| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/19/2021 | $600K | — | 415 QUINCY LLC → Private party | $487/sf building |
| 03/16/2021 | $385K | — | — → — | $313/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CHANDA ENGINEERING CONSULTANT PC | 6 | 10/10/2023 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ALL PRO PLBG & HTG INC | Plumbing | 6 | 07/08/2026 |
| DAVID CONSTRUCTING NY, IN | General Contractor | 4 | 07/08/2026 |
| A.C. MORGAN ELECTRIC | Electrical | 2 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CHANDA ENG. CONSULTANT PC | 6842 | 5 | 10/10/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | ALL PRO PLBG & HTG INC | 10/13/2022 |
| DOB NOW | Foundation | Signed-off | DAVID CONSTRUCTING NY, IN | 08/11/2022 |
| DOB NOW | Construction Fence | Signed-off | DAVID CONSTRUCTING NY, IN | 07/21/2022 |
| BIS | OT | ISSUED | CENTURION SOLAR ENERGY | 09/16/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/06/2023 | Complete | A.C. MORGAN ELECTRIC | General Wiring |
| 09/30/2022 | Complete | BERGER QUALITY ELEC'L CON | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/08/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 08/01/2023 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 07/21/2023 | No Access-Final PL - Up to 3 Requested Floors | No Access | View ↗ |
| 05/15/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 01/09/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/09/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 01/09/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/11/2023 | Fire-Resistant Penetrations and Joints | KARTIK CHANDA | special |
| 10/10/2023 | Fire-Resistant Penetrations and Joints | KARTIK CHANDA | special |
| 07/24/2023 | Concrete - Cast-In-Place | KARTIK CHANDA | special |
| 07/24/2023 | Final | KARTIK CHANDA | progress |
| 07/24/2023 | Lowest Floor Elevation | KARTIK CHANDA | progress |
| 07/24/2023 | Footing and Foundation | KARTIK CHANDA | progress |
| 07/24/2023 | Air barrier - visual inspection | KARTIK CHANDA | energy_progress |
| 07/24/2023 | Insulation placement and R values | KARTIK CHANDA | energy_progress |
| 07/24/2023 | Interior lighting power | KARTIK CHANDA | energy_progress |
| 07/24/2023 | Fenestration and door U-factor and product ratings | KARTIK CHANDA | energy_progress |
| 07/24/2023 | Fire-Resistant Penetrations and Joints | KARTIK CHANDA | special |
| 07/22/2023 | Air barrier - visual inspection | KARTIK CHANDA | energy_progress |
| 07/22/2023 | Concrete - Cast-In-Place | KARTIK CHANDA | special |
| 07/22/2023 | Fire-Resistant Penetrations and Joints | KARTIK CHANDA | special |
| 07/22/2023 | Final | KARTIK CHANDA | progress |
| 07/22/2023 | Footing and Foundation | KARTIK CHANDA | progress |
| 07/22/2023 | Lowest Floor Elevation | — | progress |
| 07/22/2023 | Insulation placement and R values | KARTIK CHANDA | energy_progress |
| 07/22/2023 | Interior lighting power | KARTIK CHANDA | energy_progress |
| 07/22/2023 | Fenestration and door U-factor and product ratings | KARTIK CHANDA | energy_progress |
| 05/06/2023 | Fire-Resistant Penetrations and Joints | KARTIK CHANDA | special |