Locations of Work
ArchitectureMechanicalPlumbingGeneral
Permit Issued — active, not yet Signed-off
Floor 1Under Construction24p · 1 filing · 20 docs
ArchitectureDMGeneralMechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Plumbing
Plumbing work in conjunction with tenant fit out.
On file for this project
23 documents · 4 drawing sheets
▾Design Consultants (Architect / Engineer of Record)
▾Special Inspection Agencies
Nothing on file for this building.
Nothing on file for this building.
Nothing on file for this building.
▾Field Inspections (DOB CAP) — 8
| Date | Type | Result | Report |
|---|
| 04/22/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/15/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/02/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/02/2026 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 01/02/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 01/02/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/02/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 12/18/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
▾Special Inspection Requirements (DOB NOW) — 13
| Date | Requirement | Inspector | Role |
|---|
| 12/11/2025 | Tenant Protection Plan Compliance | — | special |
| 12/11/2025 | Fire-Resistant Penetrations and Joints | NING LU | special |
| 12/11/2025 | Energy Code Compliance Inspections | NING LU | progress |
| 12/02/2025 | Fire-Resistant Penetrations and Joints | NING LU | special |
| 12/02/2025 | Tenant Protection Plan Compliance | — | special |
| 12/02/2025 | Energy Code Compliance Inspections | NING LU | progress |
| 09/17/2025 | Fire-Resistance Rated Construction | NING LU | progress |
| 07/28/2025 | Interior lighting power | NING LU | energy_progress |
| 07/28/2025 | Tenant Protection Plan Compliance | NING LU | special |
| 07/28/2025 | Final | NING LU | progress |
| 07/28/2025 | Energy Code Compliance Inspections | NING LU | progress |
| 07/28/2025 | Lighting controls | NING LU | energy_progress |
| 07/28/2025 | Mechanical Systems | NING LU | special |