| Owner | Filings | Most Recent |
|---|---|---|
| J BUILDERS | 1 | 08/28/2026 |
| TRANSITION | 8 | 07/08/2026 |
| Y Z DEVELOPERS | 17 | 07/08/2026 |
| 4202 13TH AVENUE REALTY | 3 | 03/22/2026 |
| JZ DEVELOPERS | 1 | 03/22/2026 |
| 4202 13 AVE | 20 | 03/21/2026 |
| HOUSING PRESERVATION DEVELOPME | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/01/2017 | $1.6M | — | 4202 13TH AVENUE REALTY LLC → 4202 13 AVE LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| MSM ENGINEERING SERVICES, PLLC | 4 | 08/07/2026 |
| KZ ENGINEERING, P.C | 4 | 06/18/2020 |
| BMG DESIGN BUILD LLC | 1 | 06/11/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| NYC DESIGN FILE | 1 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MANHATTAN D ENTERPRISES | General Contractor | 8 | 07/08/2026 |
| Y&Z DEVELOPERS INC | General Contractor | 8 | 07/08/2026 |
| OWNERS GC NY LLC | General Contractor | 6 | 03/22/2026 |
| BOAZ GOLANI | Electrical | 1 | 03/21/2026 |
| DMITRY LEVIN | Electrical | 1 | 03/21/2026 |
| GREY GOOSE ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Signed-off | Y&Z DEVELOPERS INC | 07/08/2020 |
| DOB NOW | Supported Scaffold | Signed-off | MANHATTAN D ENTERPRISES | 06/18/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | MANHATTAN D ENTERPRISES | 11/12/2019 |
| DOB NOW | Construction Fence | Signed-off | Y&Z DEVELOPERS INC | 10/23/2019 |
| DOB NOW | Construction Fence | Signed-off | Y&Z DEVELOPERS INC | 07/15/2019 |
| DOB NOW | Construction Fence | Signed-off | Y&Z DEVELOPERS INC | 10/22/2018 |
| DOB NOW | Construction Fence | Signed-off | Y&Z DEVELOPERS INC | 10/16/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | MANHATTAN D ENTERPRISES | 08/06/2018 |
| DOB NOW | Construction Fence | Signed-off | Y&Z DEVELOPERS INC | 07/13/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | MANHATTAN D ENTERPRISES | 05/18/2018 |
| BIS | — | ISSUED | OWNERS GC NY LLC | 08/30/2021 |
| BIS | PL | ISSUED | PLBG P & H INC | 01/15/2021 |
| BIS | — | ISSUED | Y&Z DEVELOPERS INC | 07/24/2020 |
| BIS | PL | ISSUED | PLBG P & H INC | 01/10/2020 |
| BIS | — | ISSUED | Y&Z DEVELOPERS INC | 12/06/2019 |
| BIS | — | ISSUED | Y&Z DEVELOPERS INC | 07/22/2019 |
| BIS | — | ISSUED | Y&Z DEVELOPERS INC | 07/11/2019 |
| BIS | — | ISSUED | Y&Z DEVELOPERS INC | 08/13/2018 |
| BIS | — | ISSUED | Y&Z DEVELOPERS INC | 08/13/2018 |
| BIS | — | ISSUED | YATZIV CORP | 07/25/2018 |
| BIS | OT | ISSUED | PRACTICAL APPRAISING &* | 02/17/2016 |
| BIS | OT | ISSUED | PRACTICAL APPRAISING &* | 12/16/2015 |
| BIS | OT | ISSUED | GATEWAY DEMO/CIVIL CORP | 11/13/2015 |
| BIS | — | ISSUED | L S SIGN CO INC | 01/10/1995 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/07/2026 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/21/2021 | Complete | TRUE POWER ELECL CONT LLC | General Wiring |
| 07/01/2020 | Complete | GREY GOOSE ELECTRIC CORP | — |
| 11/25/2019 | Complete | V. VASS ELECTRIC CORP | — |
| 05/29/2018 | Complete | V. VASS ELECTRIC CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/07/2026 | — | — | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/29/2026 | Tenant Protection Plan Compliance | — | special |
| 06/16/2026 | Sprinkler Systems | — | special |
| 06/16/2026 | Tenant Protection Plan Compliance | — | special |
| 06/16/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 06/16/2026 | Post-installed Anchors | — | special |
| 05/25/2026 | Tenant Protection Plan Compliance | — | special |
| 04/28/2026 | Air barrier - visual inspection | — | energy_progress |
| 04/28/2026 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 04/28/2026 | Interior lighting power | — | energy_progress |
| 04/28/2026 | Fenestration air leakage | — | energy_progress |
| 04/28/2026 | Permanent certificate | — | energy_progress |
| 04/28/2026 | Fenestration areas | — | energy_progress |
| 04/28/2026 | Metering | — | energy_progress |
| 04/28/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 04/28/2026 | Structural Stability – Alterations of existing buildings | — | special |
| 04/28/2026 | Energy Code Compliance Inspections | — | progress |
| 04/28/2026 | Fire-Resistance Rated Construction | — | progress |
| 04/28/2026 | Insulation placement and R values | — | energy_progress |