← Back
Two family brick
4146A 56 STREET
QUEENS · Woodside · BIN 4031034
💬 Discuss this project
1935Year Built
3Stories
B1Building Class
R5BZoning
2,473 sfGross Floor Area
2Units
Two family brick · 1,940 sf lot · 1.27 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralGeneral
Roof4p · 1 filing · 10 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NY BUILDING ASSOCIATES INC212/03/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BROOKLYN SOLARWORKS203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BROOKLYN SOLARWORKS LLCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NKM ENGINEERING PLLC6244212/03/2025
Building Lifecycle
All (8)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (4)
12/04/2025
Signed off — Alteration
INSTALLATION OF SOLAR PV SYSTEM. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
Q01275556-I1
12/03/2025
Filed — Alteration
INSTALLATION OF SOLAR PV SYSTEM. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
Q01275556-P1
12/03/2025
Special inspection requirement — Air barrier - visual inspection
NARESH MAHANGU
12/03/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
NARESH MAHANGU
12/03/2025
Special inspection requirement — Energy Code Compliance Inspections
NARESH MAHANGU
12/03/2025
Special inspection requirement — Final
NARESH MAHANGU
08/27/2025
Permit issued — Solar
Q01275556-I1-SL
08/25/2025
Filed — Alteration
INSTALLATION OF SOLAR PV SYSTEM. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
Q01275556-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offBROOKLYN SOLARWORKS LLC08/27/2025
1 project · most recent 08/21/2025
FiledStatusContractorScope
08/21/2025CompleteBROOKYLN SOLARWORKS, LLC—
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
12/03/2025Air barrier - visual inspectionNARESH MAHANGUenergy_progress
12/03/2025Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
12/03/2025Energy Code Compliance InspectionsNARESH MAHANGUprogress
12/03/2025FinalNARESH MAHANGUprogress
▾Documents — 10 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/18/2026Q01275556-P1Request digital key ↗
08/18/2026Q01275556-I1Request digital key ↗
▸Seals & Professional Certifications5
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/18/2026Q01275556-I1Open ↗
08/18/2026Q01275556-P1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
09/23/2026Q01275556-P1Open ↗
08/27/2026Q01275556-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
09/23/2026Q01275556-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/18/2026Q01275556-I1Open ↗
08/18/2026Q01275556-P1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01275556-I1Open ↗