💬 Discuss this project
2020Year Built
2Stories
B1Building Class
R3XZoning
3,828 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Two family brick · 6,250 sf lot · 0.61 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbingFire Protection
Floor 11p · 1 filing · 20 docs
Cellar4p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NEW HENGDA CONSTRUCTION203/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/28/2018$1.4M—Private party → Private party— not available
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JOHN C. CHEN ARCHITECT,PLLC510/06/2021
TIMES BUILDINGS ENGINEERING SERVICE112/11/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JOHN C CHEN ARCHITECT403/21/2026
MEIYUN CHEN103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NEW HENGDA CONSTRUCTIONGeneral Contractor607/08/2026
DYNASTY CONTRACTING LLCGeneral Contractor303/21/2026
WASOFF PLBG & UTILITY COPlumbing307/08/2026
WASOFF PLBG UTILITYGeneral Contractor103/22/2026
JOHN C CHEN ARCHITECTGeneral Contractor103/22/2026
HI-RITE ELECTRIC CORPElectrical103/22/2026
EDWARD BYRNEElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JOHN C CHEN ARCHITECT, PL2205310/06/2021
Building Lifecycle
All (45)Filed (6)Permit Issued (8)Signed Off (5)Violation (2)Inspection (2)Objection (2)Special Inspection (20)
03/10/2022
Signed off — Alteration
INSTALL STORM WATER DRAINAGE PIPING FOR GARAGE (NB.# 421730844)
Q00428211-I1
03/10/2022
Signed off — Alteration
INSTALL PLUMBING FIXTURES, GAS EQUIPMENT AND SPRINKLER(PL) HEADS AT CELLAR, 001 AND 002 FLOOR; ENERGY ANALYSIS REQUIREMENT UNDER NB. #421730808
Q00326766-I1
01/11/2022
Signed off — Alteration
INSTALL TEMP. CONSTRUCTION FENCE IN CONJUNCTION WITH NB. JOB N0.# 421730808(HOUSE) AND 421730844(GARAGE)
Q00279721-I1
01/11/2022
Signed off — Alteration
construct a 18' paired curb cut in conjunction with NB.# 421730808(HOUSE) & 421730844(GARAGE)
Q00278876-I1
01/10/2022
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
12/28/2021
Inspection — Fail-Final Curb Cut Non-Directive 14
Fail
View inspection ↗
11/17/2021
Permit issued — Curb Cut
Q00278876-I1-CC
10/21/2021
Permit issued — Plumbing
Q00326766-I1-PL
10/06/2021
Filed — Alteration
INSTALL PLUMBING FIXTURES, GAS EQUIPMENT AND SPRINKLER(PL) HEADS AT CELLAR, 001 AND 002 FLOOR; ENERGY ANALYSIS REQUIREMENT UNDER NB. #421730808
Q00326766-P1
10/06/2021
Special inspection requirement — HVAC insulation and sealing
JOHN CHEN
10/06/2021
Special inspection requirement — HVAC and service water heating system controls
JOHN CHEN
10/06/2021
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
JOHN CHEN
10/06/2021
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
JOHN CHEN
10/06/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOHN CHEN
10/06/2021
Special inspection requirement — Energy Code Compliance Inspections
JOHN CHEN
10/06/2021
Special inspection requirement — Fire-Resistance Rated Construction
JOHN CHEN
10/06/2021
Special inspection requirement — Maintenance information
JOHN CHEN
10/06/2021
Special inspection requirement — HVAC and service water heating equipment
JOHN CHEN
10/04/2021
Special inspection requirement — HVAC insulation and sealing
JOHN CHEN
10/04/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOHN CHEN
10/04/2021
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
JOHN CHEN
10/04/2021
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
JOHN CHEN
10/04/2021
