| Owner | Filings | Most Recent |
|---|---|---|
| 79TH STREET TENANTS | 26 | 07/08/2026 |
| MAXWELL-KATES, INC. | 26 | 03/21/2026 |
| PLATINUM SERVICES NY | 9 | 07/08/2026 |
| 425 EAST 79TH STREET OWNERS | 4 | 03/21/2026 |
| 79ST TENNENTS CORP CO-OP | 4 | 03/21/2026 |
| 425 EAST 79TH STREET TENANTS COR | 3 | 03/21/2026 |
| 79 ST TENNENTS CORP CO-OP | 2 | 03/21/2026 |
| TM CONSTRUCTION | 1 | 03/22/2026 |
| MAXWELL KATE 9 ES 38TH ST | 1 | 03/21/2026 |
| PRES | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| G.PALLADINO LLC | 10 | 07/27/2026 |
| ASR ENGINEERING PC | 1 | 07/07/2025 |
| JOCK DEBOER, AIA | 3 | 12/20/2024 |
| ROBERT GERMAIN JR. PE | 6 | 07/10/2024 |
| PORTER CLAPP ARCHITECTS | 1 | 10/30/2023 |
| HC ARCHITECT, PC | 4 | 12/01/2022 |
| KOJO SIMPSON ARCHITECT | 1 | 07/01/2022 |
| KELLEY DESIGN | 1 | 06/08/2022 |
| ENGINEERING PROFESSIONAL SERVICE P. | 2 | 04/19/2022 |
| ASHRAF CORP | 5 | 07/29/2021 |
| WSP | 1 | 05/26/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| A+ EXPEDITING | 6 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 4 | 03/21/2026 |
| SYNCHRON EXPEDITING | 6 | 03/21/2026 |
| ZIUM ARCH | 4 | 03/21/2026 |
| ARINNITY NYC | 2 | 03/21/2026 |
| HH BUILDING CONSULTING & ARCHITECTU | 6 | 03/21/2026 |
| NAPHTALI DEUTSCH ARCHITECTURE | 4 | 03/21/2026 |
| CADKAY | 2 | 03/21/2026 |
| TRIBECA CONST CONSULTING | 2 | 03/21/2026 |
| PROGENY MANAGEMENT & EXPEDITING SER | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GOTHAM GENERAL CARPENTRY | General Contractor | 6 | 07/08/2026 |
| C C CONTROLLED COMBUSTION | General Contractor | 4 | 03/21/2026 |
| INTERSYSTEM INSTALLATION | General Contractor | 4 | 07/08/2026 |
| PLATINUM SERVICES NY LLC | General Contractor | 4 | 07/08/2026 |
| GBI CONSTRUCTION CORP | General Contractor | 3 | 03/21/2026 |
| RENOVATION BY MY HOME INC | General Contractor | 3 | 07/08/2026 |
| HTC CONSTRUCTION MANAGEMENT | General Contractor | 3 | 03/21/2026 |
| VAN GOGH PAINTERS LLC | General Contractor | 3 | 03/21/2026 |
| CC CONTROLLED PLBG CO.,IN | Plumbing | 2 | 07/08/2026 |
| M&G PLUMBING AND HEATING | Plumbing | 2 | 07/08/2026 |
| TM CONSTRUCTION OF NY INC. | General Contractor | 1 | 07/08/2026 |
| ACCURATE MECHANICAL INC | Plumbing | 1 | 07/08/2026 |
| AURA PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| HYDROKINETIC PLBG & HTG I | Plumbing | 1 | 07/08/2026 |
| ANTHONY LUCIANO | Electrical | 1 | 03/21/2026 |
| TMS PLBG & HEATING CORP | Plumbing | 1 | 07/08/2026 |
| ARGON ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| EMPIRE LIC ELECL CONTRS | Electrical | 1 | 03/22/2026 |
| MAZZA, JOHN | Electrical | 1 | 03/21/2026 |
| NION ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| PAUL COLLETTA | Electrical | 1 | 03/21/2026 |
| PCS ELECTRICAL SVCS INC | Electrical | 1 | 03/22/2026 |
| TIKVAH ELECTRIC CO, INC. | Electrical | 1 | 03/22/2026 |
| GALLERY RESTORATION LTD | General Contractor | 1 | 07/08/2026 |
| GAUDIOSO CONTRACTING INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ASR ENGINEERING PC | 8404 | 1 | 07/07/2025 |
| JOCK DEBOER, AIA - SIA | 7008 | 3 | 12/20/2024 |
| ROBERT F. GERMAIN JR. PE | 5100 | 6 | 07/10/2024 |
| DEAN MENDEZ ARCHITECT, P. | 8621 | 1 | 03/20/2024 |
| PORTER CLAPP ARCHITECTS, | 5343 | 1 | 10/30/2023 |
| BEYOND ARCH LLC | 3600 | 2 | 12/01/2022 |
| ERIK SUN, ARCHITECT, PLLC | 3010 | 1 | 06/08/2022 |
| BUILDTECH ENGINEERING | 6369 | 1 | 04/19/2022 |
| WSP USA CORP | 1848 | 1 | 05/26/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | M&G PLUMBING AND HEATING | 02/13/2026 |
| DOB NOW | General Construction | Signed-off | GOTHAM GENERAL CARPENTRY | 02/05/2026 |
| DOB NOW | Plumbing | Permit Issued | M&G PLUMBING AND HEATING | 08/22/2025 |
| DOB NOW | General Construction | Signed-off | GOTHAM GENERAL CARPENTRY | 08/12/2025 |
