| Owner | Filings | Most Recent |
|---|---|---|
| New York University | 11 | 03/21/2026 |
| NYU School of Medicine | 3 | 03/21/2026 |
| Nyulmc | 1 | 03/22/2026 |
| NYU Medical Center Condominium | 1 | 03/21/2026 |
| NYU Hospital | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Thornton Tomasetti | 6 | 10/15/2026 |
| Howard I Shapiro & Associates | 2 | 09/22/2026 |
| Jaros Baum & Bolles | 60 | 08/06/2026 |
| Ennead Architects | 10 | 07/30/2026 |
| Douglas P. Gonzalez | 3 | 03/28/2026 |
| Rael Automatic Sprinkler Co | 1 | 02/11/2026 |
| TPG Architecture | 4 | 01/30/2026 |
| Rosa Consulting Engineers | 1 | 01/21/2026 |
| Bronzino Engineering | 1 | 12/08/2025 |
| 360 Engineering | 1 | 04/16/2024 |
| Perkinseastman Architects | 4 | 10/04/2022 |
| Severud Associates | 1 | 09/10/2021 |
| Loring Consulting Engineers | 4 | 07/29/2021 |
| Erik Villari | 2 | 06/30/2021 |
| Tohfaz Uddin PE | 4 | 01/11/2021 |
| LERA Consulting Structural Engineering | 1 | 12/03/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| Outsource Consultants | 134 | 03/21/2026 |
| A1 Expediting Service | 8 | 03/21/2026 |
| Environmental Engineering Solutions | 6 | 03/21/2026 |
| RPO | 2 | 03/21/2026 |
| JMG Consultants | 2 | 03/21/2026 |
| HS Design Studio | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Skanska USA Building | General Contractor | 22 | 08/30/2026 |
| Empire General Contracting | General Contractor | 14 | 07/08/2026 |
| Current Fire Protection | Fire Protection | 9 | 07/08/2026 |
| Cardoza Plumbing | Plumbing | 7 | 07/08/2026 |
| PJP Installers | Scaffold | 6 | 10/14/2026 |
| York Scaffold Equipment | Scaffold | 6 | 07/08/2026 |
| Rael Automatic Sprinkler Co | Fire Protection | 6 | 09/03/2026 |
| NYC Fire Sprinkler | Fire Protection | 5 | 09/12/2026 |
| Sirina Fire Protection | Fire Protection | 4 | 07/08/2026 |
| B.R. Fries & Associates | General Contractor | 4 | 07/08/2026 |
| Fresh Meadow Mechanical | specialty_contractor | 4 | 07/08/2026 |
| Nelson Air Device | General Contractor | 4 | 07/08/2026 |
| Skanska USA Building | Scaffold | 4 | 08/26/2026 |
| Alliance Plumbing | Plumbing | 4 | 07/08/2026 |
| Olympic Plumbing & Heating Service | Plumbing | 4 | 09/09/2026 |
| Louis L.buttermark & Sons | Plumbing | 3 | 07/08/2026 |
| Brosna Construction | General Contractor | 2 | 04/09/2026 |
| Consigli Construction Co | General Contractor | 2 | 07/08/2026 |
| Egg Electric | Electrical | 1 | 03/22/2026 |
| Tri-State Dismantling | Scaffold | 1 | 07/08/2026 |
| Diane Electric | Electrical | 1 | 03/21/2026 |
| Caldwell & Walsh Building Construction | General Contractor | 1 | 07/08/2026 |
| Commercial Electric Cont | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Alan Margolin & Associates | 423 | 58 | 10/15/2026 |
| Clarke Engineering Services | 3795 | 1 | 12/08/2025 |
| Outsource Special Inspection | 2827 | 2 | 01/06/2025 |
| Atlantic Engineeringlabor | 1381 | 18 | 11/22/2022 |
| Atlas ATC Engineering | 8011 | 5 | 11/22/2022 |
| Special Testing & Consulting | 1688 | 1 | 06/16/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | PJP Installers | 10/13/2026 |
| DOB NOW | Sprinklers | Permit Issued | NYC Fire Sprinkler | 09/10/2026 |
| DOB NOW | Plumbing | Permit Issued | Olympic Plumbing & Heating Service | 09/08/2026 |
| DOB NOW | Sprinklers | Permit Issued | Rael Automatic Sprinkler Co | 09/02/2026 |
| DOB NOW | Sprinklers | Permit Issued | Rael Automatic Sprinkler Co | 09/02/2026 |
| DOB NOW | Plumbing | Permit Issued | Olympic Plumbing & Heating Service | 09/01/2026 |
| DOB NOW | Plumbing | Permit Issued | Olympic Plumbing & Heating Service | 09/01/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Skanska USA Building | 08/27/2026 |
| DOB NOW | General Construction | Permit Issued | Skanska USA Building | 08/27/2026 |
| DOB NOW | General Construction | Permit Issued | Skanska USA Building | 08/27/2026 |
| DOB NOW | Construction Fence | Permit Issued | Skanska USA Building | 08/25/2026 |
| DOB NOW | General Construction | Permit Issued | Skanska USA Building | 08/25/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Skanska USA Building | 08/25/2026 |
| DOB NOW | Structural | Permit Issued | Skanska USA Building | 08/25/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Skanska USA Building | 08/24/2026 |
| DOB NOW | Standpipe | Permit Issued | Rael Automatic Sprinkler Co | 08/17/2026 |
| DOB NOW | Sprinklers | Permit Issued | Rael Automatic Sprinkler Co | 08/17/2026 |