Special inspection requirement — Energy Code Compliance Inspections
JOHN CHEN
10/04/2021
Special inspection requirement — Fire-Resistance Rated Construction
JOHN CHEN
10/04/2021
Special inspection requirement — Maintenance information
JOHN CHEN
10/04/2021
Special inspection requirement — HVAC and service water heating system controls
JOHN CHEN
10/04/2021
Special inspection requirement — HVAC and service water heating equipment
JOHN CHEN
03/29/2021
Permit issued — Construction Fence
Q00279721-I1-FN
03/23/2021
Permit issued — Plumbing
Q00428211-I1-PL
03/03/2021
Permit issued — Construction Fence
Q00279721-I1-FN
11/16/2020
Filed — Alteration
INSTALL STORM WATER DRAINAGE PIPING FOR GARAGE (NB.# 421730844)
Q00428211-I1
11/13/2020
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
JOHN CHEN
10/16/2020
Violation issued (ECB, closed)
Construction
10/16/2020
Violation issued (ECB, closed)
Construction
09/28/2020
Permit issued — Plumbing
Q00326766-I1-PL
03/05/2020
Permit issued — Construction Fence
Q00279721-I1-FN
03/04/2020
Filed — Alteration
INSTALL PLUMBING FIXTURES, GAS EQUIPMENT AND SPRINKLER(PL) HEADS AT CELLAR, 001 AND 002 FLOOR; ENERGY ANALYSIS REQUIREMENT UNDER NB. #421730808
Q00326766-I1
02/27/2020
Signed off — Alteration
Q00276784-I1
12/20/2019
Permit issued — Construction Fence
Q00276784-I1-FN
12/13/2019
Objection raised — Scope
12/13/2019
Objection resolved — Addressed
12/11/2019
Filed — Alteration
INSTALL TEMP. CONSTRUCTION FENCE IN CONJUNCTION WITH NB. JOB N0.# 421730808(HOUSE) AND 421730844(GARAGE)
Q00279721-I1
12/11/2019
Filed — Alteration
construct a 18' paired curb cut in conjunction with NB.# 421730808(HOUSE) & 421730844(GARAGE)
Q00278876-I1
12/11/2019
Filed — Alteration
Q00276784-I1
12/11/2019
Special inspection requirement — Final
JOHN CHEN
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offNEW HENGDA CONSTRUCTION11/17/2021
DOB NOWPlumbingSigned-offWASOFF PLBG & UTILITY CO10/21/2021
DOB NOWConstruction FenceSigned-offNEW HENGDA CONSTRUCTION03/29/2021
DOB NOWPlumbingSigned-offWASOFF PLBG & UTILITY CO03/23/2021
DOB NOWConstruction FenceSigned-offNEW HENGDA CONSTRUCTION03/03/2021
DOB NOWPlumbingSigned-offWASOFF PLBG & UTILITY CO09/28/2020
DOB NOWConstruction FenceSigned-offNEW HENGDA CONSTRUCTION03/05/2020
DOB NOWConstruction FenceSigned-offDYNASTY CONTRACTING LLC12/20/2019
BISOTISSUEDACCORD POWER INC07/06/2021
BIS—ISSUEDNEW HENGDA CONSTRUCTION04/14/2021
BISOTISSUEDACCORD POWER INC12/11/2020
BIS—ISSUEDNEW HENGDA CONSTRUCTION08/11/2020
BIS—ISSUEDNEW HENGDA CONSTRUCTION07/28/2020
BIS—ISSUEDNEW HENGDA CONSTRUCTION07/16/2020
BIS—ISSUEDDYNASTY CONTRACTING LLC01/14/2020
2 projects · most recent 06/15/2021
General Wiring Lighting
FiledStatusContractorScope
06/15/2021CompleteNEWGRANGE ELECTRIC, INC—
09/29/2020CompleteHI-RITE ELECTRIC CORPGeneral Wiring, Lighting
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
01/10/2022Pass-Final Curb Cut Non-Directive 14PassView ↗
12/28/2021Fail-Final Curb Cut Non-Directive 14FailView ↗
▾Special Inspection Requirements (DOB NOW) — 20
DateRequirementInspectorRole
10/06/2021HVAC insulation and sealing JOHN CHENenergy_progress
10/06/2021HVAC and service water heating system controls JOHN CHENenergy_progress
10/06/2021Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention FacilitiesJOHN CHENspecial
10/06/2021Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationJOHN CHENspecial
