← Back
Office with commercial, 7-19 stories
425 MADISON AVENUE
MANHATTAN · BIN 1035443
💬 Discuss this project
1927Year Built
19Stories
O6Building Class
C5-3Zoning
102,519 sfGross Floor Area
43Units
LL97 Covered1 Open Violation ▸FISP: SAFE
Office with commercial, 7-19 stories · Owner of record: 425 MADISON ASSOCIATE · 6,484 sf lot · 15.81 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentLandscapeCivilGeneralOther
Permit Issued — active, not yet Signed-off
Roof7p · 4 filings · 20 docs
Floor 1824p · 3 filings · 20 docs
Floor 17
Floor 16
Floor 15
Floor 14
Floor 13
Floor 12
Floor 11
Floor 10
Floor 9
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2Under Construction14p · 1 filing · 20 docs
Floor 1Under Construction46p · 5 filings · 20 docs
Cellar52p · 4 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
ABS PARTNERS REAL ESTATE LLC4108/08/2026
MWD PARTNERS207/30/2026
T-MOBILE607/08/2026
AR GROUP OF RESTAURANT504/09/2026
SILK HALPERN REALTY ASSOCIATES9603/22/2026
425 MADISON ASSOCIATES1803/22/2026
425 MADISON ASSOCIATE SIL103/22/2026
DOLMEN CONTRACTINGS503/22/2026
SICK AND HALPERN ASSOC103/22/2026
VERIZON WIRELESS103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
EPAC BUILDING CONSULTING INC1203/21/2026
J A EXPEDITING603/21/2026
A TECH ENGINEERING NYC203/21/2026
INDESIGN STUDIO203/21/2026
NY EXPEDITERS103/21/2026
JAY'S BUILDING CONSULTING INC.803/21/2026
GREEN LIGHT EXPEDITING LLC1003/21/2026
CCM CONSULTING GROUP, INC.203/21/2026
AE DESIGN SOLUTION403/21/2026
GC1 EXPEDITING403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SPRING SCAFFOLDING LLCGeneral Contractor607/08/2026
EVEREST SCAFFOLDING INCGeneral Contractor403/21/2026
SKYLINE RESTORATION INCGeneral Contractor307/08/2026
ANDAMIO SCAFFOLDING LLCGeneral Contractor303/21/2026
OVERLAND CONTRACTING INCGeneral Contractor303/21/2026
AVON PLBG & HTG INCFire Protection208/08/2026
BEAM ENTERPRISES INCGeneral Contractor207/30/2026
JFZ CONSTRUCTION, INCGeneral Contractor207/08/2026
EXPERT FIRE SPRINKLER,LLCFire Protection207/08/2026
DELTA POWER ELECTRICALElectrical203/22/2026
ZAQ CONSTRUCTION INCGeneral Contractor207/08/2026
AD LINE NYC INCGeneral Contractor208/18/2026
HP SERVICES INCPlumbing107/08/2026
I DO PLUMBING & HTG INCPlumbing107/08/2026
LG ELITE PLUMBING INCPlumbing107/08/2026
SMART PLBG & HTG CORPPlumbing106/28/2026
TAVELLA PLBG & HTG CORPPlumbing107/08/2026
BARBIERO, THOMASElectrical103/21/2026
NEPTUNE SIGNS AWNINGSScaffold107/08/2026
BOROWIDE ELECT'L CONTR'SElectrical103/22/2026
DIMOS PAPADIMASElectrical103/21/2026
LANDI, GElectrical103/21/2026
MICHAEL MURPHYElectrical103/21/2026
MURPHY, MICHAELElectrical103/21/2026
PAUL BOCCIAElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CROSSCHECK INSPECTION SER544507/31/2026
GILSANZ MURRAY STEFICEK240105/14/2026
ZELTA INSPECT LLC7764404/22/2026
YOU GAO9407103/06/2025
A TECH ENGINEERING NYC, P6738102/14/2025
JUST CONSULTING ENGINEERI5865612/07/2024
CHONG ENGINEERING P.C.7411203/30/2023
HPL ENGINEERING PC5613103/09/2023
KM CONSULTING NY, INC.5305107/28/2021
R MARSAC CONSULTING LLC329205/24/2021
Building Lifecycle
All (262)Filed (39)Permit Issued (33)Signed Off (12)Facade (FISP) (12)Violation (60)Inspection (24)Objection (52)Special Inspection (30)
09/11/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
09/10/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
