| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/02/2026 | Signed-off | ALL MAKES HTG & A/C CORP | Heating and Air Conditioning Systems | Heat / Cool |
| 03/18/2026 | Permit Issued | BALOG CONSTRUCTION LLC | Heating and Air Conditioning Systems, Heating Systems | Heat / Cool Heating Lochinvar whb085 85,000 BTU · Boiler ×1 |
| 02/04/2022 | Permit Issued | HOBBS, INC | Air Conditioning Systems, Associated Ducts and Piping |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/18/2026 | Permit Issued | Level Up Plumbing Corp | Sprinkler System |
| 12/18/2025 | — | — | 21 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/13/2026 | Permit Issued | WF PLUMBING AND HEATING L | Gas, Water/Sanitary |
| 03/18/2026 | Permit Issued | NICE PLUMBING CORP | Gas, Storm, Water/Sanitary |
| 02/09/2026 | Permit Issued | CROSSFIELD PLBG.&HTG | Gas, Water/Sanitary |
| 12/18/2025 | — | — | Gas, Water/Sanitary |
| 07/29/2024 | Signed-off | CBB PLUMBING CORP | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/03/2026 | Permit Issued | W 8 ELECTRIC CORP | General Wiring |
| 08/21/2026 | Complete | LAREDO ELECTRIC, INC. | — |
| 08/21/2026 | Complete | LAREDO ELECTRIC, INC. | — |
| 08/05/2026 | Permit Issued | NION ELECTRIC CORP | General Wiring |
| 07/09/2026 | Permit Issued | KET ELECTRIC LLC | General Wiring |
| 05/26/2026 | Complete | IP2 ELECTRIC LLC | Lighting |
| 11/09/2025 | Permit Issued | XELA ELECTRICAL CORP | General Wiring |
| 10/06/2025 | Permit Issued | KYL ELECTRIC LLC | General Wiring |
| 02/11/2025 | Complete | WCK ELECTRIC CORP. | General Wiring |
| 02/09/2025 | Complete | EINSTEIN ELEC'L CORP | General Wiring |
| 06/07/2024 | Complete | A&E ELECTRICAL SYSTEMS CO | General Wiring |
| 05/11/2024 | Complete | PJZ MAINTENANCE CORP. | General Wiring |
| 05/09/2024 | Complete | QUEENSBORO ELEC'L CONTR'G | General Wiring |
| 10/13/2023 | Complete | GRAMERCY ELECTRIC INC | — |
| 10/13/2022 | Complete | A.L. ELECTRICAL CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/18/2026 | Permit Issued | Level Up Plumbing Corp | Steel, Concrete |
| 04/06/2022 | — | — | Steel |
| Owner | Filings | Most Recent |
|---|---|---|
| K PROPERTY GROUP | 2 | 07/08/2026 |
| HARMONI | 6 | 07/08/2026 |
| RED HEART FRIENDS LLC | 7 | 03/22/2026 |
| 415 GREENWICH FEE OWNER | 94 | 03/22/2026 |
| CPG CONSTRUCTION & DEVEL | 1 | 03/22/2026 |
| CPG CONSTRUCTION | 2 | 03/22/2026 |
| 415 GREENWICH ST | 1 | 03/22/2026 |
| GLOBIX | 122 | 03/22/2026 |
| SUMMIT FUPORT COMPANY | 1 | 03/22/2026 |
| 415 GREENWICH FOR OWNER L | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| SPENCER ENGINEERING, PC | 2 | 04/22/2026 |
| RODMAN PAUL ARCHITECTS PLLC | 3 | 04/13/2026 |
| JMV CONSULTING ENGINEERING | 6 | 04/02/2026 |
| P.A. COLLINS PE | 3 | 03/18/2026 |
| TYLIN | 1 | 03/16/2026 |
| TANG KAWASAKI STUDIO | 1 | 03/15/2026 |
| A2 ARCHITECT, PC | 4 | 02/09/2026 |
| WAVIC ENGINEERING PLLC | 2 | 12/18/2025 |
| EDWARD KOZANLIAN ARCHITECT LLC | 2 | 12/11/2025 |
| DANIELLE ALBERT ARCHITECT | 2 | 12/05/2025 |
| ROB HEGEDUS ARCHITECT | 5 | 07/21/2025 |
| DAVID BLACK ARCHITECT PLLC | 3 | 07/29/2024 |
| NEW YORK DESIGN ARCHITECTS, LLP | 4 | 07/18/2024 |
| NY RESTORATION TECHNOLOGY CORP | 2 | 04/02/2024 |
