| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/17/2026 | Signed-off | D.H.E. COMPANY, INC | Heating and Air Conditioning Systems | Heat / Cool M3 Air Products VCU-T-024-1-X 24,100 BTU · Condensing Unit ×5 VCU-T-030-1-X 28,400 BTU · Condensing Unit ×5 |
| 03/16/2026 | Permit Issued | ORCHESTER MANAGEMENT COM* | Air Conditioning Systems | Cooling Trane ×1 |
| 08/22/2025 | Signed-off | REGELE BUILDERS, INC | Heating and Air Conditioning Systems | Heat / Cool Above Air VCU-C-024-1-X 2 tons · Condensing Unit ×2 First Company 24HXX-C R410 TXV 2 tons · Ahu ×4 Task TGC021TWEC-25K 2 tons · Condensing Unit ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/17/2026 | Permit Issued | DONATO PLUMBING, INC | Gas, Water/Sanitary |
| 03/16/2026 | Permit Issued | JOHN FITZGERALD PLBG &HTG | Water/Sanitary |
| 02/27/2025 | Permit Issued | SYSTEMS 2000 PLBG SVCS LL | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/03/2026 | Permit Issued | NASH ELECTRIC SERVICES IN | — |
| 06/25/2025 | Complete | CL ELECTRICAL CORP | — |
| 06/24/2025 | Complete | UNITED ELEC'L CONT'G CORP | General Wiring |
| 06/02/2025 | Complete | ROMCON ELECTRIC, INC | General Wiring |
| 03/21/2025 | Permit Issued | NASH ELECTRIC SERVICES IN | — |
| 12/09/2024 | Complete | DN ELECTRIC INC | General Wiring |
| 10/25/2023 | Complete | ELECTRICAL CHARGES CORP | General Wiring |
| 07/28/2023 | Complete | UNITED ELEC'L CONT'G CORP | General Wiring |
| 12/21/2022 | Complete | ELECTRICAL CHARGES CORP | — |
| 10/22/2021 | Complete | MEGA ELEC'L CONTR'G, INC | — |
| 04/08/2019 | Permit Issued | MEGA ELEC'L CONTR'G, INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/26/2024 | Permit Issued | WEST NEW YORK RESTORATION | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/07/2025 | Permit Issued | TOWER SERVICES INC | Suspended Scaffold (SC) |
| Owner | Filings | Most Recent |
|---|---|---|
| HIGHLINE SERVICE MAINTENANCE | 4 | 07/08/2026 |
| FIRSTSERVICE RESIDENTIAL | 6 | 04/09/2026 |
| 43 TENANTS | 139 | 03/22/2026 |
| PANTS VIEW LLC | 1 | 03/22/2026 |
| 43 FIFTH AVENUE | 5 | 03/22/2026 |
| COOPER SQUARE REALTY | 2 | 03/21/2026 |
| 43 TENANTC CORP.C/O COOPER SQUAR | 3 | 03/21/2026 |
| PHOENIX | 2 | 03/21/2026 |
| FIRST SERVICE RESIDENCIAL | 1 | 03/21/2026 |
| FIRST SERVICE RESIDENTIAL | 6 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| D'ANTONIO CONSULTING ENGINEERS | 9 | 09/17/2026 |
| RIMKUS NEW YORK PLLC | 2 | 07/07/2026 |
| ERIC SHEFFIELD ARCHITECT | 5 | 06/08/2026 |
| ELIZABETH ROBERTS ARCHITECTURE & DE | 4 | 06/03/2026 |
| WELLS ENGINEERING, PLLC | 4 | 03/16/2026 |
| SPIVAK ARCHITECTS P.C. | 2 | 03/16/2026 |
| P.A. COLLINS PE | 2 | 08/22/2025 |
| KN3 ENGINEERING LLC | 1 | 05/07/2025 |
| KZ ENGINEERING, P.C | 2 | 04/23/2025 |
| ENGINEERING SOLUTIONS | 2 | 02/27/2025 |
| JOSEPH K. BLUM CO. LLP | 1 | 12/05/2024 |
| ROBERT SILMAN ASSOCIATES | 1 | 07/26/2024 |
| CONTEXTUS ARCHITECTURE AND DESIGN | 1 | 07/02/2024 |
| 2LS CONSULTING ENGINEERING, DPC | 4 | 05/17/2023 |
| PAUL PERDEK, PROF. ENG. PLLC | 1 | 11/01/2021 |
| DOOLING & COMPANY ARCHITECTS | 2 | 04/29/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| AE DESIGN SOLUTION | 8 | 03/21/2026 |
| D D EXPEDITORS | 6 | 03/21/2026 |
| GREEN LIGHT EXPEDITING LLC | 6 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 12 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 2 | 03/21/2026 |
| JM ZONING, LLC. | 12 | 03/21/2026 |
| RIZZO GROUP | 4 | 03/21/2026 |
| ANZALONE ARCHITECTURE | 4 | 03/21/2026 |
| RIMKUS NEW YORK PLLC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| EMPIRE NY INSTALLATIONS INC | General Contractor | 7 | 07/08/2026 |
| UNIFIED AIR INDUSTRIES CO | General Contractor | 6 | 03/21/2026 |
| WEST NEW YORK RESTORATION OF CT | General Contractor | 5 | 09/16/2026 |
| REGELE BUILDERS, INC | General Contractor | 4 | 08/08/2026 |
| D.H.E. COMPANY, INC | General Contractor | 4 | 07/08/2026 |
| MICHAEL BAPTISTE | Electrical | 3 | 03/21/2026 |