09/01/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
08/20/2026
Signed off — Alteration
MECHANICAL FILING FOR COC PURPOSE ONLY, ALL WORK DONE UNDER APPLICATION # M01198715-I1
M01389904-I1
08/17/2026
Permit issued — Mechanical Systems
M01389904-I1-MS
08/07/2026
Permit issued — Sprinklers
M01198715-S1-EW-SP
08/06/2026
Special inspection requirement — Sprinkler Systems
EUGENE BIFULCO
08/06/2026
Special inspection requirement — HVAC-R and service water heating equipment
ERIK LIEPINS
08/06/2026
Special inspection requirement — HVAC-R and service water heating system controls
ERIK LIEPINS
08/06/2026
Special inspection requirement — Maintenance information
ERIK LIEPINS
07/31/2026
Filed — Alteration
SUBSEQUENT FILING FOR PLUMBING AND SPRINKLER WORKS
M01198715-P6
07/29/2026
Permit issued — Structural
M01384593-S1-ST
07/28/2026
Permit issued — General Construction
M01384593-I1-GC
05/14/2026
Filed — Alteration
De Janeiro- APPLICATION IS FILED FOR INTERIOR RENOVATION IN EXISTING RETAIL SPACE-REMOVAL & INSTALLATION OF NON-LOAD BEARING PARTITIONS, REMOVAL OF CONVENIENCE STAIR, FINISHES & ALL OTHER RELATED WORK AS PER PLANS. NO CHANGES TO USE, EGRESS OR OCCUPANCY
M01384593-I1
05/14/2026
Filed — Alteration
De Janeiro- APPLICATION IS FILED FOR INTERIOR RENOVATION IN EXISTING RETAIL SPACE-REMOVAL & INSTALLATION OF NON-LOAD BEARING PARTITIONS, REMOVAL OF CONVENIENCE STAIR, FINISHES & ALL OTHER RELATED WORK AS PER PLANS. NO CHANGES TO USE, EGRESS OR OCCUPANCY
M01384593-S1
04/22/2026
Filed — Alteration
MECHANICAL FILING FOR COC PURPOSE ONLY, ALL WORK DONE UNDER APPLICATION # M01198715-I1
M01389904-I1
04/21/2026
Filed — Alteration
SUBSEQUENT FILING FOR PLUMBING AND SPRINKLER WORKS
M01198715-P5
04/21/2026
Special inspection requirement — Maintenance information
04/21/2026
Special inspection requirement — HVAC-R and service water heating system controls
04/21/2026
Special inspection requirement — HVAC-R and service water heating equipment
04/21/2026
Special inspection requirement — Sprinkler Systems
EUGENE BIFULCO
04/16/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
04/14/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
04/09/2026
Special inspection requirement — Sprayed fire-resistant materials
Gary Steficek
04/09/2026
Special inspection requirement — Structural Steel - Welding
Gary Steficek
04/09/2026
Special inspection requirement — Structural Steel - Details
Gary Steficek
04/09/2026
Special inspection requirement — Structural Steel - High Strength Bolting
Gary Steficek
04/09/2026
Special inspection requirement — Final
Gary Steficek
04/08/2026
Special inspection requirement — Final
Anthony Nicholas
03/17/2026
Permit issued — Plumbing
M01143976-S2-EW-SP
02/02/2026
Signed off — Alteration
SUBSEQUENT FILING FOR PLUMBING AND SPRINKLER WORKS
M01198715-I1
01/29/2026
Filed — Alteration
SUBSEQUENT FILING FOR PLUMBING AND SPRINKLER WORKS
M01198715-P4
01/27/2026
Special inspection requirement — Duct leakage testing, insulation and design
ERIK LIEPINS
01/27/2026
Special inspection requirement — Fenestration air leakage
ERIK LIEPINS
01/27/2026
Special inspection requirement — Fenestration areas
ERIK LIEPINS
01/27/2026
Special inspection requirement — HVAC-R and service water heating system controls
ERIK LIEPINS
01/27/2026
Special inspection requirement — Maintenance information
ERIK LIEPINS
01/27/2026