| DOB NOW | Sprinklers | Permit Issued | Caj Construction | 08/17/2026 |
| DOB NOW | General Construction | Permit Issued | Skanska USA Building | 08/11/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Skanska USA Building | 08/11/2026 |
| DOB NOW | General Construction | Permit Issued | Skanska USA Building | 07/30/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | PJP Installers | 07/07/2026 |
| DOB NOW | Sprinklers | Permit Issued | Sirina Fire Protection | 06/25/2026 |
| DOB NOW | Plumbing | Permit Issued | Alliance Plumbing | 06/22/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Consigli Construction Co | 04/17/2026 |
| DOB NOW | General Construction | Permit Issued | Consigli Construction Co | 04/17/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | PJP Installers | 04/08/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Brosna Construction | 03/27/2026 |
| DOB NOW | General Construction | Permit Issued | Brosna Construction | 03/27/2026 |
| DOB NOW | General Construction | Permit Issued | Skanska USA Building | 03/26/2026 |
| DOB NOW | Structural | Permit Issued | Skanska USA Building | 03/26/2026 |
| DOB NOW | Sprinklers | Permit Issued | Rael Automatic Sprinkler Co | 03/03/2026 |
| DOB NOW | General Construction | Permit Issued | Skanska USA Building | 02/11/2026 |
| DOB NOW | General Construction | Permit Issued | Skanska USA Building | 02/06/2026 |
| DOB NOW | Structural | Permit Issued | Skanska USA Building | 02/04/2026 |
| DOB NOW | Construction Fence | Permit Issued | Skanska USA Building | 01/29/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Tri-State Dismantling | 01/22/2026 |
| DOB NOW | Plumbing | Permit Issued | Olympic Plumbing & Heating Service | 12/11/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | Skanska USA Building | 12/01/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | Elm Suspension Systems | 09/25/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 03/28/2026 | — | — | Air Conditioning Systems | Cooling __Junk__ PW011 38,900 BTU ×1 |
| 07/09/2025 | Permit Issued | Skanska USA Building | Air Conditioning Systems, Generators, Heating and Air Conditioning Systems, Heating Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/06/2026 | Permit Issued | Sirina Fire Protection | Sprinkler System |
| 06/10/2026 | Permit Issued | Rael Automatic Sprinkler Co | 40 heads |
| 06/08/2026 | Permit Issued | Rael Automatic Sprinkler Co | Sprinkler System |
| 03/28/2026 | — | — | Sprinkler System |
| 07/28/2025 | Permit Issued | Rael Automatic Sprinkler Co | 14 heads |
| 07/09/2025 | Permit Issued | Rael Automatic Sprinkler Co | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/15/2026 | — | — | Storm |
| 06/10/2026 | Permit Issued | Olympic Plumbing & Heating Service | Water/Sanitary |
| 06/08/2026 | Permit Issued | Olympic Plumbing & Heating Service | Water/Sanitary |
| 03/28/2026 | — | — | Medical Gas, Water/Sanitary |
| 07/28/2025 | Permit Issued | Olympic Plumbing & Heating Service | Water/Sanitary |
| 07/09/2025 | Permit Issued | Olympic Plumbing & Heating Service | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/09/2026 | Permit Issued | Bigman Brothers | General Wiring |
| 07/09/2026 | Permit Issued | Bigman Brothers | General Wiring |
| 01/12/2026 | Permit Issued | Diane Electric | General Wiring |
| 07/22/2025 | Complete | Gilston Electrical Contng | General Wiring |
| 03/25/2025 | Complete | NYU Hospitals Center | — |
| 03/25/2025 | Complete | NYU Hospitals Center | — |
| 04/17/2024 | Permit Issued | Top Shelf Electric | — |
| 03/15/2022 | Complete | Gilston Electrical Contng | General Wiring |
| 03/10/2022 | Complete | Bigman Brothers | General Wiring |
| 01/11/2022 | Complete | Bigman Brothers | General Wiring |
| 03/05/2021 | Complete | E-J Electric Installation Co | General Wiring |
| 01/12/2021 | Complete | Gilston Electrical Contng | General Wiring |
| 01/08/2021 | Cancelled | Stanco System Electrical Cont | — |
| 01/08/2021 | Cancelled | Stanco System Electrical Cont | — |
| 02/19/2020 | Cancelled | Bigman Brothers | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/15/2026 | Permit Issued | Skanska USA Building | Concrete |
| 08/06/2026 | Permit Issued | Sirina Fire Protection | 1 scope_items |
| 06/23/2026 | — | — | Concrete |
| 03/28/2026 | — | — | Steel |
| 07/09/2025 | Permit Issued | Skanska USA Building | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/08/2025 | Permit Issued | Skanska USA Building | Fence |
