Converted dwellings or rooming house
42 WEST 91ST STREET
MANHATTAN · BIN 1081770
💬 Discuss this project
1910Year Built
4Stories
C5Building Class
R7-2Zoning
76,968 sfGross Floor Area
96Units
LL97 Covered14 Active Violations ▸
Converted dwellings or rooming house · Owner of record: NYC Housing Authority · 29,105 sf lot · 2.64 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofRoofing Replacement and Rooftop Structure Renovation30p · 2 filings · 20 docs
Floor 3Replace existing gas pipe6p · 1 filing · 11 docs
Floor 2Replace existing gas pipe6p · 1 filing · 11 docs
Floor 1Replace existing gas pipe6p · 1 filing · 11 docs
CellarReplace existing gas pipe6p · 1 filing · 11 docs
Sub-BasementReplace existing gas pipe6p · 1 filing · 11 docs
Site & exteriorTemporary fence installation WSUR BROWNSTONE BL #2121p · 3 filings · 13 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
New York City Housing Authority1807/08/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Joel Phagoo P.E410/24/2025
STV409/05/2025
NYCHA208/04/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
STV803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Zoria HousingScaffold304/08/2026
Zoria HousingGeneral Contractor107/01/2026
J.k.construction New YorkScaffold104/09/2026
D.D.S. Mechanical PBG & HeatingPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Joel Phagoo, PE2416109/12/2025
Alan Margolin & Associates423410/13/2022
Building Lifecycle
All (36)Filed (10)Permit Issued (5)Signed Off (4)Special Inspection (17)
07/06/2026
Signed off — Alteration
WSUR BLDG21_Roof Roofing Replacement and Rooftop Structure Renovation.
M08012243-I1
06/02/2026
Signed off — Alteration
INSTALLATION OF TEMPORARY CHAIN LINK FENCE AS PER PLANS. CHAIN LINK FENCE SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01282206-I1
06/02/2026
Signed off — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01282273-I1
06/02/2026
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01282713-I1
10/24/2025
Filed — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01282273-P1
09/25/2025
Permit issued — General Construction
M08012243-I1-GC-CX
09/23/2025
Permit issued — Construction Fence
M01282206-I1-FN
09/23/2025
Permit issued — Sidewalk Shed
M01282273-I1-SH
09/22/2025
Filed — Alteration
INSTALLATION OF TEMPORARY CHAIN LINK FENCE AS PER PLANS. CHAIN LINK FENCE SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01282206-I1
09/22/2025
Filed — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01282273-I1
09/12/2025
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01282713-I1
09/12/2025
Permit issued — Supported Scaffold
M01282713-I1-SF
09/08/2025
Special inspection requirement — Structural Steel - Welding
Young Suh
09/08/2025
Special inspection requirement — Wood – Seismic Resistance
Young Suh
09/08/2025
Special inspection requirement — Masonry
Young Suh
09/08/2025
Special inspection requirement — Final
Young Suh
09/08/2025
Special inspection requirement — Structural Wood Frame
Young Suh
09/05/2025
Filed — Alteration
WSUR BLDG21_Roof Roofing Replacement and Rooftop Structure Renovation.
M08012243-P3
09/05/2025
Special inspection requirement — Post-installed Anchors
JOEL PHAGOO
08/18/2025
Special inspection requirement — Masonry
08/18/2025
Special inspection requirement — Structural Steel - Welding
08/18/2025
Special inspection requirement — Wood – Seismic Resistance
08/18/2025
Special inspection requirement — Final
08/18/2025
Special inspection requirement — Structural Wood Frame
08/08/2025
Filed — Alteration
WSUR BLDG21_Roof Roofing Replacement and Rooftop Structure Renovation.
M08012243-P2
07/15/2024
Filed — Alteration
WSUR BLDG21_Roof Roofing Replacement and Rooftop Structure Renovation.
M08012243-P1
05/01/2024
Special inspection requirement — Masonry
05/01/2024
Special inspection requirement — Structural Steel - Welding
05/01/2024
Special inspection requirement — Final
05/01/2024
Special inspection requirement — Structural Wood Frame
10/13/2022
Filed — Alteration
WSUR BLDG21_Roof Roofing Replacement and Rooftop Structure Renovation.