Special inspection requirement — Final
ERIK LIEPINS
01/27/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
ERIK LIEPINS
01/27/2026
Special inspection requirement — Energy Code Compliance Inspections
ERIK LIEPINS
01/27/2026
Special inspection requirement — Mechanical Systems
ERIK LIEPINS
01/27/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
ERIK LIEPINS
01/27/2026
Special inspection requirement — Shutoff dampers
ERIK LIEPINS
01/27/2026
Special inspection requirement — Interior lighting power
ERIK LIEPINS
01/27/2026
Special inspection requirement — HVAC-R and service water heating equipment
ERIK LIEPINS
01/27/2026
Special inspection requirement — Exterior lighting power
ERIK LIEPINS
01/14/2026
Signed off — Alteration
CELL SITE INSPECTION VIA INDUSTRIAL ROPE ACCESS
M01250046-I1
01/08/2026
Filed — Alteration
SUBSEQUENT FILING FOR PLUMBING AND SPRINKLER WORKS
M01198715-P2
01/07/2026
Filed — Alteration
SUBSEQUENT FILING FOR PLUMBING AND SPRINKLER WORKS
M01198715-P3
01/05/2026
Special inspection requirement — Sprinkler Systems
EUGENE BIFULCO
01/05/2026
Special inspection requirement — HVAC-R and service water heating system controls
12/12/2025
Signed off — Alteration
MODIFICATION TO EXISTING FIRE SPRINKLER SYSTEM FOR THE INTERIOR RENOVATION OF AN EXISTING COMMERCIAL RETAIL SPACE (DUNKIN DONUTS).
M01175371-I1
12/05/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
12/01/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
10/20/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
10/14/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
07/23/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
07/22/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
07/03/2025
Permit issued — Suspended Scaffold
M01250046-I1-SC
07/01/2025
Filed — Alteration
CELL SITE INSPECTION VIA INDUSTRIAL ROPE ACCESS
M01250046-I1
Latest 60 of 262 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offAD LINE NYC INC08/17/2026
DOB NOWSprinklersPermit IssuedAVON PLBG & HTG INC08/07/2026
DOB NOWStructuralPermit IssuedBEAM ENTERPRISES INC07/29/2026
DOB NOWGeneral ConstructionPermit IssuedBEAM ENTERPRISES INC07/28/2026
DOB NOWPlumbingPermit IssuedEXPERT FIRE SPRINKLER,LLC03/17/2026
DOB NOWSuspended ScaffoldSigned-offKAY WATERPROOFING CORP.07/03/2025
DOB NOWPlumbingPermit IssuedSMART PLBG & HTG CORP05/20/2025
DOB NOWMechanical SystemsSigned-offAD LINE NYC INC04/25/2025
DOB NOWSignPermit IssuedDESTHERS, JOSEPH04/08/2025
DOB NOWSprinklersSigned-offFIVE BOROUGH NYC LLC02/19/2025
DOB NOWPlumbingPermit IssuedEXPERT FIRE SPRINKLER,LLC01/22/2025
DOB NOWPlumbingPermit IssuedHP SERVICES INC01/22/2025
DOB NOWMechanical SystemsPermit IssuedZAQ CONSTRUCTION INC01/22/2025
DOB NOWGeneral ConstructionPermit IssuedZAQ CONSTRUCTION INC01/15/2025
DOB NOWPlumbingSigned-offLG ELITE PLUMBING INC11/01/2024
DOB NOWMechanical SystemsPermit IssuedJFZ CONSTRUCTION, INC10/04/2024
DOB NOWGeneral ConstructionPermit IssuedJFZ CONSTRUCTION, INC10/04/2024
DOB NOWSprinklersPermit IssuedAVON PLBG & HTG INC03/23/2023
DOB NOWPlumbingPermit IssuedI DO PLUMBING & HTG INC10/14/2022
DOB NOWGeneral ConstructionPermit IssuedSITE ENTER INC09/09/2022
DOB NOWAntennaSigned-offAMP COMMUNICATIONS LLC04/28/2022
DOB NOWSidewalk ShedSigned-offANDAMIO SCAFFOLDING LLC09/29/2021
DOB NOWAntennaSigned-offPRIORE CONSTRUCTION SVCS08/10/2021
DOB NOWSidewalk ShedSigned-offEVEREST SCAFFOLDING INC03/11/2021
