← Back
BuildNYC
General warehouse
43 9TH STREET
BROOKLYN · BIN 3337603
💬 Discuss this project
1930Year Built
1Stories
E1Building Class
M2-1Zoning
118,367 sfGross Floor Area
7Units
LL97 Covered2 Active Violations 0 unresolved · 2 paperwork only 1 old, status unconfirmed ▸FDNY Report ↗
General warehouse · Owner of record: Gowanus 9th Street Owner · 126,067 sf lot · 0.94 FAR built · Flood zone X500
Locations of Work
ArchitectureMechanicalPlumbingFire Protection
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofTenant improvement for ceramics manufacture25p · 1 filing · 20 docs
Floor 1Tenant improvement for ceramics manufacture42p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Pottery Studio3007/08/2026
Gowanus 9th Street Owner103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/13/2026$37.5M—GOWANUS 9TH STREET OWNER LLC → GOWANUS 9TH STREET HOLDINGS LLC,$317/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Concord Associates1106/11/2025
Opera Studio Architecture208/20/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Opera Studio Architecture2203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DGJ ContractingGeneral Contractor107/08/2026
Hydro MechanicalFire Protection107/08/2026
Hydro MechanicalPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Opera Studio Architecture59701106/11/2025
Steel Core Engineering PL1098208/27/2024
Building Lifecycle
All (94)Filed (13)Permit Issued (3)Violation (9)Inspection (9)Objection (30)Special Inspection (30)
09/23/2025
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
08/28/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
06/27/2025
Special inspection requirement — HVAC-R and service water heating equipment
Thomas Barry
06/27/2025
Special inspection requirement — Maintenance information
Thomas Barry
06/27/2025
Special inspection requirement — HVAC-R and service water heating system controls
Thomas Barry
06/27/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Thomas Barry
06/27/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Thomas Barry
06/11/2025
Filed — Alteration
TENANT IMPROVEMENT WORK ON THE 1ST FLOOR OF EXISTING COMMERCIALBUILDING INCLUDES THE DEMOLITION AND INSTALLATION OF NONSTRUCTURALPARTITION WALLS, FLOOR FINISHES, INSTALLATION OF HIGHVOLUME GAS KILNS FOR CERAMICS MANUFACTURE
B01065931-P9
06/11/2025
Special inspection requirement — HVAC-R and service water heating equipment
Thomas Barry
06/11/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Thomas Barry
06/11/2025
Special inspection requirement — Maintenance information
Thomas Barry
06/11/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Thomas Barry
06/11/2025
Special inspection requirement — HVAC-R and service water heating system controls
Thomas Barry
05/27/2025
Filed — Alteration
TENANT IMPROVEMENT WORK ON THE 1ST FLOOR OF EXISTING COMMERCIALBUILDING INCLUDES THE DEMOLITION AND INSTALLATION OF NONSTRUCTURALPARTITION WALLS, FLOOR FINISHES, INSTALLATION OF HIGHVOLUME GAS KILNS FOR CERAMICS MANUFACTURE
B01065931-P8
05/27/2025
Special inspection requirement — HVAC-R and service water heating equipment
Thomas Barry
05/27/2025
Special inspection requirement — HVAC-R and service water heating system controls
Thomas Barry
05/27/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Thomas Barry
05/27/2025
Special inspection requirement — Maintenance information
Thomas Barry
05/27/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Thomas Barry
04/16/2025
Violation issued (FDNY_NOV, closed)
04/16/2025
Violation issued (FDNY_NOV, closed)
04/16/2025
Violation issued (FDNY_NOV, closed)
04/16/2025
Violation issued (FDNY_NOV, closed)
04/16/2025
Violation issued (FDNY_NOV, closed)
02/05/2025
Filed — Alteration
TENANT IMPROVEMENT WORK ON THE 1ST FLOOR OF EXISTING COMMERCIALBUILDING INCLUDES THE DEMOLITION AND INSTALLATION OF NONSTRUCTURALPARTITION WALLS, FLOOR FINISHES, INSTALLATION OF HIGHVOLUME GAS KILNS FOR CERAMICS MANUFACTURE
B01065931-P7
02/05/2025
Special inspection requirement — HVAC-R and service water heating equipment
Thomas Barry
02/05/2025
Special inspection requirement — Maintenance information
Thomas Barry
02/05/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Thomas Barry
02/05/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Thomas Barry
02/05/2025
Special inspection requirement — HVAC-R and service water heating system controls
Thomas Barry
12/20/2024
Filed — Alteration
TENANT IMPROVEMENT WORK ON THE 1ST FLOOR OF EXISTING COMMERCIALBUILDING INCLUDES THE DEMOLITION AND INSTALLATION OF NONSTRUCTURALPARTITION WALLS, FLOOR FINISHES, INSTALLATION OF HIGHVOLUME GAS KILNS FOR CERAMICS MANUFACTURE