M08012243-I1
08/05/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Young Suh
08/04/2021
Filed — Alteration
REPLACE EXISTING GAS PIPE IN ITS ENTIRETY AFTER THE EXISTING GAS METER, THE EXISTING GAS METER IS TO REMAIN.THE REPLACEMENT WORK WILL INCLUDE FROM THE CELLAR LEVEL UP TO BASEMENT, FROM THE BASEMENT UP TO FIRSTFLOOR, FROM THE FIRST FLOOR UP TO THIRD FLOOR
M00444518-P1
08/04/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Young Suh
04/09/2021
Permit issued — Plumbing
M00444518-I1-PL
01/19/2021
Filed — Alteration
REPLACE EXISTING GAS PIPE IN ITS ENTIRETY AFTER THE EXISTING GAS METER, THE EXISTING GAS METER IS TO REMAIN.THE REPLACEMENT WORK WILL INCLUDE FROM THE CELLAR LEVEL UP TO BASEMENT, FROM THE BASEMENT UP TO FIRSTFLOOR, FROM THE FIRST FLOOR UP TO THIRD FLOOR
M00444518-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offZoria Housing09/25/2025
DOB NOWConstruction FenceSigned-offZoria Housing09/23/2025
DOB NOWSidewalk ShedSigned-offJ.k.construction New York09/23/2025
DOB NOWSupported ScaffoldSigned-offZoria Housing09/12/2025
DOB NOWPlumbingSigned-offD.D.S. Mechanical PBG & Heating04/09/2021
BISPLISSUEDDelphi Plumbing & Heating10/14/2009
BISPLISSUEDDelphi Plumbing & Heating08/31/2007
1 project · most recent 08/04/2021
Gas
FiledStatusContractorScope
08/04/2021Signed-offD.D.S. Mechanical PBG & HeatingGas
1 project · most recent 07/21/2025
FiledStatusContractorScope
07/21/2025CompleteAujla Electric—
3 projects · most recent 10/24/2025
Sidewalk Shed Fence Scaffold
FiledStatusContractorScope
10/24/2025Signed-offJ.k.construction New YorkSidewalk Shed
09/22/2025Signed-offZoria HousingFence
09/12/2025Signed-offZoria HousingScaffold
▾Special Inspection Requirements (DOB NOW) — 17
DateRequirementInspectorRole
09/08/2025Structural Steel - WeldingYoung Suhspecial
09/08/2025Wood – Seismic ResistanceYoung Suhspecial
09/08/2025MasonryYoung Suhspecial
09/08/2025FinalYoung Suhprogress
09/08/2025Structural Wood FrameYoung Suhprogress
09/05/2025Post-installed AnchorsJOEL PHAGOOspecial
08/18/2025Masonry—special
08/18/2025Structural Steel - Welding—special
08/18/2025Wood – Seismic Resistance—special
08/18/2025Final—progress
08/18/2025Structural Wood Frame—progress
05/01/2024Masonry—special
05/01/2024Structural Steel - Welding—special
05/01/2024Final—progress
05/01/2024Structural Wood Frame—progress
08/05/2021Fire-Resistant Penetrations and JointsYoung Suhspecial
08/04/2021Fire-Resistant Penetrations and JointsYoung Suhspecial
▾Documents — 49 on file (BIS + DOB NOW)
▸Plans & Drawings10
▸DOB NOWPlans/Sketch8
08/22/2026M08012243-P3Request digital key ↗
08/22/2026M08012243-P2Request digital key ↗
08/22/2026M08012243-P1Request digital key ↗
Showing 3 of 8 on file for this type
▸DOB NOWPlans/Sketch - Plumbing2
09/04/2026M00444518-P1Request digital key ↗
09/04/2026M00444518-I1Request digital key ↗
▸Applications & Permits4
▸DOB NOWLPC Approval/Permit4
08/13/2026M08012243-P3Open ↗
08/13/2026M08012243-P1Open ↗
08/13/2026M08012243-I1Open ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications15
▸DOB NOWDPL-1: Design Professional Seal & Signature10
09/04/2026M00444518-P1Open ↗
09/04/2026M00444518-I1Open ↗
08/22/2026M08012243-P2Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
10/05/2026M01282713-I1Open ↗
09/01/2026M00444518-P1Open ↗
08/25/2026M08012243-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature1
08/25/2026M08012243-I1Open ↗
▸Safety & Tenant Protection2
▸DOB NOWTenant Protection Plan2
09/04/2026M00444518-I1Open ↗
09/04/2026M00444518-P1Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/22/2026M08012243-P2Open ↗
08/22/2026M08012243-I1Open ↗
08/22/2026M08012243-P3Open ↗
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
09/04/2026M00444518-I1Open ↗
▸Approvals, Objections & Sign-offs10
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter10
09/04/2026M00444518-P1Open ↗
09/04/2026M00444518-I1Open ↗
08/22/2026M08012243-P2Open ↗
Showing 3 of 10 on file for this type
▸Other Documents4
▸DOB NOWProof of Historic Building4
08/13/2026M08012243-P1Open ↗
08/13/2026M08012243-P3Open ↗
08/13/2026M08012243-I1Open ↗
Showing 3 of 4 on file for this type