RoofStructural and general construction work5p · 1 filing · 20 docs
ArchitectureMechanical
Issued Permit Scope
Mechanical Systems
STRUCTURAL WORK IN CONJUCTION WITH GENERAL CONSTRUCTION WORK DOB NOW JOB #M00478521
On file for this project
21 documents · 1 drawing sheet
Floor 4Interior and exterior renovation, cellar to 4th floor44p · 4 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
INTERIOR AND EXTERIOR RENOVATION THROUGHOUT IN AN EXISTING CELLAR, BASEMENT AND 1ST -4TH FLOOR BUILDING
On file for this project
55 documents · 4 drawing sheets
PLUMBING WORK FILED IN CONJUNCTION WITH GC JOB # M00478521-I1
On file for this project
19 documents · 4 drawing sheets
INSTALL NEW SPRINKLER SYSTEM AND PLUMBING SYSTEM FOR WATER SERVICE FOR 4-STORY BUILDINGS IN CONJUNCTION WITH A1 JOB#M00478521.NO CHANGE IN USE,EGRESS AND OCCUPANCY.
On file for this project
22 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 3Interior and exterior renovation, cellar to 4th floor41p · 4 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
INTERIOR AND EXTERIOR RENOVATION THROUGHOUT IN AN EXISTING CELLAR, BASEMENT AND 1ST -4TH FLOOR BUILDING
On file for this project
55 documents · 3 drawing sheets
PLUMBING WORK FILED IN CONJUNCTION WITH GC JOB # M00478521-I1
On file for this project
19 documents · 3 drawing sheets
INSTALL NEW SPRINKLER SYSTEM AND PLUMBING SYSTEM FOR WATER SERVICE FOR 4-STORY BUILDINGS IN CONJUNCTION WITH A1 JOB#M00478521.NO CHANGE IN USE,EGRESS AND OCCUPANCY.
On file for this project
22 documents
Latest 3 of 4 filings on this floor.
Floor 2Interior and exterior renovation, cellar to 4th floor42p · 4 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
INTERIOR AND EXTERIOR RENOVATION THROUGHOUT IN AN EXISTING CELLAR, BASEMENT AND 1ST -4TH FLOOR BUILDING
On file for this project
55 documents · 3 drawing sheets
PLUMBING WORK FILED IN CONJUNCTION WITH GC JOB # M00478521-I1
On file for this project
19 documents · 4 drawing sheets
INSTALL NEW SPRINKLER SYSTEM AND PLUMBING SYSTEM FOR WATER SERVICE FOR 4-STORY BUILDINGS IN CONJUNCTION WITH A1 JOB#M00478521.NO CHANGE IN USE,EGRESS AND OCCUPANCY.
On file for this project
22 documents
Latest 3 of 4 filings on this floor.
Floor 1Interior and exterior renovation, cellar to 4th floor37p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
INTERIOR AND EXTERIOR RENOVATION THROUGHOUT IN AN EXISTING CELLAR, BASEMENT AND 1ST -4TH FLOOR BUILDING
On file for this project
55 documents
PLUMBING WORK FILED IN CONJUNCTION WITH GC JOB # M00478521-I1
On file for this project
19 documents
INSTALL NEW SPRINKLER SYSTEM AND PLUMBING SYSTEM FOR WATER SERVICE FOR 4-STORY BUILDINGS IN CONJUNCTION WITH A1 JOB#M00478521.NO CHANGE IN USE,EGRESS AND OCCUPANCY.
On file for this project
22 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
CellarInterior and exterior renovation, cellar to 4th floor45p · 4 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
INTERIOR AND EXTERIOR RENOVATION THROUGHOUT IN AN EXISTING CELLAR, BASEMENT AND 1ST -4TH FLOOR BUILDING
On file for this project
55 documents · 4 drawing sheets
PLUMBING WORK FILED IN CONJUNCTION WITH GC JOB # M00478521-I1
On file for this project
19 documents · 5 drawing sheets
INSTALL NEW SPRINKLER SYSTEM AND PLUMBING SYSTEM FOR WATER SERVICE FOR 4-STORY BUILDINGS IN CONJUNCTION WITH A1 JOB#M00478521.NO CHANGE IN USE,EGRESS AND OCCUPANCY.
On file for this project
22 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
BasementInterior and exterior renovation, cellar to 4th floor12p · 3 filings · 20 docs
ArchitecturePlumbing
Issued Permit Scope
General Construction
INTERIOR AND EXTERIOR RENOVATION THROUGHOUT IN AN EXISTING CELLAR, BASEMENT AND 1ST -4TH FLOOR BUILDING
On file for this project
55 documents
PLUMBING WORK FILED IN CONJUNCTION WITH GC JOB # M00478521-I1
On file for this project
19 documents · 1 drawing sheet
STRUCTURAL WORK IN CONJUCTION WITH GENERAL CONSTRUCTION WORK DOB NOW JOB #M00478521
On file for this project
21 documents · 1 drawing sheet
Sub-BasementNew gas boiler for hot water27p · 3 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Structural
PLUMBING WORK FILED IN CONJUNCTION WITH GC JOB # M00478521-I1
On file for this project
19 documents
INSTALL NEW SPRINKLER SYSTEM AND PLUMBING SYSTEM FOR WATER SERVICE FOR 4-STORY BUILDINGS IN CONJUNCTION WITH A1 JOB#M00478521.NO CHANGE IN USE,EGRESS AND OCCUPANCY.
On file for this project
22 documents
STRUCTURAL WORK IN CONJUCTION WITH GENERAL CONSTRUCTION WORK DOB NOW JOB #M00478521
On file for this project
21 documents
Site & exteriorNew sprinkler and plumbing system installation7p · 2 filings · 20 docs
Fire ProtectionPlumbing
Issued Permit Scope
Plumbing · Sprinklers · Supported Scaffold
LEGALIZATION OF ILLEGALLY INSTALLED AND REMOVED SCAFFOLDING IN FRONT YARD TO REMOVE VIOLATION # 39509399X.
On file for this project
2 documents · 1 drawing sheet
INSTALL NEW SPRINKLER SYSTEM AND PLUMBING SYSTEM FOR WATER SERVICE FOR 4-STORY BUILDINGS IN CONJUNCTION WITH A1 JOB#M00478521.NO CHANGE IN USE,EGRESS AND OCCUPANCY.
On file for this project
22 documents · 10 drawing sheets