| 04/16/2024 | Permit Issued | PJP Installers | Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/30/2026 | Permit Issued | Elm Suspension Systems | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/28/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/22/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/07/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 07/17/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 07/17/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 07/02/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/27/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/09/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/28/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/27/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/08/2024 | Certified Medical Gas - MG - PL - Finish | Certified | View ↗ |
| 03/08/2024 | Certified Medical Gas - MG - PL - Roughing | Certified | View ↗ |
| 03/08/2024 | Certified Medical Gas - MG - PL - Test | Certified | View ↗ |
| 06/27/2023 | Certified Medical Gas - MG - PL - Finish | Certified | View ↗ |
| 06/27/2023 | Certified Medical Gas - MG - PL - Roughing | Certified | View ↗ |
| 06/27/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/27/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/13/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/24/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/20/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/29/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/16/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/21/2022 | Certified Medical Gas - MG - PL - Finish | Certified | View ↗ |
| 03/21/2022 | Certified Medical Gas - MG - PL - Roughing | Certified | View ↗ |
| 03/21/2022 | Certified Medical Gas - MG - PL - Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/22/2026 | Concrete - Cast-In-Place | Young Suh | special |
| 09/22/2026 | Subsurface Conditions – Fill Placement & In-Place Density | Young Suh | special |
| 09/09/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Young Suh | special |
| 09/01/2026 | Final | — | progress |
| 08/13/2026 | Post-installed Anchors | Young Suh | special |
| 08/13/2026 | HVAC-R and service water heating equipment | Young Suh | energy_progress |
| 08/13/2026 | Interior lighting power | Young Suh | energy_progress |
| 08/13/2026 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | Young Suh | special |
| 08/13/2026 | Mechanical Systems | Young Suh | special |
| 08/13/2026 | Duct leakage testing, insulation and design | Young Suh | energy_progress |
| 08/13/2026 | Maintenance information | Young Suh | energy_progress |
| 08/13/2026 | HVAC-R and service water heating system controls | Young Suh | energy_progress |
| 08/13/2026 | Lighting controls | Young Suh | energy_progress |
| 08/13/2026 | Final | Young Suh | progress |
| 08/07/2026 | Air barrier - visual inspection | Young Suh | energy_progress |
| 08/07/2026 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | Young Suh | special |
| 08/07/2026 | Fire-Resistance Rated Construction | Young Suh | progress |
| 08/07/2026 | Fire-Resistant Penetrations and Joints | Young Suh | special |
| 08/07/2026 | Luminous Exit Path Markings | Young Suh | special |
| 08/07/2026 | Fenestration and door U-factor and product ratings | Young Suh | energy_progress |
| 08/07/2026 | Fenestration areas | Young Suh | energy_progress |
| 08/07/2026 | Final | Young Suh | progress |
| 08/07/2026 | Insulation placement and R values | Young Suh | energy_progress |
| 08/07/2026 | Fenestration air leakage | Young Suh | energy_progress |
| 08/07/2026 | Energy Code Compliance Inspections | Young Suh | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| NYU Langone Health | Medical / Healthcare | Floors 1–3, 6–8, 11, 12, Roof | Project M01442314 Project M01262482 Project M01338928 Project M01252914 Project M01163241 Project M01023901 Project M00960331 Project M08005776 Project M08005791 Project M08005815 Project M08005762 Project M00566255 |
| NYU Kimmel | Medical / Healthcare | Floors 1–18, 20 | Project M01391832 Project M01349859 Project M01221162 Project M00953246 Project M00960184 Project M00836366 Project M00762104 Project M00763102 Project M00704007 Project M00704037 Project M00566262 Project M00566277 |
| NYU Hospitals Center Helen L. and Martin S. Kimmel Pavilion | Medical / Healthcare | — | Project M01329315 |
| Compass | Office | Floor 20 | Project M00956922 |