| DOB NOW | General Construction | Signed-off | GBI CONSTRUCTION CORP | 08/08/2025 |
| DOB NOW | Plumbing | Signed-off | CC CONTROLLED PLBG CO.,IN | 07/24/2024 |
| DOB NOW | General Construction | Permit Issued | GOTHAM GENERAL CARPENTRY | 05/10/2024 |
| DOB NOW | General Construction | Permit Issued | RENOVATION BY MY HOME INC | 03/04/2024 |
| DOB NOW | Plumbing | Permit Issued | TMS PLBG & HEATING CORP | 02/29/2024 |
| DOB NOW | General Construction | Signed-off | C C CONTROLLED COMBUSTION | 01/03/2024 |
| DOB NOW | General Construction | Permit Issued | RENOVATION BY MY HOME INC | 12/15/2023 |
| DOB NOW | General Construction | Signed-off | TM CONSTRUCTION OF NY INC | 12/08/2023 |
| DOB NOW | Boiler Equipment | Signed-off | C C CONTROLLED COMBUSTION | 09/20/2023 |
| DOB NOW | General Construction | Signed-off | C C CONTROLLED COMBUSTION | 09/20/2023 |
| DOB NOW | Plumbing | Signed-off | CC CONTROLLED PLBG CO.,IN | 09/20/2023 |
| DOB NOW | General Construction | Signed-off | GAUDIOSO CONTRACTING | 06/23/2023 |
| DOB NOW | Plumbing | Signed-off | AURA PLUMBING INC | 07/05/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | PLATINUM SERVICES NY LLC | 07/04/2022 |
| DOB NOW | General Construction | Signed-off | VAN GOGH PAINTERS LLC | 06/20/2022 |
| DOB NOW | Plumbing | Signed-off | HYDROKINETIC PLBG & HTG I | 05/31/2022 |
| DOB NOW | General Construction | Signed-off | GALLERY RESTORATION LTD | 05/23/2022 |
| DOB NOW | Structural | Permit Issued | GOTHAM GENERAL CARPENTRY | 08/03/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | PLATINUM SERVICES NY LLC | 07/09/2021 |
| DOB NOW | Plumbing | Permit Issued | ANTHONY DISABATO | 07/02/2021 |
| DOB NOW | General Construction | Signed-off | GOTHAM GENERAL CARPENTRY | 05/25/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | INTERSYSTEM INSTALLATION | 09/24/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | INTERSYSTEM INSTALLATION | 10/02/2019 |
| BIS | OT | ISSUED | DJM NYC, LLC | 02/18/2022 |
| BIS | OT | ISSUED | DJM NYC, LLC | 02/12/2021 |
| BIS | OT | ISSUED | DJM NYC, LLC | 08/19/2020 |
| BIS | OT | ISSUED | ALMA DESIGN INC | 07/14/2020 |
| BIS | OT | ISSUED | DJM NYC, LLC | 03/12/2020 |
| BIS | OT | ISSUED | BARRY FISHELBERG CO., INC. | 08/08/2017 |
| BIS | PL | ISSUED | F1 MECHANICAL INC | 07/26/2017 |
| BIS | OT | ISSUED | BARRY FISHELBERG CO., INC. | 07/17/2017 |
| BIS | OT | ISSUED | WK RENOVATION CORP | 11/28/2016 |
| BIS | PL | ISSUED | SUPERB PLUMBING & HEATING | 09/19/2016 |
| BIS | OT | ISSUED | WK RENOVATION CORP | 08/26/2016 |
| BIS | OT | ISSUED | DJM NYC, LLC | 01/15/2015 |
| BIS | EQ | ISSUED | ROCKLEDGE SCAFFOLD CORP | 09/19/2014 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/27/2026 | Signed-off | M&G PLUMBING AND HEATING | Gas, Water/Sanitary |
| 10/28/2025 | Permit Issued | M&G PLUMBING AND HEATING | Gas, Water/Sanitary |
| 12/20/2024 | Permit Issued | TMS PLBG & HEATING CORP | Gas, Water/Sanitary |
| 07/10/2024 | Signed-off | CC CONTROLLED PLBG CO.,IN | Gas |
| 10/18/2021 | Permit Issued | ACCURATE MECHANICAL INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/28/2026 | Permit Issued | PCS ELECTRICAL SVCS INC | General Wiring |
| 02/13/2026 | Permit Issued | PCS ELECTRICAL SVCS INC | General Wiring |
| 01/30/2026 | Permit Issued | JAM ELECTRICAL CORP | — |
| 09/17/2025 | Complete | POWER UP NYC ELECTRIC COR | General Wiring |
| 08/18/2025 | Complete | PCS ELECTRICAL SVCS INC | General Wiring |
| 07/01/2025 | Complete | SUNBIRD ELECTRICAL CONTR | General Wiring |
| 03/31/2025 | Permit Issued | KJK ELECTRIC INC | General Wiring |
| 02/10/2025 | Complete | ROBERT CHIMENTI | — |
| 01/28/2025 | Complete | N.Z. PILGRIM ELECTRIC INC | General Wiring |
| 07/02/2024 | Complete | NASH ELECTRIC SERVICES IN | General Wiring |