DOB NOWSupported ScaffoldSigned-offSKYLINE RESTORATION INC03/03/2021
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC03/03/2021
DOB NOWSupported ScaffoldSigned-offSPRING SCAFFOLDING LLC03/03/2021
DOB NOWSupported ScaffoldSigned-offSKYLINE RESTORATION INC10/30/2020
DOB NOWPlumbingSigned-offTAVELLA PLBG & HTG CORP10/28/2020
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC10/20/2020
DOB NOWSupported ScaffoldSigned-offSPRING SCAFFOLDING LLC10/20/2020
DOB NOWSidewalk ShedSigned-offEVEREST SCAFFOLDING INC03/11/2020
DOB NOWAntennaSigned-offOVERLAND CONTRACTING INC03/05/2020
BISPLISSUEDG. C. PLBG & HTG INC09/11/2025
BISOTISSUEDSKYLINE RESTORATION INC03/01/2021
BISOTISSUEDSKYLINE RESTORATION INC01/25/2021
BISMHISSUEDCAVALRY LLC01/02/2019
BISSPISSUEDACCURATE MECHANICAL INC10/24/2018
BISSPISSUEDACCURATE MECHANICAL INC09/25/2018
BISPLISSUEDSMART PLBG & HTG CORP08/10/2018
+ 43 more permits on file
3 projects · most recent 04/22/2026
Heating and Air Conditioning Systems Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
04/22/2026Signed-offAD LINE NYC INCHeating and Air Conditioning Systems
Heat / Cool
Sigma SDSH-D.1-060-2-F-1-SS-P-A-G-A-1-S-A-0-0-0-0-0 5 tons · Packaged Unit ×1
12/07/2024Permit IssuedZAQ CONSTRUCTION INCHeating and Air Conditioning Systems
Heat / Cool
Lg ARNU483M3A4 4 tons · Vrf Indoor ×1
ARUM048GSS5 4 tons · Vrf Outdoor ×1
01/23/2020——Air Conditioning Systems
Cooling
Mitsubishi Electric PKA-A36FA 34,200 BTU · Vrf Indoor ×1
2 projects · most recent 07/31/2026
FiledStatusContractorScope
07/31/2026Permit IssuedAVON PLBG & HTG INC56 heads
03/09/2023Permit IssuedAVON PLBG & HTG INC24 heads
2 projects · most recent 07/31/2026
Water/Sanitary Gas
FiledStatusContractorScope
07/31/2026Permit IssuedSMART PLBG & HTG CORPGas, Water/Sanitary
09/30/2024Signed-offLG ELITE PLUMBING INCWater/Sanitary
10 projects · most recent 01/22/2025
General Wiring
FiledStatusContractorScope
01/22/2025CompleteR & T ELECTRICAL CORPGeneral Wiring
11/22/2024CompleteR & T ELECTRICAL CORPGeneral Wiring
07/25/2023Permit IssuedROBERT CHIMENTI10 meters, 1 new_meters
06/14/2023CompleteTM SELECT ELECTRIC CORPGeneral Wiring
10/07/2022CompleteASKO ELEC CONST & MAIN INGeneral Wiring
10/08/2020CompleteTOP SHELF ELECTRIC CORP—
02/27/2020CompleteBOROWIDE ELECT'L CONTR'S—
06/03/2019CompleteDELTA POWER ELECTRICAL10 meters, 1 new_meters
05/14/2018CompletePOWER SURGE ELECTRIC, INCGeneral Wiring
03/28/2018CompleteNY ELECT MAINT & DATA CORGeneral Wiring
1 project · most recent 05/14/2026
Steel
FiledStatusContractorScope
05/14/2026Permit IssuedBEAM ENTERPRISES INCSteel
▾Field Inspections (DOB CAP) — 24
DateTypeResultReport
09/11/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
09/10/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
09/01/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
04/16/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
04/14/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
12/05/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
12/01/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/20/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
10/14/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/23/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/30/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
