← Back
BRONX
4241 WEBSTER AVENUE
BRONX · BIN 2131342
💬 Discuss this project
—Year Built
—Stories
—Building Class
—Zoning
—Gross Floor Area
—Units
Locations of Work
ArchitectureGeneral
Bulkhead1p · 1 filing · 7 docs
Floor 81p · 1 filing · 7 docs
Floor 7
Floor 6
Floor 5
Floor 4
Floor 31p · 1 filing · 7 docs
Floor 21p · 1 filing · 7 docs
Floor 11p · 1 filing · 7 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
GRUN GROUP109/15/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
LEANDRO NILS DICKSON ARCHITECT, LLC309/03/2026
Building Lifecycle
All (22)Filed (3)Special Inspection (19)
09/03/2026
Filed — New Building
INSTALLATION OF A TEMPORARY WOODEN CONSTRUCTION FENCE
X01433269-S2
08/18/2026
Filed — New Building
INSTALLATION OF A TEMPORARY WOODEN CONSTRUCTION FENCE
X01433269-S1
07/22/2026
Filed — New Building
INSTALLATION OF A TEMPORARY WOODEN CONSTRUCTION FENCE
X01433269-I1
07/21/2026
Special inspection requirement — Air barrier - visual inspection
07/20/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
07/20/2026
Special inspection requirement — Energy Code Compliance Inspections
07/20/2026
Special inspection requirement — Fire-Resistance Rated Construction
07/20/2026
Special inspection requirement — Interior lighting power
07/20/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
07/20/2026
Special inspection requirement — Electrical motors and elevators
07/20/2026
Special inspection requirement — Lighting controls
07/20/2026
Special inspection requirement — Fenestration areas
07/20/2026
Special inspection requirement — Air barrier — testing
07/20/2026
Special inspection requirement — Exterior lighting power
07/20/2026
Special inspection requirement — Lighting in dwelling units
07/20/2026
Special inspection requirement — Air barrier continuity plan testing
07/20/2026
Special inspection requirement — Insulation placement and R values
07/20/2026
Special inspection requirement — Maintenance information
07/20/2026
Special inspection requirement — Fenestration air leakage
07/20/2026
Special inspection requirement — Metering
07/20/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
07/20/2026
Special inspection requirement — Protection of exposed foundation insulation
Nothing on file for this building.
1 project · most recent 08/10/2026
FiledStatusContractorScope
08/10/2026Permit IssuedHIVOLTS ELECTRICAL INC1 meters, 1 new_meters
1 project · most recent 09/03/2026
Fence
FiledStatusContractorScope
09/03/2026——Fence
▾Special Inspection Requirements (DOB NOW) — 19
DateRequirementInspectorRole
07/21/2026Air barrier - visual inspection—energy_progress
07/20/2026Fire-Resistant Penetrations and Joints—special
07/20/2026Energy Code Compliance Inspections—progress
07/20/2026Fire-Resistance Rated Construction—progress
07/20/2026Interior lighting power—energy_progress
07/20/2026Fenestration and door U-factor and product ratings—energy_progress
07/20/2026Electrical motors and elevators—energy_progress
07/20/2026Lighting controls—energy_progress
07/20/2026Fenestration areas—energy_progress
07/20/2026Air barrier — testing —energy_progress
07/20/2026Exterior lighting power—energy_progress
07/20/2026Lighting in dwelling units—energy_progress
07/20/2026Air barrier continuity plan testing—energy_progress
07/20/2026Insulation placement and R values—energy_progress
07/20/2026Maintenance information—energy_progress
07/20/2026Fenestration air leakage—energy_progress
07/20/2026Metering—energy_progress
07/20/2026Exterior Insulation and Finish Systems (EIFS)—special
07/20/2026Protection of exposed foundation insulation—energy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/16/2026X01433269-I1Request digital key ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram1
08/16/2026X01433269-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/16/2026X01433269-I1Open ↗
▸Seals & Professional Certifications3
▸DOB NOWDPL-1: Design Professional Seal & Signature3
09/15/2026X01433269-S2Open ↗
08/19/2026X01433269-S1Open ↗
08/16/2026X01433269-I1Open ↗
▸Other Documents1
▸DOB NOWSite Survey: Initial1
08/16/2026X01433269-I1Open ↗