← Back
One family attached or semi-detached
4119 PAULDING AVENUE
BRONX · BIN 2064608
💬 Discuss this project
1925Year Built
2Stories
A5Building Class
R4Zoning
1,344 sfGross Floor Area
1Units
One family attached or semi-detached · 1,900 sf lot · 0.71 FAR built · Flood zone X
Locations of Work
Architecture
Roof3p · 1 filing · 7 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
11/13/2024$595K—— → —$443/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
UNISOLAR104/28/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CENTURION SOLAR ENERGYGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CENTURION SOLAR ENERGY LL9475104/28/2025
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
10/22/2025
Signed off — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONICGENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS OR OCCUPANCY.*
X01215846-I1
05/13/2025
Permit issued — Solar
X01215846-I1-SL
04/28/2025
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONICGENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS OR OCCUPANCY.*
X01215846-I1
04/24/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Andres Arias Londono
04/24/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Andres Arias Londono
04/24/2025
Special inspection requirement — Energy Code Compliance Inspections
Andres Arias Londono
04/24/2025
Special inspection requirement — Final
Andres Arias Londono
04/24/2025
Special inspection requirement — Air barrier - visual inspection
Andres Arias Londono
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offCENTURION SOLAR ENERGY05/13/2025
2 projects · most recent 08/06/2025
General Wiring
FiledStatusContractorScope
08/06/2025CompleteVILLAGE ELECTL CONTRS INCGeneral Wiring
04/24/2025CompleteBERGER QUALITY ELEC'L CON—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
04/24/2025Fire-Resistant Penetrations and JointsAndres Arias Londonospecial
04/24/2025Structural Stability – Alterations of existing buildingsAndres Arias Londonospecial
04/24/2025Energy Code Compliance InspectionsAndres Arias Londonoprogress
04/24/2025FinalAndres Arias Londonoprogress
04/24/2025Air barrier - visual inspectionAndres Arias Londonoenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/19/2026X01215846-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
09/21/2026X01215846-I1Open ↗
09/21/2026X01215846-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/19/2026X01215846-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
09/21/2026X01215846-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/19/2026X01215846-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026X01215846-I1Open ↗