10/06/2021Fire-Resistant Penetrations and JointsJOHN CHENspecial
10/06/2021Energy Code Compliance InspectionsJOHN CHENprogress
10/06/2021Fire-Resistance Rated ConstructionJOHN CHENprogress
10/06/2021Maintenance informationJOHN CHENenergy_progress
10/06/2021HVAC and service water heating equipment JOHN CHENenergy_progress
10/04/2021HVAC insulation and sealing JOHN CHENenergy_progress
10/04/2021Fire-Resistant Penetrations and JointsJOHN CHENspecial
10/04/2021Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationJOHN CHENspecial
10/04/2021Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention FacilitiesJOHN CHENspecial
10/04/2021Energy Code Compliance InspectionsJOHN CHENprogress
10/04/2021Fire-Resistance Rated ConstructionJOHN CHENprogress
10/04/2021Maintenance informationJOHN CHENenergy_progress
10/04/2021HVAC and service water heating system controls JOHN CHENenergy_progress
10/04/2021HVAC and service water heating equipment JOHN CHENenergy_progress
11/13/2020Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention FacilitiesJOHN CHENspecial
12/11/2019FinalJOHN CHENprogress
▾Documents — 152 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch - Plumbing3
08/28/2026Q00326766-I1Request digital key ↗
08/27/2026Q00428211-I1Request digital key ↗
08/15/2026Q00326766-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence2
08/28/2026Q00279721-I1Request digital key ↗
08/28/2026Q00276784-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Curb Cut1
08/15/2026Q00278876-I1Request digital key ↗
▸Applications & Permits12
▸BISPLAN / WORK APPROVAL APPLICATION7
11/16/2021421730808Open ↗
12/02/2020440651901Open ↗
06/15/2020421730808Open ↗
Showing 3 of 7 on file for this type
▸BISWORK PERMIT APPLICATION4
12/11/2020440651901Open ↗
08/11/2020421730808Open ↗
08/10/2020421730808Open ↗
Showing 3 of 4 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
10/22/2021421730808Open ↗
▸Zoning, Tax Lot & Property Records3
▸BISVERIFY TAX LOT1
02/10/2022421730808Open ↗
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
06/23/2020421730808Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
02/10/2022421730808Open ↗
▸Seals & Professional Certifications32
▸DOB NOWProgress Inspector Seal & Signature13
08/27/2026Q00326766-P1Open ↗
08/27/2026Q00326766-P1Open ↗
08/27/2026Q00326766-P1Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
08/28/2026Q00428211-I1Open ↗
08/27/2026Q00326766-P1Open ↗
08/27/2026Q00326766-P1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/28/2026Q00276784-I1Open ↗
08/28/2026Q00326766-P1Open ↗
08/28/2026Q00326766-I1Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION4
07/20/2020421730808Open ↗
07/20/2020421730808Open ↗
07/20/2020421730808Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
12/02/2020440651901Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
12/02/2020440651901Open ↗
▸Trade Schedules & Equipment6
▸BIS* SEWER CONNECTION: DEP SD1 & SD21
06/23/2020421730808Open ↗
▸BISHEATING SYSTEMS1
03/29/2022421730808Open ↗
▸BISHVAC & SERVICE WATER HEATING EQUIPMENT1
03/29/2022421730808Open ↗
▸BISELECTRIC CUT-OFF1
01/21/2020421744786Open ↗
▸BISHVAC & SERVICE WATER HEATING SYSTEM CONTROLS1
03/29/2022421730808Open ↗
▸BISSPRINKLER SYSTEMS1
12/20/2021421730808Open ↗
▸Safety & Tenant Protection6
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM2
01/21/2020421744786Open ↗
01/21/2020421744786Open ↗
▸BISSTREET TREE SIGNOFF2