| ARRA ARCHITECTURE | 2 | 09/22/2023 |
| STUDIO DB ARCHITECTURE DPC | 2 | 04/18/2023 |
| ENTHINK ENGINEERS LLC | 5 | 03/22/2023 |
| H. A. BADER CONSULTANTS | 2 | 09/07/2022 |
| ARCH EXPRESS LLC | 1 | 08/24/2022 |
| CES ENGINEERING LLC | 2 | 07/21/2022 |
| FORTY SEVENTY-THREE, LLC | 1 | 07/21/2022 |
| BLUE SKY DESIGN, INC. | 1 | 04/06/2022 |
| PAUL PERDEK, PROF. ENG. PLLC | 1 | 04/06/2022 |
| JMA CONSULTANTS AND ENGINEERS P.C. | 1 | 04/01/2022 |
| GREEN DESIGN | 1 | 04/26/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| DOMANI CONSULTING | 5 | 03/21/2026 |
| RESOLUTION EXPEDITING | 10 | 03/21/2026 |
| NEW YORK DESIGN ARCHITECT LLP | 8 | 03/21/2026 |
| M HASHAS | 6 | 03/21/2026 |
| J. CALLAHAN CONSULTING, INC. | 4 | 03/21/2026 |
| SOL BUILDING CONSULTING SERVICES | 1 | 03/21/2026 |
| AGOUTI CONSTRUCTION CONSULTING | 4 | 03/21/2026 |
| JENNY FLORES EXPEDITING | 2 | 03/21/2026 |
| METROPOLIS GROUP INC | 4 | 03/21/2026 |
| OUTSOURCE CONSULTANTS, INC. | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ANDAMIO SCAFFOLDING LLC | General Contractor | 12 | 07/08/2026 |
| AM&G WATERPROOFING LLC | General Contractor | 9 | 07/08/2026 |
| HOBBS, INC | General Contractor | 6 | 03/21/2026 |
| LENNIE CONSTRUCTION CORP | General Contractor | 4 | 07/08/2026 |
| DECECK & LEONARD,INC | Electrical | 3 | 03/22/2026 |
| DEMAR PLUMBING CORP | Fire Protection | 2 | 07/08/2026 |
| RENOVATION PARTNERS INC | General Contractor | 2 | 07/08/2026 |
| APOLLO ELECTRIC USA, INC | Electrical | 2 | 03/22/2026 |
| RENOV INC | General Contractor | 2 | 08/27/2026 |
| ADS CONSTRUCTION CORP | General Contractor | 2 | 03/21/2026 |
| KG SPRINKLER CORP | Fire Protection | 2 | 07/08/2026 |
| DUPRAT CONSTRUCTION CORP | General Contractor | 2 | 07/08/2026 |
| CASELLA CONSTRUCTION CORP. | General Contractor | 1 | 07/08/2026 |
| CGR SYSTEMS MANAGEMENT | General Contractor | 1 | 07/08/2026 |
| EVEREST SCAFFOLDING INC | General Contractor | 1 | 07/08/2026 |
| LEWIS CONSTRUCTION NYC IN | General Contractor | 1 | 07/08/2026 |
| ON SITE NYC INC | General Contractor | 1 | 04/08/2026 |
| THE ALBERONA GROUP INC | General Contractor | 1 | 07/08/2026 |
| URBAN STANDARD GENERAL CO | General Contractor | 1 | 07/08/2026 |
| A&H EXPRESS PLBG&HTG CORP | Plumbing | 1 | 07/08/2026 |
| AP PLUMBING & HVAC LLC | Plumbing | 1 | 06/28/2026 |
| CBB PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| ETHOS PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| HYDROKINETIC PLBG & HTG I | Plumbing | 1 | 07/08/2026 |
| NICE PLUMBING CORP | Plumbing | 1 | 09/02/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SRA INSPECTIONS | 3461 | 2 | 04/22/2026 |
| JMV CONSULTING ENGINEERIN | 804 | 8 | 04/02/2026 |
| AG ENGINEERING PLLC | 8899 | 3 | 03/18/2026 |
| SGM ENGINEERING | 2366 | 1 | 03/16/2026 |
| A2 ARCHITECT, PC | 2504 | 4 | 02/09/2026 |
| NAPACH ARCHITECTU | 2945 | 2 | 07/29/2024 |
| AKS ARCHITECTURAL & ENGIN | 1957 | 8 | 07/18/2024 |
| NY RESTORATION TECHNOLOGY | 6187 | 1 | 09/22/2022 |
| H. A. BADER CONSULTANTS | 2332 | 4 | 09/07/2022 |
| INTEGRITY CONSULTING SERV | 666 | 3 | 09/07/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Permit Issued | Level Up Plumbing Corp | 09/03/2026 |
