| Owner | Filings | Most Recent |
|---|---|---|
| 431 Broad West | 17 | 03/22/2026 |
| Morton Barrow Condo | 6 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Bluarch | 4 | 09/28/2026 |
| Twig Consulting Engineers | 4 | 12/13/2023 |
| Ogawa Depardon | 4 | 01/13/2023 |
| Navi Structural Engineering | 1 | 08/29/2022 |
| Cycle Architecture | 3 | 07/18/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| Bluarch | 8 | 03/21/2026 |
| RPO | 8 | 03/21/2026 |
| Eurocelt Expediting | 2 | 03/21/2026 |
| Kna Consulting | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| K & B HVAC | specialty_contractor | 3 | 03/21/2026 |
| Acara Construction | General Contractor | 2 | 07/08/2026 |
| Sage Construction Service | General Contractor | 2 | 04/09/2026 |
| Accurate Mechanical | Fire Protection | 2 | 07/08/2026 |
| Loduca Associates | General Contractor | 2 | 07/08/2026 |
| Caputek Electrical Services | Electrical | 2 | 03/21/2026 |
| Universal Systems | Scaffold | 1 | 07/08/2026 |
| Wawel Plumbing and Heating | Plumbing | 1 | 07/08/2026 |
| Dynamic Electric Service | Electrical | 1 | 03/21/2026 |
| Vilanova Electrical Co | Electrical | 1 | 03/22/2026 |
| Perfectaire Co | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| New York Special Inspecti | 6286 | 7 | 09/28/2026 |
| Century Testing & Consulting | 4081 | 3 | 12/13/2023 |
| Ase Engineering | 5785 | 4 | 01/13/2023 |
| Twig Special Inspections | 885 | 1 | 12/16/2022 |
| Twin Peaks | 317 | 3 | 07/18/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Signed-off | Accurate Mechanical | 10/23/2025 |
| DOB NOW | General Construction | Permit Issued | Sage Construction Service | 08/14/2024 |
| DOB NOW | Sprinklers | Signed-off | Accurate Mechanical | 05/12/2023 |
| DOB NOW | Mechanical Systems | Signed-off | K & B HVAC | 04/19/2023 |
| DOB NOW | Plumbing | Signed-off | Wawel Plumbing and Heating | 04/14/2023 |
| DOB NOW | General Construction | Permit Issued | Sage Construction Service | 03/23/2023 |
| DOB NOW | General Construction | Signed-off | Acara Construction | 02/17/2023 |
| DOB NOW | General Construction | Signed-off | Acara Construction | 02/02/2023 |
| DOB NOW | Mechanical Systems | Signed-off | Perfectaire Co | 01/25/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | Universal Systems | 08/29/2022 |
| DOB NOW | Structural | Signed-off | Loduca Associates | 01/20/2022 |
| DOB NOW | Structural | Signed-off | Loduca Associates | 11/10/2021 |
| BIS | PL | ISSUED | Calray Gas Heat | 10/26/2018 |
| BIS | BL | ISSUED | Calray Gas Heat | 10/26/2018 |
| BIS | — | ISSUED | Signs Cad | 12/08/2011 |
| BIS | — | ISSUED | Pwi Construction | 07/14/2010 |
| BIS | — | ISSUED | Pwi Construction | 07/06/2010 |
| BIS | EQ | ISSUED | Perimeter Bridge & Scaffo | 06/21/2010 |
| BIS | PL | ISSUED | Tristate Plumbing Services | 06/08/2010 |
| BIS | PL | ISSUED | Code Mechanical | 05/21/2010 |
| BIS | — | ISSUED | Pwi Construction | 05/13/2010 |
| BIS | PL | ISSUED | Jumper P&H Gen Contracting | 10/30/2000 |
| BIS | BL | ISSUED | Jumper P&H Gen Contracting | 10/30/2000 |
| BIS | EQ | ISSUED | Ace Scaffold Co | 10/05/2000 |
| BIS | PL | ISSUED | New York Standard Mechanical | 07/10/1991 |
| BIS | OT | ISSUED | Eurostruct | 04/25/1991 |
| BIS | OT | ISSUED | Eurostruct | 04/25/1991 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/10/2025 | Complete | Eastern Electrical Construction | General Wiring |
| 08/26/2022 | Complete | Top Shelf Electric | — |
| 05/03/2018 | Complete | Vilanova Electrical Co | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/08/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/27/2026 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 11/13/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/07/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 11/03/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/11/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/22/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/01/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/28/2026 | Energy Code Compliance Inspections | ANTONIO DI ORONZO | progress |
| 09/28/2026 | Fire-Resistant Penetrations and Joints | ANTONIO DI ORONZO | special |
| 09/28/2026 | Tenant Protection Plan Compliance | — | special |
| 09/28/2026 | Fire-Resistance Rated Construction | ANTONIO DI ORONZO | progress |
| 09/28/2026 | Air barrier - visual inspection | ANTONIO DI ORONZO | energy_progress |
| 03/20/2026 | Fire-Resistant Penetrations and Joints | ANTONIO DI ORONZO | special |
| 03/20/2026 | Air barrier - visual inspection | ANTONIO DI ORONZO | energy_progress |
| 03/20/2026 | Fire-Resistance Rated Construction | ANTONIO DI ORONZO | progress |
| 03/20/2026 | Energy Code Compliance Inspections | ANTONIO DI ORONZO | progress |
| 03/20/2026 | Tenant Protection Plan Compliance | ANTONIO DI ORONZO | special |
| 03/02/2026 | Energy Code Compliance Inspections | ANTONIO DI ORONZO | progress |
| 03/02/2026 | Air barrier - visual inspection | ANTONIO DI ORONZO | energy_progress |
| 03/02/2026 | Fire-Resistant Penetrations and Joints | ANTONIO DI ORONZO | special |
| 03/02/2026 | Tenant Protection Plan Compliance | — | special |
| 03/02/2026 | Fire-Resistance Rated Construction | ANTONIO DI ORONZO | progress |
| 12/14/2023 | Post-installed Anchors | FRANZ SEBORGA | special |
| 12/14/2023 | Energy Code Compliance Inspections | ANTONIO DI ORONZO | progress |
| 12/14/2023 | Fire-Resistant Penetrations and Joints | ANTONIO DI ORONZO | special |
| 12/14/2023 | Tenant Protection Plan Compliance | ANTONIO DI ORONZO | special |
| 11/21/2023 | Tenant Protection Plan Compliance | — | special |
| 11/17/2023 | Energy Code Compliance Inspections | ANTONIO DI ORONZO | progress |
| 11/17/2023 | Fire-Resistant Penetrations and Joints | ANTONIO DI ORONZO | special |
| 11/17/2023 | Post-installed Anchors | ALDO BRAVO | special |
| 01/13/2023 | HVAC-R and service water piping design and insulation | alon egozi | energy_progress |
| 01/13/2023 | Duct leakage testing, insulation and design | alon egozi | energy_progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Scavolini USA | Retail | Floor 1 | Project M08049585 Project M08019138 |