| Owner | Filings | Most Recent |
|---|---|---|
| 43-12 214 Place Realty | 2 | 03/21/2026 |
| 214 Place | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/07/2022 | $1.3M | — | BASSLEV REALTY LLC → Private party | $529/sf building |
| 08/15/2019 | $900K | — | Private party → BASSLEV REALTY LLC | $375/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| TL Engineering | 9 | 07/02/2026 |
| Chon Engineering | 1 | 04/18/2024 |
| Infocus Design and Planning | 6 | 04/07/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| XH&RC Plumbing and Heating | 12 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Dong San Construction | General Contractor | 2 | 03/21/2026 |
| C Plus Design Group | General Contractor | 1 | 08/26/2026 |
| Avon Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| I Do Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TL Engineering | 1222 | 9 | 07/02/2026 |
| Infocus Design & Planning | 932 | 3 | 01/20/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | C Plus Design Group | 08/25/2026 |
| DOB NOW | Plumbing | Signed-off | I Do Plumbing & Heating | 04/24/2024 |
| DOB NOW | Plumbing | Signed-off | Avon Plumbing & Heating | 07/20/2022 |
| DOB NOW | General Construction | Signed-off | Dong San Construction | 07/18/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/19/2020 | — | — | Air Conditioning Systems, Heating Systems | Cooling Mitsubishi Electric MXZ-3C30NA2 28,400 BTU · Heat Pump Outdoor ×3 MXZ-4C36NAHZ 36,000 BTU · Heat Pump Outdoor ×1 Heating Mitsubishi Electric MXZ-3C30NA2 28,600 BTU · Heat Pump Outdoor ×3 MXZ-4C36NAHZ 45,000 BTU · Heat Pump Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/07/2021 | — | — | 216 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/18/2024 | Signed-off | I Do Plumbing & Heating | Gas |
| 04/07/2021 | — | — | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/22/2022 | Complete | Asko Electric Construction & Maintenance | 1 meters |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/07/2021 | — | — | Steel, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/07/2021 | — | — | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/23/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/15/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 05/13/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/13/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/27/2022 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 08/17/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/12/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/05/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/19/2026 | Structural Stability – Alterations of existing buildings | Simon Lee | special |
| 08/19/2026 | Protection of exposed foundation insulation | Simon Lee | energy_progress |
| 08/19/2026 | Air barrier — testing | Simon Lee | energy_progress |
| 08/19/2026 | Air barrier - visual inspection | Simon Lee | energy_progress |
| 08/19/2026 | Fenestration areas | Simon Lee | energy_progress |
| 08/19/2026 | Interior lighting power | Simon Lee | energy_progress |
| 08/19/2026 | Insulation placement and R values | Simon Lee | energy_progress |
| 08/19/2026 | Maintenance information | Simon Lee | energy_progress |
| 08/19/2026 | Fenestration and door U-factor and product ratings | Simon Lee | energy_progress |
| 08/19/2026 | Permanent certificate | Simon Lee | energy_progress |
| 08/19/2026 | Metering | Simon Lee | energy_progress |
| 08/19/2026 | Fenestration air leakage | Simon Lee | energy_progress |
| 08/19/2026 | Energy Code Compliance Inspections | Simon Lee | progress |
| 08/19/2026 | Fire-Resistance Rated Construction | Simon Lee | progress |
| 08/19/2026 | Concrete - Cast-In-Place | Simon Lee | special |
| 08/19/2026 | Fire-Resistant Penetrations and Joints | Simon Lee | special |
| 07/01/2026 | Permanent certificate | Simon Lee | energy_progress |
| 07/01/2026 | Concrete - Cast-In-Place | Simon Lee | special |
| 07/01/2026 | Fire-Resistant Penetrations and Joints | Simon Lee | special |
| 07/01/2026 | Structural Stability – Alterations of existing buildings | Simon Lee | special |
| 07/01/2026 | Energy Code Compliance Inspections | Simon Lee | progress |
| 07/01/2026 | Fire-Resistance Rated Construction | Simon Lee | progress |
| 07/01/2026 | Air barrier — testing | Simon Lee | energy_progress |
| 07/01/2026 | Interior lighting power | Simon Lee | energy_progress |
| 07/01/2026 | Fenestration areas | Simon Lee | energy_progress |