| 05/17/2024 | Complete | EMPIRE LIC ELECL CONTRS | General Wiring |
| 04/17/2024 | Complete | ARGON ELECTRICAL CORP | General Wiring |
| 06/27/2023 | Complete | SUNBIRD ELECTRICAL CONTR | General Wiring |
| 04/06/2023 | Complete | EMPIRE LIC ELECL CONTRS | — |
| 02/23/2023 | Complete | NION ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/26/2021 | Permit Issued | GOTHAM GENERAL CARPENTRY | Steel |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/13/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/28/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/24/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/24/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/19/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/09/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 01/30/2026 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 09/25/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/18/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/23/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/02/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/30/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/26/2024 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 04/30/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/24/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/18/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/05/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/03/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/23/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/28/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/19/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/20/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/16/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/20/2021 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/20/2021 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/18/2025 | Energy Code Compliance Inspections | GEORGE PALLADINO | progress |
| 11/18/2025 | Final | GEORGE PALLADINO | progress |
| 11/18/2025 | Lighting controls | GEORGE PALLADINO | energy_progress |
| 11/18/2025 | Interior lighting power | GEORGE PALLADINO | energy_progress |
| 11/18/2025 | Lighting in dwelling units | GEORGE PALLADINO | energy_progress |
| 10/20/2025 | Lighting controls | GEORGE PALLADINO | energy_progress |
| 10/20/2025 | Interior lighting power | GEORGE PALLADINO | energy_progress |
| 10/20/2025 | Energy Code Compliance Inspections | GEORGE PALLADINO | progress |
| 10/20/2025 | Final | GEORGE PALLADINO | progress |
| 10/20/2025 | Lighting in dwelling units | GEORGE PALLADINO | energy_progress |
| 01/28/2025 | Insulation placement and R values | Jock deBoer | energy_progress |
| 01/28/2025 | Lighting controls | Jock deBoer | energy_progress |
| 01/28/2025 | Fire-Resistance Rated Construction | Jock deBoer | progress |
| 01/28/2025 | Fire-Resistant Penetrations and Joints | Jock deBoer | special |
| 01/28/2025 | Final | Jock deBoer | progress |
| 01/28/2025 | Energy Code Compliance Inspections | Jock deBoer | progress |
| 01/28/2025 | Lighting in dwelling units | Jock deBoer | energy_progress |
| 12/12/2024 | Final | Jock deBoer | progress |
| 12/12/2024 | Fire-Resistance Rated Construction | Jock deBoer | progress |
| 12/12/2024 | Energy Code Compliance Inspections | Jock deBoer | progress |
| 12/12/2024 | Fire-Resistant Penetrations and Joints | Jock deBoer | special |
| 12/12/2024 | Lighting in dwelling units | Jock deBoer | energy_progress |
| 12/12/2024 | Insulation placement and R values | Jock deBoer | energy_progress |
| 12/12/2024 | Lighting controls | Jock deBoer | energy_progress |
| 07/12/2024 | Fuel-Oil Storage and Fuel-Oil Piping Systems | Robert Germain Jr. | special |