Two stories - detached, small or mid-size
420 BEACH AVENUE
BRONX · BIN 2020733
💬 Discuss this project
1940Year Built
2Stories
A1Building Class
R4AZoning
1,525 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 2,500 sf lot · 0.61 FAR built · Flood zone X
Locations of Work
Architecture
Roof1p · 1 filing · 7 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NY BUILDING ASSOCIATES INC112/17/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
S R SOLAR DESIGN203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
HARVEST POWER LLCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NKM ENGINEERING PLLC6244112/17/2025
Building Lifecycle
All (7)Filed (1)Permit Issued (1)Special Inspection (5)
01/07/2026
Permit issued — Solar
X01325444-I1-SL
12/17/2025
Filed — Alteration
INSTALLATION OF SOLAR PANELS ON EXISTING ROOF. NO CHANGE IN USE, OCCUPANCY, OR EGRESS. NO CHANGE IN BULK
X01325444-I1
11/26/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
NARESH MAHANGU
11/26/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
NARESH MAHANGU
11/26/2025
Special inspection requirement — Energy Code Compliance Inspections
NARESH MAHANGU
11/26/2025
Special inspection requirement — Final
NARESH MAHANGU
11/26/2025
Special inspection requirement — Air barrier - visual inspection
NARESH MAHANGU
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offHARVEST POWER LLC01/07/2026
1 project · most recent 12/04/2025
FiledStatusContractorScope
12/04/2025CompleteISLAND ELECTRIC CORP—
1 project · most recent 12/17/2025
FiledStatusContractorScope
12/17/2025Signed-offHARVEST POWER LLC20 panels, 9.1 kw, 950 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
11/26/2025Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
11/26/2025Structural Stability – Alterations of existing buildingsNARESH MAHANGUspecial
11/26/2025Energy Code Compliance InspectionsNARESH MAHANGUprogress
11/26/2025FinalNARESH MAHANGUprogress
11/26/2025Air barrier - visual inspectionNARESH MAHANGUenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/17/2026X01325444-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
09/01/2026X01325444-I1Open ↗
09/01/2026X01325444-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/17/2026X01325444-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
09/01/2026X01325444-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/17/2026X01325444-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026X01325444-I1Open ↗