| Owner | Filings | Most Recent |
|---|---|---|
| GENESIS 22 LLC | 8 | 03/22/2026 |
| 4209 162ND STREET | 4 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/20/2022 | $1.3M | — | 4209 162ND STREET INC. → GENESIS 22 LLC | $797/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| TL ENGINEERING, PC | 5 | 06/05/2025 |
| ECOPLUSDESIGN | 3 | 06/28/2024 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| R & T ELECTRICAL CORP | Electrical | 2 | 03/22/2026 |
| L&L CONSTRUCTION DEVELOP | General Contractor | 2 | 04/09/2026 |
| S Y CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| PETER PLUMBING ASSOC. INC. | Plumbing | 1 | 07/08/2026 |
| WASOFF PLBG & UTILITY CO | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MEHDI GHAZI, P.E. P.C. | 7129 | 2 | 06/05/2025 |
| TL ENGINEERING, PC | 1222 | 3 | 03/10/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | L&L CONSTRUCTION DEVELOP | 05/07/2025 |
| DOB NOW | General Construction | Signed-off | L&L CONSTRUCTION DEVELOP | 02/14/2025 |
| DOB NOW | Plumbing | Signed-off | WASOFF PLBG & UTILITY CO | 02/14/2025 |
| DOB NOW | Plumbing | Signed-off | PETER PLUMBING ASSOC. INC. | 06/04/2024 |
| DOB NOW | General Construction | Signed-off | S Y CONSTRUCTION INC | 05/23/2024 |
| BIS | OT | ISSUED | HAO HUA SERVICE CORP | 08/09/2013 |
| BIS | OT | ISSUED | JME CONSTRUCTION CORP | 12/04/2012 |
| BIS | PL | ISSUED | PETER PLUMBING ASSOC. INC. | 01/11/2005 |
| BIS | OT | ISSUED | KORMAN DESIGN & BUILD | 11/17/2004 |
| BIS | FS | ISSUED | BAYSIDE FUEL | 09/21/2004 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/14/2025 | Complete | R & T ELECTRICAL CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/12/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/31/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 09/25/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 03/06/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/16/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 06/24/2024 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 06/13/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/12/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/06/2025 | Fire-Resistant Penetrations and Joints | MEHDI GHAZI | special |
| 06/06/2025 | Interior lighting power | MEHDI GHAZI | energy_progress |
| 06/06/2025 | Lighting controls | MEHDI GHAZI | energy_progress |
| 06/06/2025 | Energy Code Compliance Inspections | MEHDI GHAZI | progress |
| 06/06/2025 | Tenant Protection Plan Compliance | MEHDI GHAZI | special |
| 06/05/2025 | Fire-Resistant Penetrations and Joints | MEHDI GHAZI | special |
| 06/05/2025 | Tenant Protection Plan Compliance | MEHDI GHAZI | special |
| 06/05/2025 | Energy Code Compliance Inspections | — | progress |
| 06/05/2025 | Interior lighting power | MEHDI GHAZI | energy_progress |
| 06/05/2025 | Lighting controls | MEHDI GHAZI | energy_progress |
| 03/10/2025 | HVAC-R and service water heating equipment | Simon Lee | energy_progress |
| 03/10/2025 | HVAC-R and service water piping design and insulation | Simon Lee | energy_progress |
| 03/10/2025 | HVAC-R and service water heating system controls | Simon Lee | energy_progress |
| 03/10/2025 | Fire-Resistant Penetrations and Joints | Simon Lee | special |
| 03/10/2025 | Energy Code Compliance Inspections | Simon Lee | progress |
| 03/07/2025 | Final | Simon Lee | progress |
| 03/07/2025 | Mechanical Systems | Simon Lee | special |
| 03/07/2025 | Tenant Protection Plan Compliance | Simon Lee | special |
| 03/04/2025 | Tenant Protection Plan Compliance | Simon Lee | special |