06/30/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/26/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/20/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
04/09/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/10/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/11/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/10/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
04/21/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/21/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/21/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/06/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/27/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
11/18/2022No Access-Final PL - Up to 3 Requested FloorsNo AccessView ↗
▾Special Inspection Requirements (DOB NOW) — 66
DateRequirementInspectorRole
08/06/2026Maintenance informationERIK LIEPINSenergy_progress
08/06/2026HVAC-R and service water heating equipmentERIK LIEPINSenergy_progress
08/06/2026Sprinkler SystemsEUGENE BIFULCOspecial
08/06/2026HVAC-R and service water heating system controlsERIK LIEPINSenergy_progress
04/21/2026HVAC-R and service water heating system controls—energy_progress
04/21/2026Maintenance information—energy_progress
04/21/2026Sprinkler SystemsEUGENE BIFULCOspecial
04/21/2026HVAC-R and service water heating equipment—energy_progress
04/09/2026Structural Steel - High Strength BoltingGary Steficekspecial
04/09/2026Sprayed fire-resistant materialsGary Steficekspecial
04/09/2026Structural Steel - DetailsGary Steficekspecial
04/09/2026FinalGary Steficekprogress
04/09/2026Structural Steel - WeldingGary Steficekspecial
04/08/2026FinalAnthony Nicholasprogress
01/27/2026Fenestration air leakageERIK LIEPINSenergy_progress
01/27/2026Shutoff dampersERIK LIEPINSenergy_progress
01/27/2026HVAC-R and service water piping design and insulationERIK LIEPINSenergy_progress
01/27/2026Fenestration areasERIK LIEPINSenergy_progress
01/27/2026HVAC-R and service water heating equipmentERIK LIEPINSenergy_progress
01/27/2026Duct leakage testing, insulation and designERIK LIEPINSenergy_progress
01/27/2026Fire-Resistant Penetrations and JointsERIK LIEPINSspecial
01/27/2026Mechanical SystemsERIK LIEPINSspecial
01/27/2026Energy Code Compliance InspectionsERIK LIEPINSprogress
01/27/2026FinalERIK LIEPINSprogress
01/27/2026Maintenance informationERIK LIEPINSenergy_progress
Latest 25 of 66.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Broad Nosh BagelsRestaurant / Food ServiceCellar, Floor 1
Project M01389904 Alteration · LOC Issued · 04/22/2026
Project M01198715 Alteration · Permit Entire · 04/16/2025
Dunkin'Restaurant / Food Service—
Project M01087293 Alteration · Permit Entire · 07/31/2024
Jonathan Okon, DMDMedical / HealthcareFloor 18
Project M00839458 Alteration · Permit Entire · 03/09/2023
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 770 on file (BIS + DOB NOW)
▸Plans & Drawings39
▸DOB NOWPlans/Sketch29
09/03/2026M00565787-I1Request digital key ↗
09/02/2026M00683349-P1Request digital key ↗
09/02/2026M00683349-I1Request digital key ↗
Showing 3 of 29 on file for this type
▸DOB NOWPlans/Sketch - Supported Scaffold3
09/04/2026M00410747-I1Request digital key ↗
09/03/2026M00419039-P1Request digital key ↗
09/03/2026M00419039-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing2
09/03/2026M00359113-I1Request digital key ↗
