| Owner | Filings | Most Recent |
|---|---|---|
| P&L Associates | 13 | 03/22/2026 |
| Braddock Ave Owners | 5 | 03/21/2026 |
| Vision Enterprises | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/28/2026 | $13.0M | — | P & L ASSOCIATES, LLC → BAYSIDE 88 CORP. | $211/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Ejc Engineering | 1 | 07/08/2026 |
| Tectonic Engineering & Surveying Co | 4 | 08/25/2025 |
| Scherer Design Group | 1 | 09/01/2023 |
| Tectonic Engineering | 4 | 04/11/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| Construction Permit Services | 10 | 03/21/2026 |
| CCM Services Group | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Levest Electric | specialty_contractor | 7 | 07/08/2026 |
| Metro RF Services | General Contractor | 5 | 03/21/2026 |
| RC3 Electric | specialty_contractor | 3 | 03/21/2026 |
| Current Communications | General Contractor | 1 | 07/08/2026 |
| RSC Electrical Co | Electrical | 1 | 03/21/2026 |
| TLS Construction Group I* | General Contractor | 1 | 09/01/2026 |
| Hudson Plumbing & MCH | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Z & T Engineering | 591 | 1 | 07/08/2026 |
| Tectonic Engineering Cons | 106 | 5 | 08/25/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | TLS Construction Group I* | 08/31/2026 |
| DOB NOW | Plumbing | Signed-off | Hudson Plumbing & MCH | 06/09/2025 |
| DOB NOW | Mechanical Systems | Signed-off | RC3 Electric | 03/14/2025 |
| DOB NOW | Antenna | Signed-off | Current Communications | 11/15/2023 |
| DOB NOW | Antenna | Signed-off | Metro RF Services | 04/27/2022 |
| DOB NOW | Antenna | Permit Issued | Levest Electric | 06/09/2021 |
| DOB NOW | Antenna | Permit Issued | Levest Electric | 04/19/2021 |
| DOB NOW | Antenna | Signed-off | Metro RF Services | 12/22/2020 |
| DOB NOW | Antenna | Permit Issued | Levest Electric | 11/23/2020 |
| DOB NOW | Antenna | Permit Issued | Levest Electric | 03/07/2019 |
| DOB NOW | Antenna | Signed-off | Metro RF Services | 07/31/2018 |
| BIS | PL | ISSUED | P.A.C. Heating | 09/08/2021 |
| BIS | BL | ISSUED | A.M. Sage PLG & Heating | 07/23/2021 |
| BIS | MH | ISSUED | Levest Electric | 11/20/2020 |
| BIS | BL | ISSUED | A.M. Sage PLG & Heating | 07/07/2020 |
| BIS | MH | ISSUED | Brighton Installation Co | 09/27/2019 |
| BIS | BL | ISSUED | A.M. Sage PLG & Heating | 07/11/2019 |
| BIS | MH | ISSUED | Levest Electric | 03/08/2019 |
| BIS | OT | ISSUED | Charles M Dwyer | 07/13/2017 |
| BIS | MH | ISSUED | Folor | 11/18/2015 |
| BIS | OT | ISSUED | Folor | 11/18/2015 |
| BIS | OT | ISSUED | Telcom Engineering GP | 07/03/2014 |
| BIS | OT | ISSUED | Telcom Engineering GP | 06/24/2014 |
| BIS | EQ | ISSUED | Vlad Restoration | 06/06/2014 |
| BIS | OT | ISSUED | Wireless Network Group | 10/30/2006 |
| BIS | OT | ISSUED | Odyssia Global Commercial | 09/15/2004 |
| BIS | PL | ISSUED | Sugar Plumbing | 03/27/2001 |
| BIS | MH | ISSUED | C Enterprises | 01/24/2001 |
| BIS | MH | ISSUED | C Enterprisises | 01/18/2001 |
| BIS | — | ISSUED | Frank Torrone & Sons | 06/16/1997 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/08/2026 | Permit Issued | TLS Construction Group I* | Heating and Air Conditioning Systems, Ventilation Systems | — |
| 08/25/2025 | Signed-off | RC3 Electric | Generators | Generators Kohler KG50 50 kW · Generator ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/25/2025 | Signed-off | Hudson Plumbing & MCH | Gas |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/21/2026 | Complete | Spiro Electric | — |
| 03/09/2021 | Complete | Gotham Wiring Licensed | Boiler Controls |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/30/2026 | HVAC-R and service water heating equipment | Fei Zeng | energy_progress |
| 06/30/2026 | Fire-Resistant Penetrations and Joints | Fei Zeng | special |
| 06/30/2026 | Heating Systems | Fei Zeng | special |
| 06/30/2026 | Post-installed Anchors | Fei Zeng | special |
| 06/30/2026 | Energy Code Compliance Inspections | Fei Zeng | progress |
| 06/30/2026 | Duct leakage testing, insulation and design | Fei Zeng | energy_progress |
| 06/30/2026 | Maintenance information | Fei Zeng | energy_progress |
| 06/30/2026 | HVAC-R and service water heating system controls | Fei Zeng | energy_progress |
| 06/30/2026 | HVAC-R and service water piping design and insulation | Fei Zeng | energy_progress |
| 06/29/2026 | Final | Fei Zeng | progress |
| 06/29/2026 | Mechanical Systems | Fei Zeng | special |
| 09/03/2025 | Fire-Resistant Penetrations and Joints | Manojkumar Patel | special |
| 09/03/2025 | Tenant Protection Plan Compliance | Manojkumar Patel | special |
| 08/22/2025 | Fire-Resistant Penetrations and Joints | Manojkumar Patel | special |
| 08/22/2025 | Tenant Protection Plan Compliance | Manojkumar Patel | special |
| 04/25/2024 | Tenant Protection Plan Compliance | Manojkumar Patel | special |
| 03/18/2024 | Final | Manojkumar Patel | progress |
| 03/18/2024 | Mechanical Systems | Manojkumar Patel | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Verizon | Telecom site | Cellar, Floors 1–6, Roof | Project Q01021388 Project Q00912765 |