| BEDNARZ CONSTRUCTION LLC | General Contractor | 3 | 03/21/2026 |
| JEFF SKOWRONSKI | Electrical | 2 | 03/21/2026 |
| ORCHESTER MANAGEMENT COM* | General Contractor | 2 | 07/08/2026 |
| DONATO PLUMBING, INC | Plumbing | 2 | 07/03/2026 |
| NEW WAVE DESIGN & CONTRACTING | General Contractor | 2 | 07/08/2026 |
| MACREDDIN PLBG & HTG INC | Plumbing | 2 | 07/08/2026 |
| SAL-TECH PLBG & HTG, INC | Plumbing | 2 | 07/08/2026 |
| SKOWRONSKI JEFF | Electrical | 2 | 03/21/2026 |
| SYSTEMS 2000 PLBG SVCS LL | Plumbing | 1 | 06/28/2026 |
| DN ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| HOLNESS, GEORGE | Electrical | 1 | 03/21/2026 |
| MEGA ELEC'L CONTR'G, INC | Electrical | 1 | 03/22/2026 |
| ROBERT LOGOZIO | Electrical | 1 | 03/21/2026 |
| TRANSCANADA | Electrical | 1 | 03/21/2026 |
| UNITED ELEC'L CONT'G CORP | Electrical | 1 | 03/22/2026 |
| WINSER, KEVIN | Electrical | 1 | 03/21/2026 |
| SYSTEMS 2000 PLUMBING SER | General Contractor | 1 | 07/08/2026 |
| JOHN FITZGERALD PLBG &HTG | Plumbing | 1 | 06/28/2026 |
| BECKWITH, BRUCE | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| D'ANTONIO CONSULTING ENGI | 931 | 6 | 09/17/2026 |
| RIMKUS NEW YORK, PLLC | 8123 | 2 | 07/07/2026 |
| P.A.COLLINS INSPECTIONS P | 2168 | 5 | 06/08/2026 |
| WELLS DESIGN & CONSULTING | 7750 | 6 | 03/16/2026 |
| ALAN MARGOLIN & ASSOC | 423 | 2 | 11/14/2025 |
| ERIC SHEFFIELD ARCHITECT | 2195 | 2 | 06/23/2025 |
| LEO Y LEE ASSOCIATES | 2481 | 1 | 05/07/2025 |
| ENGINEERING SOLUTIONS, PL | 6492 | 1 | 12/05/2024 |
| JOSEPH K. BLUM CO. LLP | 1741 | 1 | 12/05/2024 |
| URBAN INTEGRATIONS LLC | 7993 | 2 | 07/26/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | WEST NEW YORK RESTORATION OF CT | 09/15/2026 |
| DOB NOW | Mechanical Systems | Signed-off | REGELE BUILDERS, INC | 08/07/2026 |
| DOB NOW | General Construction | Signed-off | REGELE BUILDERS, INC | 06/11/2026 |
| DOB NOW | Plumbing | Signed-off | MACREDDIN PLBG & HTG INC | 06/11/2026 |
| DOB NOW | Plumbing | Permit Issued | DONATO PLUMBING, INC | 11/12/2025 |
| DOB NOW | Mechanical Systems | Signed-off | REGELE BUILDERS, INC | 08/06/2025 |
| DOB NOW | Mechanical Systems | Signed-off | D.H.E. COMPANY, INC | 08/01/2025 |
| DOB NOW | General Construction | Signed-off | D.H.E. COMPANY, INC | 08/01/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | DEMARI SERVICES INC | 06/25/2025 |
| DOB NOW | Plumbing | Permit Issued | JOHN FITZGERALD PLBG &HTG | 06/24/2025 |
| DOB NOW | General Construction | Permit Issued | ORCHESTER MANAGEMENT COM* | 06/20/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | ORCHESTER MANAGEMENT COM* | 06/20/2025 |
| DOB NOW | Plumbing | Signed-off | MACREDDIN PLBG & HTG INC | 06/12/2025 |
| DOB NOW | General Construction | Signed-off | REGELE BUILDERS, INC | 06/09/2025 |
| DOB NOW | Plumbing | Permit Issued | SYSTEMS 2000 PLBG SVCS LL | 05/08/2025 |
| DOB NOW | General Construction | Permit Issued | SYSTEMS 2000 PLUMBING SER | 04/10/2025 |
| DOB NOW | General Construction | Permit Issued | A. PETER LUGER CONST INC | 02/27/2025 |
| DOB NOW | Structural | Permit Issued | A. PETER LUGER CONST INC | 02/27/2025 |
| DOB NOW | Construction Fence | Signed-off | A. PETER LUGER CONST INC | 02/06/2025 |
| DOB NOW | Plumbing | Permit Issued | DONATO PLUMBING, INC | 08/28/2024 |
| DOB NOW | General Construction | Signed-off | D.H.E. COMPANY, INC | 08/02/2024 |
| DOB NOW | Mechanical Systems | Signed-off | D.H.E. COMPANY, INC | 08/02/2024 |
| DOB NOW | Mechanical Systems | Signed-off | NEW WAVE DESIGN & CONTRAC | 05/31/2024 |
| DOB NOW | General Construction | Signed-off | NEW WAVE DESIGN & CONTRAC | 03/26/2024 |
| DOB NOW | General Construction | Signed-off | BEDNARZ CONSTRUCTION LLC | 03/06/2024 |
| DOB NOW | Plumbing | Signed-off | SAL-TECH PLBG & HTG, INC | 09/20/2022 |
| DOB NOW | Mechanical Systems | Permit Issued | UNIFIED AIR INDUSTRIES CO | 06/29/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | EMPIRE NY INSTALLATIONS I | 11/01/2021 |