| DOB NOW | Plumbing | Permit Issued | NICE PLUMBING CORP | 09/01/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | BALOG CONSTRUCTION LLC | 08/31/2026 |
| DOB NOW | General Construction | Permit Issued | RENOV INC | 08/26/2026 |
| DOB NOW | General Construction | Permit Issued | DUPRAT CONSTRUCTION CORP | 05/04/2026 |
| DOB NOW | General Construction | Permit Issued | DUPRAT CONSTRUCTION CORP | 05/04/2026 |
| DOB NOW | Sprinklers | Permit Issued | DEMAR PLUMBING CORP | 03/27/2026 |
| DOB NOW | Plumbing | Permit Issued | WF PLUMBING AND HEATING L | 01/14/2026 |
| DOB NOW | General Construction | Permit Issued | RENOV INC | 12/05/2025 |
| DOB NOW | Plumbing | Permit Issued | CROSSFIELD PLBG.&HTG | 10/06/2025 |
| DOB NOW | General Construction | Permit Issued | ON SITE NYC INC | 09/26/2025 |
| DOB NOW | General Construction | Signed-off | LENNIE CONSTRUCTION | 05/05/2025 |
| DOB NOW | General Construction | Signed-off | THE ALBERONA GROUP INC | 03/24/2025 |
| DOB NOW | Sprinklers | Permit Issued | DEMAR PLUMBING CORP | 03/10/2025 |
| DOB NOW | General Construction | Signed-off | LENNIE CONSTRUCTION | 03/07/2025 |
| DOB NOW | Plumbing | Signed-off | ETHOS PLUMBING CORP | 02/13/2025 |
| DOB NOW | Sprinklers | Permit Issued | BLETSAS P&H CORP | 02/12/2025 |
| DOB NOW | Mechanical Systems | Signed-off | ALL MAKES HTG & A/C CORP | 02/12/2025 |
| DOB NOW | General Construction | Signed-off | LENNIE CONSTRUCTION | 02/10/2025 |
| DOB NOW | Plumbing | Signed-off | CBB PLUMBING CORP | 08/29/2024 |
| DOB NOW | General Construction | Signed-off | LEWIS CONSTRUCTION NYC IN | 08/28/2024 |
| DOB NOW | Sprinklers | Signed-off | DEPENDABLE MECHANICAL COR | 06/21/2024 |
| DOB NOW | Plumbing | Signed-off | A&H EXPRESS PLBG&HTG CORP | 06/21/2024 |
| DOB NOW | Plumbing | Signed-off | HYDROKINETIC PLBG & HTG I | 05/13/2024 |
| DOB NOW | General Construction | Signed-off | CASELLA CONSTRUCTION CORP. | 05/08/2024 |
| DOB NOW | General Construction | Signed-off | A & G MAINTENANCE INC | 04/08/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | AM&G WATERPROOFING LLC | 04/08/2024 |
| DOB NOW | General Construction | Signed-off | AM&G WATERPROOFING LLC | 03/11/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | AM&G WATERPROOFING LLC | 03/07/2024 |
| DOB NOW | Supported Scaffold | Signed-off | ANDAMIO SCAFFOLDING LLC | 01/23/2024 |
| DOB NOW | General Construction | Signed-off | ADS CONSTRUCTION CORP | 09/28/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 08/11/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | AM&G WATERPROOFING LLC | 03/13/2023 |
| DOB NOW | General Construction | Signed-off | AM&G WATERPROOFING LLC | 03/13/2023 |
| DOB NOW | Supported Scaffold | Signed-off | ANDAMIO SCAFFOLDING LLC | 01/31/2023 |
| DOB NOW | Sprinklers | Permit Issued | H M SPRINKLER INC | 11/24/2022 |
| DOB NOW | Structural | Signed-off | AM&G WATERPROOFING LLC | 11/17/2022 |
| DOB NOW | Plumbing | Permit Issued | HF GROUP PLMBG & SPNKLER | 10/14/2022 |
| DOB NOW | Sprinklers | Permit Issued | SMART PLBG & HTG CORP | 10/14/2022 |
