| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/10/2025 | Permit Issued | GREGG NY PLUMBING, INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/17/2026 | Permit Issued | New Century Electrical Contracting | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/10/2025 | Permit Issued | MJDAQUIAL CONSTR CORP | Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/10/2025 | Permit Issued | MJDAQUIAL CONSTR CORP | Fence |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/26/2024 | $950K | — | Private party → Private party | $536/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ASKON ARCHITECTS, P.C. | 3 | 10/10/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| ASKON ARCHITECTS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MJDAQUIAL CONSTR CORP | General Contractor | 6 | 09/18/2026 |
| GREGG NY PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ASKON ARCHITECT, P.C. | 3596 | 2 | 10/10/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Permit Issued | MJDAQUIAL CONSTR CORP | 09/17/2026 |
| DOB NOW | Foundation | Permit Issued | MJDAQUIAL CONSTR CORP | 05/28/2026 |
| DOB NOW | Plumbing | Permit Issued | GREGG NY PLUMBING, INC | 04/21/2026 |
| DOB NOW | Structural | Permit Issued | MJDAQUIAL CONSTR CORP | 09/17/2025 |
| DOB NOW | Construction Fence | Permit Issued | MJDAQUIAL CONSTR CORP | 07/01/2025 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/11/2025 | Fire-Resistant Penetrations and Joints | Akeeb Shekoni | special |
| 10/24/2025 | HVAC-R and service water piping design and insulation | Akeeb Shekoni | energy_progress |
| 10/24/2025 | Maintenance information | Akeeb Shekoni | energy_progress |
| 05/13/2025 | Subgrade Inspections | Akeeb Shekoni | special |
| 05/13/2025 | Energy Code Compliance Inspections | Akeeb Shekoni | progress |
| 05/13/2025 | Fire-Resistance Rated Construction | Akeeb Shekoni | progress |
| 05/13/2025 | Structural Wood Frame | Akeeb Shekoni | progress |
| 05/13/2025 | Fenestration areas | Akeeb Shekoni | energy_progress |
| 05/13/2025 | Air barrier - visual inspection | Akeeb Shekoni | energy_progress |
| 05/13/2025 | Concrete - Cast-In-Place | Akeeb Shekoni | special |
| 05/13/2025 | Interior lighting power | Akeeb Shekoni | energy_progress |
| 05/13/2025 | Maintenance information | Akeeb Shekoni | energy_progress |
| 05/13/2025 | Electric vehicle service equipment requirements | Akeeb Shekoni | energy_progress |
| 05/13/2025 | Fenestration and door U-factor and product ratings | Akeeb Shekoni | energy_progress |
| 05/13/2025 | Fenestration air leakage | Akeeb Shekoni | energy_progress |
| 05/13/2025 | Permanent certificate | Akeeb Shekoni | energy_progress |
| 05/13/2025 | Protection of exposed foundation insulation | Akeeb Shekoni | energy_progress |
| 05/13/2025 | Insulation placement and R values | Akeeb Shekoni | energy_progress |
| 05/13/2025 | Fire-Resistant Penetrations and Joints | Akeeb Shekoni | special |
| 05/13/2025 | Structural Stability – Alterations of existing buildings | Akeeb Shekoni | special |
| 01/17/2025 | Footing and Foundation | Akeeb Shekoni | progress |
| 01/17/2025 | Final | HANSA PERSAUD | progress |