08/15/2026M00359113-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Antenna2
09/05/2026M00259981-P1Request digital key ↗
08/15/2026M00259981-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed2
09/05/2026M00323064-I1Request digital key ↗
09/04/2026M00410734-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems1
09/05/2026M00239895-I1Request digital key ↗
▸Applications & Permits137
▸BISPLAN / WORK APPROVAL APPLICATION74
03/20/2025104758647Open ↗
03/10/2025104758647Open ↗
03/07/2025104618335Open ↗
Showing 3 of 74 on file for this type
▸BISWORK PERMIT APPLICATION60
09/11/2025104618335Open ↗
01/25/2021140948278Open ↗
05/28/2019123665131Open ↗
Showing 3 of 60 on file for this type
▸BISSCAFFOLD APPLICATION & PERMIT1
01/25/2021140948278Open ↗
▸BISPARTIAL DEMO PLAN & DS1 (FOR AL/EW-OT PERMITS)1
01/25/2021140948278Open ↗
▸BISSIDEWALK SHED APPLICATION & PERMIT1
12/28/2020140948278Open ↗
▸Seals & Professional Certifications191
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION58
02/03/2020123665131Open ↗
11/20/2019123432133Open ↗
10/25/2019123319729Open ↗
Showing 3 of 58 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature38
09/05/2026M00259981-I1Open ↗
09/05/2026M00323064-I1Open ↗
09/04/2026M00410747-I1Open ↗
Showing 3 of 38 on file for this type
▸DOB NOWProgress Inspector Seal & Signature19
09/01/2026M00410747-I1Open ↗
09/01/2026M01198715-P4Open ↗
09/01/2026M01198715-P4Open ↗
Showing 3 of 19 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature18
09/01/2026M01198715-P4Open ↗
09/01/2026M00763522-I1Open ↗
09/01/2026M01189943-I1Open ↗
Showing 3 of 18 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT14
03/26/2019123665131Open ↗
10/01/2018123319729Open ↗
01/24/2018140733801Open ↗
Showing 3 of 14 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION12
01/24/2018140733801Open ↗
07/16/2017140668506Open ↗
Showing 2 of 12 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY12
01/24/2018140733801Open ↗
07/16/2017140668506Open ↗
Showing 2 of 12 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST8
03/26/2019123665131Open ↗
10/01/2018123319729Open ↗
11/08/2017140642044Open ↗
Showing 3 of 8 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
09/22/2020140948278Open ↗
▸Trade Schedules & Equipment43
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE16
09/13/2019123319729Open ↗
09/12/2019123319729Open ↗
04/10/2019123319729Open ↗
Showing 3 of 16 on file for this type
▸BISSCHEDULE B - PLUMBING10
01/24/2018140733801Open ↗
Showing 1 of 10 on file for this type
▸BISSELF-CERT PLUMBING NOTICE10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISEQUIPMENT USE PERMITS2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA2
07/17/2020121442956Open ↗
Showing 1 of 2 on file for this type
▸BISSPRINKLER INSP REPORT : FP-851
03/26/2019123665131Open ↗
▸Safety & Tenant Protection1
▸BISTenant Protection Plan and Notes1
04/30/2018123432133Open ↗
▸Environmental & Asbestos104
▸DOB NOWDEP ACP-5: Asbestos Assessment Report31
09/03/2026M00565787-I1Open ↗
08/31/2026M00766586-I1Open ↗
08/31/2026M00766586-P1Open ↗
Showing 3 of 31 on file for this type
▸DOB NOWOER: Notice to Proceed24
09/04/2026M00410747-I1Open ↗
09/03/2026M00419039-I1Open ↗
09/03/2026M00565787-I1Open ↗
Showing 3 of 24 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)22
03/26/2019123665131Open ↗
12/10/2018123589679Open ↗