B01065931-P6
12/18/2024
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
12/18/2024
Inspection — Certified Sprinkler - SP - Roughing
Certified
View inspection ↗
12/17/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/09/2024
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
12/05/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
12/02/2024
Filed — Alteration
TENANT IMPROVEMENT WORK ON THE 1ST FLOOR OF EXISTING COMMERCIALBUILDING INCLUDES THE DEMOLITION AND INSTALLATION OF NONSTRUCTURALPARTITION WALLS, FLOOR FINISHES, INSTALLATION OF HIGHVOLUME GAS KILNS FOR CERAMICS MANUFACTURE
B01065931-P5
11/13/2024
Special inspection requirement — Maintenance information
Thomas Barry
11/13/2024
Special inspection requirement — HVAC-R and service water heating equipment
Thomas Barry
11/13/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Thomas Barry
11/13/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Thomas Barry
11/13/2024
Special inspection requirement — HVAC-R and service water heating system controls
Thomas Barry
10/30/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/22/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
10/02/2024
Permit issued — Sprinklers
B01065931-S2-EW-SP
10/02/2024
Permit issued — General Construction
B01065931-I1-GC
10/01/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Thomas Barry
10/01/2024
Special inspection requirement — Sprinkler Systems
Alexander Sheyman
09/25/2024
Objection resolved — Addressed
09/19/2024
Permit issued — Plumbing
B01065931-S1-PL
08/30/2024
Objection raised — Other
08/27/2024
Filed — Alteration
TENANT IMPROVEMENT WORK ON THE 1ST FLOOR OF EXISTING COMMERCIALBUILDING INCLUDES THE DEMOLITION AND INSTALLATION OF NONSTRUCTURALPARTITION WALLS, FLOOR FINISHES, INSTALLATION OF HIGHVOLUME GAS KILNS FOR CERAMICS MANUFACTURE
B01065931-P3
08/27/2024
Special inspection requirement — Energy Code Compliance Inspections
Thomas Barry
08/27/2024
Special inspection requirement — Final
Thomas Barry
08/27/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Thomas Barry
08/22/2024
Filed — Alteration
TENANT IMPROVEMENT WORK ON THE 1ST FLOOR OF EXISTING COMMERCIALBUILDING INCLUDES THE DEMOLITION AND INSTALLATION OF NONSTRUCTURALPARTITION WALLS, FLOOR FINISHES, INSTALLATION OF HIGHVOLUME GAS KILNS FOR CERAMICS MANUFACTURE
B01065931-P2
08/22/2024
Filed — Alteration
TENANT IMPROVEMENT WORK ON THE 1ST FLOOR OF EXISTING COMMERCIALBUILDING INCLUDES THE DEMOLITION AND INSTALLATION OF NONSTRUCTURALPARTITION WALLS, FLOOR FINISHES, INSTALLATION OF HIGHVOLUME GAS KILNS FOR CERAMICS MANUFACTURE
B01065931-P4
08/20/2024
Filed — Alteration
TENANT IMPROVEMENT WORK ON THE 1ST FLOOR OF EXISTING COMMERCIALBUILDING INCLUDES THE DEMOLITION AND INSTALLATION OF NONSTRUCTURALPARTITION WALLS, FLOOR FINISHES, INSTALLATION OF HIGHVOLUME GAS KILNS FOR CERAMICS MANUFACTURE
B01065931-P1
07/02/2024
Objection resolved — Addressed
07/02/2024
Objection resolved — Addressed
Latest 60 of 94 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersSigned-offHydro Mechanical10/02/2024
DOB NOWGeneral ConstructionPermit IssuedDGJ Contracting10/02/2024
DOB NOWPlumbingPermit IssuedHydro Mechanical09/19/2024
BISOTISSUEDBSD Tri-State Maintenance06/25/2014
BISOTISSUEDBSD Tri-State Maintenance11/12/2013
BISOTISSUEDM&B Maintenance Group02/18/2011
BISOTISSUEDM&B Maintenance Group10/05/2010
1 project · most recent 06/11/2025
Heating and Air Conditioning Systems
FiledStatusContractorScope
06/11/2025Permit IssuedDGJ ContractingHeating and Air Conditioning Systems
1 project · most recent 06/11/2025
Sprinkler System
FiledStatusContractorScope
06/11/2025Signed-offHydro MechanicalSprinkler System
1 project · most recent 06/11/2025
Gas Water/Sanitary
FiledStatusContractorScope
06/11/2025Permit IssuedHydro MechanicalGas, Water/Sanitary
3 projects · most recent 02/17/2025
General Wiring
FiledStatusContractorScope
02/17/2025CompleteCurrent Power Electric—
04/03/2024On Hold - Returned CheckNet Power ElectricGeneral Wiring
05/16/2018Permit IssuedIlluminous ElectricGeneral Wiring
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
09/23/2025Pass-Final General Construction Non-Directive 14PassView ↗
08/28/2025Fail-Final General Construction Non-Directive 14FailView ↗
12/18/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
12/18/2024Certified Sprinkler - SP - RoughingCertifiedView ↗
12/17/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/09/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
