informationStephen Shishkoenergy_progress
07/16/2024Mechanical SystemsStephen Shishkospecial
07/16/2024Fire-Resistant Penetrations and JointsStephen Shishkospecial
07/16/2024FinalStephen Shishkoprogress
07/16/2024Tenant Protection Plan ComplianceStephen Shishkospecial
01/11/2024Final—progress
01/11/2024Tenant Protection Plan Compliance—special
▾Documents — 103 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch7
08/29/2026B00511066-I1Request digital key ↗
08/25/2026B00989107-I1Request digital key ↗
08/24/2026B01081545-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸DOB NOWPlans/Sketch - General Construction1
09/01/2026B00464310-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Antenna1
08/14/2026B00407185-I1Request digital key ↗
▸Applications & Permits11
▸BISWORK PERMIT APPLICATION6
09/22/2017321624051Open ↗
09/22/2017321624060Open ↗
09/20/2017321624042Open ↗
Showing 3 of 6 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION5
08/08/2017321624051Open ↗
08/08/2017321624060Open ↗
08/08/2017321624042Open ↗
Showing 3 of 5 on file for this type
▸Seals & Professional Certifications38
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION9
05/31/2018321624060Open ↗
05/31/2018321624051Open ↗
05/31/2018321624042Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature9
09/02/2026B00407185-I1Open ↗
09/01/2026B00464310-I1Open ↗
08/29/2026B00511066-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
09/27/2026B01172100-P1Open ↗
09/01/2026B01172100-S2Open ↗
09/01/2026B01172100-S2Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST4
08/08/2017321624051Open ↗
08/08/2017321624042Open ↗
05/13/2016321379254Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
08/28/2026B01081545-I1Open ↗
08/28/2026B01081545-I1Open ↗
08/28/2026B01081545-I1Open ↗
Showing 3 of 4 on file for this type
▸BISProfessional and Owner Certification (POC3)3
08/08/2017321624051Open ↗
08/08/2017321624060Open ↗
08/08/2017321624060Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
08/08/2017321624042Open ↗
05/13/2016321379254Open ↗
05/13/2016321379254Open ↗
▸Trade Schedules & Equipment2
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
05/13/2016321379254Open ↗
▸DOB NOWFDNY: Letter of No Objection1
08/13/2026B00407185-I1Open ↗
▸Safety & Tenant Protection1
▸DOB NOWTenant Protection Plan1
08/13/2026B00407185-I1Open ↗
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
09/01/2026B00464310-I1Open ↗
08/17/2026B01172100-P1Open ↗
08/17/2026B01172100-S1Open ↗
Showing 3 of 6 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
05/13/2016321379254Open ↗
▸Energy Compliance14
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS10
05/31/2018321624060Open ↗
05/31/2018321624051Open ↗
05/31/2018321624042Open ↗
Showing 3 of 10 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
05/31/2018321624060Open ↗
05/31/2018321624051Open ↗
05/31/2018321624042Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026B00511066-I1Open ↗
▸Approvals, Objections & Sign-offs4
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST4
05/31/2018321624060Open ↗
05/31/2018321624051Open ↗
05/31/2018321624042Open ↗
Showing 3 of 4 on file for this type
▸Cost, Insurance & Ownership9
▸BISCOST AFFIDAVIT9
05/31/2018321624060Open ↗
05/31/2018321624051Open ↗
05/31/2018321624042Open ↗
Showing 3 of 9 on file for this type
▸Filing & Intake Forms8
▸BISEFILING COVER SHEET5
08/10/2017321624060Open ↗
08/10/2017321624042Open ↗
08/10/2017321624051Open ↗
Showing 3 of 5 on file for this type
▸BISBOROUGH INTAKE FORM3
05/31/2018321624060Open ↗
05/31/2018321624051Open ↗
05/31/2018321624042Open ↗