02/18/2022421781183Open ↗
02/10/2022421730808Open ↗
▸BISSTREET TREES SITE PLAN1
12/20/2021421730808Open ↗
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE1
01/21/2020421744786Open ↗
▸Energy Compliance15
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
03/04/2022440651901Open ↗
12/02/2020440651901Open ↗
06/23/2020421730808Open ↗
Showing 3 of 4 on file for this type
▸BISAIR SEALING AND INSULATION - TESTING2
03/18/2022421730808Open ↗
03/18/2022421730808Open ↗
▸BISFENESTRATION AIR LEAKAGE1
03/29/2022421730808Open ↗
▸BISAIR SEALING AND INSULATION - VISUAL1
03/29/2022421730808Open ↗
▸BISINTERIOR LIGHTING POWER1
03/29/2022421730808Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
03/04/2022440651901Open ↗
▸BISSOLAR TAX ABATEMENT APPLICATION1
03/07/2022440651901Open ↗
▸BISFENESTRATION U-FACTOR & PRODUCT RATING1
03/29/2022421730808Open ↗
▸BISFENESTRATION AREAS1
03/29/2022421730808Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
12/02/2020440651901Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
03/29/2022421730808Open ↗
▸Inspections & Test Reports18
▸BISTECHNICAL REPORT: RESPONSIBILITY6
03/04/2022440651901Open ↗
12/20/2021421730808Open ↗
12/02/2020440651901Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: SOIL INSPECTION3
07/20/2020421730808Open ↗
06/23/2020421730808Open ↗
06/23/2020421730808Open ↗
▸BISFRAME (2008)/STRUCTURAL WOOD FRAME (2014) INSPECTION1
03/29/2022421730808Open ↗
▸BISDEMOLITION (DM) JOB SIGNOFF1
02/10/2022421730808Open ↗
▸BISCONCRETE - CAST-IN-PLACE1
03/29/2022421730808Open ↗
▸BISTR2: CONCRETE FIELD TESTING TECHNICAL REPORT1
04/04/2022421730808Open ↗
▸BISSUBSURFACE / SOILS INVESTIGATION (BORINGS/TEST PITS)1
12/23/2021421730808Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
03/29/2022421730808Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
03/29/2022421730808Open ↗
▸BISFOOTING AND FOUNDATION INSPECTION1
03/29/2022421730808Open ↗
▸BISMASONRY1
03/29/2022421730808Open ↗
▸Approvals, Objections & Sign-offs8
▸BISLETTERS - SUPPORTING DOCUMENTATION3
03/07/2022440651901Open ↗
03/14/2020421781183Open ↗
01/21/2020421744786Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE2
06/15/2020421730808Open ↗
06/15/2020421730808Open ↗
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
02/18/2022421781183Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
03/07/2022440651901Open ↗
▸BISTAP LETTER - DOM SVC : DEP-DOM1
01/21/2020421744786Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT2
03/04/2022440651901Open ↗
12/02/2020440651901Open ↗
▸BISPROJECT SPECIFIC GENERAL LIABILITY INSURANCE1
01/21/2020421744786Open ↗
▸Filing & Intake Forms8
▸BISEFILING COVER SHEET3
03/13/2020421781183Open ↗
10/23/2019421730808Open ↗
08/30/2019421744786Open ↗
▸BISADDITIONAL INFORMATION2
12/08/2020440651901Open ↗
12/02/2020440651901Open ↗
▸BISBOROUGH INTAKE FORM2
08/10/2020421730808Open ↗
07/20/2020421730808Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
03/24/2020421781183Open ↗
▸Other Documents9
▸BISPLOT DIAGRAM2
06/23/2020421730808Open ↗
06/23/2020421730808Open ↗
▸BISPRELIMINARY1
03/29/2022421730808Open ↗
▸BISSHUTOFF DAMPERS1
03/29/2022421730808Open ↗
▸BISCHIMNEYS1
03/29/2022421730808Open ↗
▸BISLOWEST FLOOR ELEVATION1
12/20/2021421730808Open ↗
▸BISMAINTENANCE INFORMATION1
03/29/2022421730808Open ↗
▸BISPERMANENT CERTIFICATE1
03/29/2022421730808Open ↗
▸BISBPP: FILING REQUIRED1
06/23/2020421730808Open ↗