← Back
Two family brick
412 TORRY AVENUE
BRONX · BIN 2021104
💬 Discuss this project
1970Year Built
3Stories
B1Building Class
R5Zoning
2,710 sfGross Floor Area
2Units
7 Open Violations 6 unresolved · 1 paperwork only ▸FDNY Report ↗
Two family brick · 2,706 sf lot · 1 FAR built · Flood zone X
Locations of Work
Architecture
Floor 21p · 1 filing · 6 docs
Floor 1
Basement1p · 1 filing · 6 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
04/02/2024$885K—— → —$327/sf building
05/17/2022$605K—— → —$223/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ERROL MCINTOSH, R.A., P.C.301/08/2026
Building Lifecycle
All (56)Filed (3)Violation (7)Objection (33)Special Inspection (13)
05/04/2026
Objection resolved — Addressed
04/30/2026
Objection resolved — Open
04/15/2026
Objection resolved — Resolved
03/30/2026
Special inspection requirement — Maintenance information
03/30/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
03/04/2026
Objection resolved — Addressed
03/04/2026
Special inspection requirement — Fenestration areas
03/04/2026
Special inspection requirement — HVAC-R and service water heating system controls
03/04/2026
Special inspection requirement — Interior lighting power
03/04/2026
Special inspection requirement — Air barrier - visual inspection
03/04/2026
Special inspection requirement — Electric vehicle service equipment requirements
03/04/2026
Special inspection requirement — Permanent certificate
03/04/2026
Special inspection requirement — Fenestration air leakage
03/04/2026
Special inspection requirement — Metering
03/04/2026
Special inspection requirement — Energy Code Compliance Inspections
03/04/2026
Special inspection requirement — Insulation placement and R values
03/04/2026
Special inspection requirement — Fire-Resistance Rated Construction
01/29/2026
Objection raised — Fire_Protection
01/29/2026
Objection raised — Fire_Protection
01/29/2026
Objection raised — Fire_Protection
01/29/2026
Objection raised — Fire_Protection
01/08/2026
Filed — Alteration
INSTALL SPRINKLER SYSTEM.
X01096470-S1
12/26/2025
Objection resolved — Addressed
12/26/2025
Objection resolved — Addressed
12/26/2025
Objection resolved — Addressed
05/20/2025
Objection resolved — Addressed
05/20/2025
Objection resolved — Addressed
05/20/2025
Objection resolved — Addressed
05/20/2025
Objection resolved — Addressed
05/20/2025
Objection resolved — Addressed
05/20/2025
Objection resolved — Addressed
05/20/2025
Objection resolved — Addressed
12/16/2024
Objection raised — Zoning
12/16/2024
Objection raised — Scope
12/16/2024
Objection raised — Fire_Protection
12/16/2024
Objection raised — Scope
12/16/2024
Objection raised — Zoning
12/16/2024
Objection raised — Zoning
12/16/2024
Objection raised — Structural
12/16/2024
Objection raised — Zoning
12/16/2024
Objection raised — Inspections
12/16/2024
Objection raised — Energy
12/16/2024
Objection raised — Fire_Protection
12/16/2024
Objection raised — Admin
12/16/2024
Objection raised — Fire_Protection
12/16/2024
Objection raised — Fire_Protection
12/03/2024
Objection raised — Scope
12/02/2024
Filed — Alteration CO
CONVERT EXISTING 2 FAMILY INTO A 3 FAMILY DWELLING.
X01093851-I1
11/25/2024
Filed — Alteration
INSTALL SPRINKLER SYSTEM.
X01096470-I1
09/10/2007
Violation issued (ECB, open)
HPD
07/27/2007
Violation issued (HPD, open)
B
07/27/2007
Violation issued (HPD, open)
C
07/27/2007
Violation issued (HPD, open)
C
07/27/2007
Violation issued (HPD, open)
B
07/27/2007
Violation issued (HPD, open)
B
07/27/2007
Violation issued (HPD, open)
B
Nothing on file for this building.
1 project · most recent 01/08/2026
FiledStatusContractorScope
01/08/2026——14 heads
1 project · most recent 01/08/2026
FiledStatusContractorScope
01/08/2026———
▾Special Inspection Requirements (DOB NOW) — 13
DateRequirementInspectorRole
03/30/2026Maintenance information—energy_progress
03/30/2026Fenestration and door U-factor and product ratings—energy_progress
03/04/2026Fenestration areas—energy_progress
03/04/2026HVAC-R and service water heating system controls—energy_progress
03/04/2026Interior lighting power—energy_progress
03/04/2026Air barrier - visual inspection—energy_progress
03/04/2026Electric vehicle service equipment requirements—energy_progress
03/04/2026Permanent certificate—energy_progress
03/04/2026Fenestration air leakage—energy_progress
03/04/2026Metering—energy_progress
03/04/2026Energy Code Compliance Inspections—progress
03/04/2026Insulation placement and R values—energy_progress
03/04/2026Fire-Resistance Rated Construction—progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/20/2026X01096470-I1Request digital key ↗
08/20/2026X01093851-I1Request digital key ↗
08/15/2026X01096470-S1Request digital key ↗
▸Zoning, Tax Lot & Property Records1
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026X01093851-I1Open ↗
▸Seals & Professional Certifications3
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/20/2026X01093851-I1Open ↗
08/13/2026X01096470-S1Open ↗
08/13/2026X01096470-I1Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/13/2026X01093851-I1Open ↗
▸Other Documents1
▸DOB NOWProperty Ownership Certification1
08/20/2026X01093851-I1Open ↗