| DOB NOW | Mechanical Systems | Permit Issued | RENOVATION PARTNERS INC | 09/13/2022 |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/27/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/27/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/10/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/08/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/07/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/07/2026 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 03/26/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/12/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/11/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/27/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/26/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/15/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/07/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/31/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/16/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/11/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/19/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/18/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 11/18/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 10/23/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/11/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/01/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 09/09/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/05/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/05/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/22/2026 | Tenant Protection Plan Compliance | Adrian Figueroa | special |
| 04/10/2026 | Final | Joseph Vuto | progress |
| 04/10/2026 | Fire-Resistant Penetrations and Joints | Joseph Vuto | special |
| 04/10/2026 | Mechanical Systems | Joseph Vuto | special |
| 04/10/2026 | Post-installed Anchors | Joseph Vuto | special |
| 04/09/2026 | Final | Spencer Goroff | progress |
| 04/09/2026 | Tenant Protection Plan Compliance | Adrian Figueroa | special |
| 04/09/2026 | Final | Spencer Goroff | progress |
| 03/11/2026 | Final | Joseph Vuto | progress |
| 03/11/2026 | Mechanical Systems | Joseph Vuto | special |
| 03/11/2026 | Fire-Resistant Penetrations and Joints | Joseph Vuto | special |
| 03/11/2026 | Post-installed Anchors | Joseph Vuto | special |
| 02/24/2026 | Lighting in dwelling units | Ann Macklin | energy_progress |
| 02/24/2026 | Energy Code Compliance Inspections | Ann Macklin | progress |
| 02/24/2026 | Fire-Resistant Penetrations and Joints | Ann Macklin | special |
| 02/24/2026 | Final | Ann Macklin | progress |
| 02/24/2026 | Mechanical Systems | Ann Macklin | special |
| 02/16/2026 | Fire-Resistant Penetrations and Joints | Ann Macklin | special |
| 02/03/2026 | Fire-Resistant Penetrations and Joints | ARIEL GOLSHAN | special |
| 02/03/2026 | Fire-Resistant Penetrations and Joints | ARIEL GOLSHAN | special |
| 02/03/2026 | Heating Systems | Paul Collins | special |
| 02/03/2026 | Post-installed Anchors | ARIEL GOLSHAN | special |
| 02/02/2026 | Tenant Protection Plan Compliance | ARIEL GOLSHAN | special |
| 02/02/2026 | Structural Steel - Welding | steven Giammona | special |
| 02/02/2026 | Structural Steel - High Strength Bolting | steven Giammona | special |