12/05/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
12/05/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
10/30/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/22/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 50
DateRequirementInspectorRole
06/27/2025HVAC-R and service water heating equipmentThomas Barryenergy_progress
06/27/2025Maintenance informationThomas Barryenergy_progress
06/27/2025HVAC-R and service water heating system controlsThomas Barryenergy_progress
06/27/2025Fire-Resistant Penetrations and JointsThomas Barryspecial
06/27/2025HVAC-R and service water piping design and insulationThomas Barryenergy_progress
06/11/2025HVAC-R and service water heating equipmentThomas Barryenergy_progress
06/11/2025HVAC-R and service water piping design and insulationThomas Barryenergy_progress
06/11/2025Maintenance informationThomas Barryenergy_progress
06/11/2025Fire-Resistant Penetrations and JointsThomas Barryspecial
06/11/2025HVAC-R and service water heating system controlsThomas Barryenergy_progress
05/27/2025HVAC-R and service water heating equipmentThomas Barryenergy_progress
05/27/2025HVAC-R and service water heating system controlsThomas Barryenergy_progress
05/27/2025HVAC-R and service water piping design and insulationThomas Barryenergy_progress
05/27/2025Maintenance informationThomas Barryenergy_progress
05/27/2025Fire-Resistant Penetrations and JointsThomas Barryspecial
02/05/2025HVAC-R and service water heating equipmentThomas Barryenergy_progress
02/05/2025Maintenance informationThomas Barryenergy_progress
02/05/2025HVAC-R and service water piping design and insulationThomas Barryenergy_progress
02/05/2025Fire-Resistant Penetrations and JointsThomas Barryspecial
02/05/2025HVAC-R and service water heating system controlsThomas Barryenergy_progress
11/13/2024Maintenance informationThomas Barryenergy_progress
11/13/2024HVAC-R and service water heating equipmentThomas Barryenergy_progress
11/13/2024Fire-Resistant Penetrations and JointsThomas Barryspecial
11/13/2024HVAC-R and service water piping design and insulationThomas Barryenergy_progress
11/13/2024HVAC-R and service water heating system controlsThomas Barryenergy_progress
Latest 25 of 50.
▾Documents — 105 on file (BIS + DOB NOW)
▸Plans & Drawings13
▸DOB NOWPlans/Sketch13
08/21/2026B01065931-I1Request digital key ↗
08/21/2026B01065931-P9Request digital key ↗
08/21/2026B01065931-P8Request digital key ↗
Showing 3 of 13 on file for this type
▸Applications & Permits8
▸BISPLAN / WORK APPROVAL APPLICATION4
07/03/2012320495530Open ↗
01/10/2012320263479Open ↗
02/24/2011320263479Open ↗
Showing 3 of 4 on file for this type
▸BISWORK PERMIT APPLICATION4
07/18/2014320495530Open ↗
11/25/2013320495530Open ↗
02/22/2011320208725Open ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications54
▸DOB NOWProgress Inspector Seal & Signature27
08/31/2026B01065931-P8Open ↗
08/31/2026B01065931-P8Open ↗
08/31/2026B01065931-P8Open ↗
Showing 3 of 27 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature13
08/21/2026B01065931-I1Open ↗
08/21/2026B01065931-P9Open ↗
08/21/2026B01065931-P8Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
10/03/2026B01065931-P3Open ↗
08/31/2026B01065931-P8Open ↗
08/27/2026B01065931-I1Open ↗
Showing 3 of 9 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION5
07/03/2012320495530Open ↗
03/16/2012320208725Open ↗
01/27/2011320263479Open ↗
Showing 3 of 5 on file for this type
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING1
01/27/2011320263479Open ↗
▸Environmental & Asbestos16
▸DOB NOWDEP ACP-5: Asbestos Assessment Report13
08/21/2026B01065931-I1Open ↗
08/21/2026B01065931-P9Open ↗
08/21/2026B01065931-P8Open ↗
Showing 3 of 13 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'2
01/27/2011320263479Open ↗
09/08/2010320208725Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
06/28/2012320495530Open ↗
▸Energy Compliance2
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
07/03/2012320495530Open ↗
▸BISTR8: Energy Code Progress Inspections1
07/22/2013320495530Open ↗
▸Approvals, Objections & Sign-offs5
▸BISADMINISTRATIVE OBJECTIONS3
06/28/2012320495530Open ↗
01/27/2011320263479Open ↗
09/08/2010320208725Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
07/22/2013320495530Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
03/16/2012320208725Open ↗
▸Cost, Insurance & Ownership4
▸BISCOST AFFIDAVIT4
07/03/2012320495530Open ↗
03/16/2012320208725Open ↗
01/27/2011320263479Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms2
▸BISEFILING COVER SHEET2
07/03/2012320495530Open ↗
09/08/2010320208725Open ↗