| Owner | Filings | Most Recent |
|---|---|---|
| TCM | 18 | 07/08/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/14/2018 | $5.1M | — | — → — | $600/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ALL CITY ENGINEERING PC | 5 | 04/11/2023 |
| MW PROFESSIONAL ENGINEERING, P.C. | 1 | 01/29/2021 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TCM CORPORATION | General Contractor | 4 | 07/08/2026 |
| KJK ELECTRIC INC | Electrical | 2 | 03/22/2026 |
| BEST PLUMBING & HVAC INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ALL CITY ENGINEERING PC | 7115 | 5 | 04/11/2023 |
| MW PROFESSIONAL ENGINEERI | 570 | 1 | 01/29/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | BEST PLUMBING & HVAC INC | 06/14/2021 |
| DOB NOW | Mechanical Systems | Signed-off | TCM CORPORATION | 02/19/2021 |
| DOB NOW | General Construction | Signed-off | TCM CORPORATION | 02/08/2021 |
| BIS | FS | ISSUED | MANHATTAN & QUEENS FUEL CORP | 12/26/1989 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/09/2022 | Complete | KJK ELECTRIC INC | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/11/2023 | Fire-Resistant Penetrations and Joints | ZHAO DENG | special |
| 04/11/2023 | Mechanical Systems | ZHAO DENG | special |
| 04/11/2023 | Energy Code Compliance Inspections | ZHAO DENG | progress |
| 04/11/2023 | Fire-Resistance Rated Construction | ZHAO DENG | progress |
| 04/11/2023 | Final | ZHAO DENG | progress |
| 04/11/2023 | Maintenance information | ZHAO DENG | energy_progress |
| 04/11/2023 | HVAC-R and service water piping design and insulation | ZHAO DENG | energy_progress |
| 04/11/2023 | HVAC-R and service water heating system controls | ZHAO DENG | energy_progress |
| 04/11/2023 | HVAC-R and service water heating equipment | ZHAO DENG | energy_progress |
| 02/28/2023 | Fire-Resistant Penetrations and Joints | ZHAO DENG | special |
| 02/28/2023 | Mechanical Systems | ZHAO DENG | special |
| 02/28/2023 | Energy Code Compliance Inspections | ZHAO DENG | progress |
| 02/28/2023 | Final | ZHAO DENG | progress |
| 02/28/2023 | Fire-Resistance Rated Construction | ZHAO DENG | progress |
| 02/28/2023 | HVAC-R and service water piping design and insulation | ZHAO DENG | energy_progress |
| 02/28/2023 | Maintenance information | ZHAO DENG | energy_progress |
| 02/28/2023 | HVAC-R and service water heating system controls | ZHAO DENG | energy_progress |
| 02/28/2023 | HVAC-R and service water heating equipment | ZHAO DENG | energy_progress |
| 12/28/2021 | Fire-Resistant Penetrations and Joints | ZHAO DENG | special |
| 12/28/2021 | Energy Code Compliance Inspections | ZHAO DENG | progress |
| 12/28/2021 | HVAC-R and service water heating equipment | ZHAO DENG | energy_progress |
| 12/28/2021 | HVAC-R and service water piping design and insulation | ZHAO DENG | energy_progress |
| 12/28/2021 | HVAC-R and service water heating system controls | ZHAO DENG | energy_progress |
| 12/28/2021 | Maintenance information | ZHAO DENG | energy_progress |