| DOB NOW | Mechanical Systems | Permit Issued | UNIFIED AIR INDUSTRIES CO | 09/29/2021 |
| DOB NOW | Plumbing | Signed-off | SAL-TECH PLBG & HTG, INC | 09/15/2021 |
| DOB NOW | Supported Scaffold | Signed-off | EMPIRE NY INSTALLATIONS I | 04/30/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | EMPIRE NY INSTALLATIONS I | 04/30/2019 |
| BIS | PL | ISSUED | GLENNS PLUMBING SVCS INC | 07/03/2025 |
| BIS | OT | ISSUED | U.M. CONSTRUCTION CORP | 07/13/2023 |
| BIS | OT | ISSUED | U.M. CONSTRUCTION CORP | 06/24/2022 |
| BIS | OT | ISSUED | U.M. CONSTRUCTION CORP | 02/25/2022 |
| BIS | OT | ISSUED | U.M. CONSTRUCTION CORP | 08/03/2021 |
| BIS | OT | ISSUED | MILLENIUM RESTORATION CORP | 01/06/2021 |
| BIS | OT | ISSUED | MILLENIUM RESTORATION CORP | 01/24/2020 |
| BIS | EQ | ISSUED | EMPIRE NY INSTALLATIONS INC | 05/03/2019 |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/07/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/13/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/22/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/06/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/16/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/10/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/14/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/10/2025 | Pass-Final PL - More than 10 Requested Floors | Pass | View ↗ |
| 10/01/2025 | Pass-Final PL - More than 10 Requested Floors | Pass | View ↗ |
| 09/26/2025 | Pass-Final PL - More than 10 Requested Floors | Pass | View ↗ |
| 09/11/2025 | Pass-Final PL - More than 10 Requested Floors | Pass | View ↗ |
| 08/29/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/29/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/29/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/26/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/23/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 07/18/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/02/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 02/07/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/05/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/15/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/16/2026 | Post-installed Anchors | GAETANO D'ANTONIO | special |
| 09/16/2026 | Fire-Resistant Penetrations and Joints | GAETANO D'ANTONIO | special |
| 07/17/2026 | Fire-Resistant Penetrations and Joints | Paul Collins | special |
| 07/16/2026 | Fire-Resistance Rated Construction | — | progress |
| 07/16/2026 | Final | Elizabeth Roberts | progress |
| 07/16/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 07/13/2026 | Fire-Resistance Rated Construction | — | progress |
| 07/13/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 07/01/2026 | Fire-Resistant Penetrations and Joints | GAETANO D'ANTONIO | special |
| 07/01/2026 | Post-installed Anchors | GAETANO D'ANTONIO | special |
| 06/08/2026 | Fire-Resistant Penetrations and Joints | Paul Collins | special |
| 06/01/2026 | Final | Elizabeth Roberts | progress |
| 03/20/2026 | Final | Howard Spivak | progress |
| 03/20/2026 | Fire-Resistant Penetrations and Joints | Tyrone Wells | special |
| 03/12/2026 | Post-installed Anchors | GAETANO D'ANTONIO | special |
| 03/12/2026 | Fire-Resistant Penetrations and Joints | GAETANO D'ANTONIO | special |
| 03/11/2026 | Final | Tyrone Wells | progress |
| 03/11/2026 | Mechanical Systems | Tyrone Wells | special |
| 03/11/2026 | Fire-Resistant Penetrations and Joints | Tyrone Wells | special |
| 03/11/2026 | Final | Howard Spivak | progress |
| 03/11/2026 | Fire-Resistant Penetrations and Joints | Tyrone Wells | special |
| 03/11/2026 | Fire-Resistant Penetrations and Joints | Tyrone Wells | special |
| 12/10/2025 | Structural Stability – Alterations of existing buildings | WILLIAM DAVIS | special |
| 12/10/2025 | Final | WILLIAM DAVIS | progress |
| 12/10/2025 | Tenant Protection Plan Compliance | WILLIAM DAVIS | special |