10/02/2018123319729Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWOER: Notice of Satisfaction14
09/04/2026M00410747-I1Open ↗
09/03/2026M00565787-I1Open ↗
08/17/2026M01198715-P6Open ↗
Showing 3 of 14 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE OF SATISFACTION2
11/03/2021140948278Open ↗
11/03/2021140948278Open ↗
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED2
09/22/2020140948278Open ↗
01/24/2018140733801Open ↗
▸BISASBESTOS: VARIANCE (DEP FORM V5)1
01/25/2021140948278Open ↗
▸Energy Compliance40
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS11
11/03/2021140948278Open ↗
09/27/2019121450777Open ↗
12/29/2017122167975Open ↗
Showing 3 of 11 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY5
02/27/2025104618335Open ↗
02/14/2025104758647Open ↗
09/22/2020140948278Open ↗
Showing 3 of 5 on file for this type
▸BISTR8: Energy Code Progress Inspections4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
01/24/2018140733801Open ↗
Showing 1 of 2 on file for this type
▸BISTECHNICAL REPORT: ENERGY2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
11/05/2021140948278Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026M00763522-I1Open ↗
▸Inspections & Test Reports29
▸BISTECHNICAL REPORT: RESPONSIBILITY25
03/06/2025104618335Open ↗
02/27/2025104618335Open ↗
02/25/2025104618335Open ↗
Showing 3 of 25 on file for this type
▸BISSTRUCTURAL STEEL - HIGH STRENGTH BOLTING1
11/05/2021140948278Open ↗
▸BISSTRUCTURAL STABILITY - EXISTING BUILDINGS1
11/05/2021140948278Open ↗
▸BISSTRUCTURAL STEEL - WELDING1
11/05/2021140948278Open ↗
▸BISHYDRAULIC FLOW CALCULATIONS1
10/02/2018123319729Open ↗
▸Approvals, Objections & Sign-offs53
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST24
11/05/2021140948278Open ↗
11/05/2021140948278Open ↗
11/05/2021140948278Open ↗
Showing 3 of 24 on file for this type
▸BISADMINISTRATIVE OBJECTIONS13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISSUPERSEDING LETTER4
09/11/2025104618335Open ↗
01/03/2019121450777Open ↗
06/15/2017121450777Open ↗
Showing 3 of 4 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE3
03/07/2025104758647Open ↗
03/05/2025104758647Open ↗
03/05/2025104758647Open ↗
▸BISFINAL1
11/05/2021140948278Open ↗
▸BISAPPLICANT SHALL PROVIDE 1 ACP-12 FORM_PRIOR TO SIGN OFF: TRU1989MN201
11/05/2021140948278Open ↗
▸Cost, Insurance & Ownership49
▸BISCOST AFFIDAVIT48
11/03/2021140948278Open ↗
09/22/2020140948278Open ↗
02/03/2020123665131Open ↗
Showing 3 of 48 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
11/05/2021140948278Open ↗
▸Filing & Intake Forms76
▸BISEFILING COVER SHEET24
03/26/2019123665131Open ↗
12/10/2018123589679Open ↗
10/01/2018123319729Open ↗
Showing 3 of 24 on file for this type
▸BISBOROUGH INTAKE FORM22
09/11/2025104618335Open ↗
02/03/2020123665131Open ↗
11/20/2019123432133Open ↗
Showing 3 of 22 on file for this type
▸BISADDITIONAL INFORMATION15
03/20/2025104758647Open ↗
09/13/2019123319729Open ↗
07/16/2019140733801Open ↗
Showing 3 of 15 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET14
09/22/2020140948278Open ↗
01/24/2018140733801Open ↗
07/16/2017140668506Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWAI1 Form (from plan PDF)1
08/16/2026M00419039-P1Open ↗
▸Other Documents8
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION7
07/06/2018123432133Open ↗
Showing 1 of 7 on file for this type
▸DOB NOWIRA Certification1
08/13/2026M01250046-I1Open ↗