| Owner | Filings | Most Recent |
|---|---|---|
| 413 GREENWICH STREET | 35 | 06/28/2026 |
| 413 GREENWICH CORP | 3 | 03/22/2026 |
| 484 GREENWICH ST | 1 | 03/22/2026 |
| TRIBECCA REALTY LLC. | 2 | 03/22/2026 |
| 73 CRANBERRY ST | 2 | 03/21/2026 |
| LAPP REALTY | 3 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| TSF ENGINEERING, PC | 5 | 11/24/2025 |
| ANDREW REYNIAK ARCHITECT, P.C. | 2 | 11/20/2025 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| FABRIZZIO CONSTRUCTION IN | General Contractor | 4 | 04/10/2026 |
| DOOKER, KENY | Electrical | 1 | 03/21/2026 |
| RYAN, ROBERT | Electrical | 1 | 03/21/2026 |
| VOSILLA, ALBERTO | Electrical | 1 | 03/21/2026 |
| L & N PLUMBING, INC | Plumbing | 1 | 06/28/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TSF ENGINEERING, PC | 1274 | 2 | 11/24/2025 |
| ANDREW REYNIAK ARCHITECT, | 4712 | 5 | 11/20/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | FABRIZZIO CONSTRUCTION IN | 04/08/2026 |
| DOB NOW | General Construction | Signed-off | FABRIZZIO CONSTRUCTION IN | 04/15/2025 |
| DOB NOW | Plumbing | Permit Issued | L & N PLUMBING, INC | 03/04/2025 |
| DOB NOW | General Construction | Signed-off | FABRIZZIO CONSTRUCTION IN | 01/14/2025 |
| BIS | PL | ISSUED | PACE PLUMBING CORP | 05/30/2023 |
| BIS | PL | ISSUED | PACE PLUMBING CORP | 01/10/2022 |
| BIS | SP | ISSUED | PACE PLUMBING CORP | 11/17/2020 |
| BIS | PL | ISSUED | PACE PLUMBING CORP | 11/17/2020 |
| BIS | PL | ISSUED | DO RITE MECHANICAL CORP | 10/22/2014 |
| BIS | OT | ISSUED | KEVIN BELL | 09/24/2014 |
| BIS | SP | ISSUED | METRO FIRE PROTECTION INC | 04/01/2014 |
| BIS | PL | ISSUED | NORTHEAST PLBG & HTG CORP | 03/20/2014 |
| BIS | MH | ISSUED | SUPERIOR AIR SYSTEMS MECHANICAL | 03/18/2014 |
| BIS | OT | ISSUED | PREININGER CONSTR CORP | 03/18/2014 |
| BIS | EQ | ISSUED | B & S RESTORATION INC | 03/06/2009 |
| BIS | PL | ISSUED | WAGNER ZIV PLUMBING AND HTG INC | 03/20/2007 |
| BIS | OT | ISSUED | RISE CONSTRUCTION OF NY INC | 03/09/2007 |
| BIS | OT | ISSUED | DJM CONTRACTING SERVICES CORP | 08/27/2001 |
| BIS | OT | ISSUED | DIM CONTR. CO., INC. | 08/07/2001 |
| BIS | PL | ISSUED | BRANCH PLUMBING LLC | 10/12/2000 |
| BIS | MH | ISSUED | MONACO CONSTRUCTION | 06/21/2000 |
| BIS | FP | ISSUED | IDEAL FIRE CONTROL,INC. | 07/16/1999 |
| BIS | OT | ISSUED | QUALITY MECHANICAL CONTRACTORS I | 12/08/1993 |
| BIS | PL | ISSUED | ROOTER PLUS, INC | 12/08/1993 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 11/24/2025 | Signed-off | FABRIZZIO CONSTRUCTION IN | Ventilation Systems | Ventilation Captiveaire 5418 SND-2-PSP-F 255 CFM · Kitchen Exhaust ×5 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/15/2025 | Permit Issued | L & N PLUMBING, INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/30/2025 | Complete | LAREDO ELECTRIC, INC. | General Wiring |
| 06/04/2018 | Complete | MAXIMUM ELECTRIC CORP. | General Wiring |
| 05/07/2018 | Permit Issued | MAXIMUM ELECTRIC CORP. | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/29/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/02/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/02/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/20/2025 | Pass-Final House Connection | Pass | View ↗ |
| 03/14/2025 | Fail-Final House Connection | Fail | View ↗ |
| 03/07/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/07/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/05/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/21/2025 | Fire-Resistant Penetrations and Joints | Andrew Reyniak | special |
| 11/21/2025 | Final | Andrew Reyniak | progress |
| 11/20/2025 | Mechanical Systems | Nicholas Tucci | special |
| 11/20/2025 | Final | Nicholas Tucci | progress |
| 07/10/2025 | Fire-Resistant Penetrations and Joints | Andrew Reyniak | special |
| 02/19/2025 | Fire-Resistant Penetrations and Joints | Andrew Reyniak | special |
| 02/19/2025 | Final | Andrew Reyniak | progress |