| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/10/2021 | $1.5M | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| Yang Engineering | 2 | 01/21/2025 |
| Jimenez Building Consulting | 7 | 10/29/2024 |
| Bayside Associates | 4 | 10/28/2024 |
| Jian Engineering | 6 | 12/08/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| SD Design Studio | 38 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Acer Construction | General Contractor | 13 | 04/09/2026 |
| Winway Development | Scaffold | 10 | 04/09/2026 |
| Acer Construction | Scaffold | 7 | 04/09/2026 |
| Steel Tone Construction | General Contractor | 5 | 04/09/2026 |
| Dynamic Plumbing & Sprinkler | Plumbing | 2 | 07/08/2026 |
| Dynamic Plumbing & Sprinkler | Fire Protection | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Jian Engineering | 7397 | 16 | 01/21/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | Acer Construction | 11/20/2024 |
| DOB NOW | General Construction | Permit Issued | Acer Construction | 10/17/2024 |
| DOB NOW | Plumbing | Signed-off | Citywide Plumbing & Heating & SPKLS | 08/09/2024 |
| DOB NOW | Sprinklers | Signed-off | Citywide Plumbing, Heating & Sprinkler | 08/09/2024 |
| DOB NOW | Construction Fence | Signed-off | Acer Construction | 05/30/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | Acer Construction | 05/30/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | Winway Development | 05/23/2024 |
| DOB NOW | Construction Fence | Signed-off | Winway Development | 02/20/2024 |
| DOB NOW | Supported Scaffold | Signed-off | Acer Construction | 12/28/2023 |
| DOB NOW | Foundation | Signed-off | Acer Construction | 10/12/2023 |
| DOB NOW | General Construction | Permit Issued | Acer Construction | 10/12/2023 |
| DOB NOW | Structural | Signed-off | Acer Construction | 10/12/2023 |
| DOB NOW | Structural | Signed-off | Acer Construction | 07/24/2023 |
| DOB NOW | Earth Work | Signed-off | Acer Construction | 07/24/2023 |
| DOB NOW | Support of Excavation | Signed-off | Acer Construction | 07/24/2023 |
| DOB NOW | General Construction | Permit Issued | Acer Construction | 07/24/2023 |
| DOB NOW | Sprinklers | Signed-off | Citywide Plumbing, Heating & Sprinkler | 07/22/2023 |
| DOB NOW | Plumbing | Signed-off | Citywide Plumbing & Heating & SPKLS | 07/22/2023 |
| DOB NOW | General Construction | Permit Issued | Steel Tone Construction | 06/09/2023 |
| DOB NOW | Support of Excavation | Signed-off | Steel Tone Construction | 06/06/2023 |
| DOB NOW | Structural | Signed-off | Steel Tone Construction | 06/06/2023 |
| DOB NOW | Earth Work | Signed-off | Steel Tone Construction | 06/05/2023 |
| DOB NOW | Construction Fence | Signed-off | Winway Development | 02/24/2023 |
| DOB NOW | Construction Fence | Signed-off | Winway Development | 02/24/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 01/21/2025 | Signed-off | Acer Construction | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric SUZ-KA36NAHZ 40,000 BTU · Condensing Unit ×6 MXZ-SM48NAMHZ 54,000 BTU · Condensing Unit ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/21/2025 | Signed-off | Dynamic Plumbing & Sprinkler | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/21/2025 | Signed-off | Dynamic Plumbing & Sprinkler | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/06/2025 | Complete | Eric & NG Electrical | General Wiring |
| 01/11/2024 | Complete | A.C. Morgan Electric | — |
| 08/09/2023 | Complete | Eric & NG Electrical | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/21/2025 | Signed-off | Acer Construction | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/21/2025 | Signed-off | Acer Construction | Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/21/2025 | Signed-off | Acer Construction | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/08/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/06/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/13/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/01/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/26/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/14/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/17/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/28/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/22/2025 | Fire-Resistant Penetrations and Joints | JIAN DENG | special |
| 01/22/2025 | Sprinkler Systems | JIAN DENG | special |
| 01/22/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | JIAN DENG | special |
| 01/22/2025 | HVAC-R and service water heating equipment | JIAN DENG | energy_progress |
| 01/22/2025 | Maintenance information | JIAN DENG | energy_progress |
| 01/22/2025 | HVAC-R and service water piping design and insulation | JIAN DENG | energy_progress |
| 01/22/2025 | HVAC-R and service water heating system controls | JIAN DENG | energy_progress |
| 01/22/2025 | Energy Code Compliance Inspections | JIAN DENG | progress |
| 01/17/2025 | Energy Code Compliance Inspections | JIAN DENG | progress |
| 01/17/2025 | Maintenance information | JIAN DENG | energy_progress |
| 01/17/2025 | HVAC-R and service water piping design and insulation | JIAN DENG | energy_progress |
| 01/17/2025 | Sprinkler Systems | JIAN DENG | special |
| 01/17/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | JIAN DENG | special |
| 01/17/2025 | Fire-Resistant Penetrations and Joints | JIAN DENG | special |
| 01/17/2025 | HVAC-R and service water heating equipment | JIAN DENG | energy_progress |
| 01/17/2025 | HVAC-R and service water heating system controls | JIAN DENG | energy_progress |
| 11/06/2024 | Exterior lighting power | JIAN DENG | energy_progress |
| 11/06/2024 | Energy Code Compliance Inspections | JIAN DENG | progress |
| 11/06/2024 | Fire-Resistance Rated Construction | JIAN DENG | progress |
| 11/06/2024 | Exterior Insulation and Finish Systems (EIFS) | JIAN DENG | special |
| 11/06/2024 | Structural Stability – Alterations of existing buildings | JIAN DENG | special |
| 11/06/2024 | Fire-Resistant Penetrations and Joints | JIAN DENG | special |
| 11/06/2024 | Concrete - Cast-In-Place | JIAN DENG | special |
| 11/06/2024 | Fenestration air leakage | JIAN DENG | energy_progress |
| 11/06/2024 | Electrical motors and elevators | JIAN DENG | energy_progress |