| Firm | Filings | Most Recent |
|---|---|---|
| Parker and West Engineering | 2 | 08/07/2026 |
| Joseph M. Morace, A.I.A., Architect | 4 | 12/12/2024 |
| Island Associates | 2 | 12/21/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| Island Associates | 7 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Wallace Avenue Construction | General Contractor | 3 | 04/09/2026 |
| Duo Plumbing & Heating | Plumbing | 2 | 07/08/2026 |
| Sunrun Installation Service | General Contractor | 1 | 07/10/2026 |
| Wallace Avenue Construction | Scaffold | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Parker and West Engineering | 5272 | 2 | 08/07/2026 |
| Island Engineering Associates | 264 | 1 | 12/20/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | Sunrun Installation Service | 07/09/2026 |
| DOB NOW | Curb Cut | Signed-off | Wallace Avenue Construction | 12/12/2024 |
| DOB NOW | Plumbing | Signed-off | Duo Plumbing & Heating | 05/20/2024 |
| DOB NOW | Plumbing | Signed-off | Duo Plumbing & Heating | 05/20/2024 |
| DOB NOW | Foundation | Permit Issued | Wallace Avenue Construction | 04/02/2024 |
| DOB NOW | Full Demolition | Signed-off | Wallace Avenue Construction | 01/19/2024 |
| DOB NOW | Construction Fence | Signed-off | Wallace Avenue Construction | 12/26/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/12/2024 | Signed-off | Duo Plumbing & Heating | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/02/2026 | Complete | Sunrun Solar Electl | — |
| 08/25/2024 | Complete | A. J. Caruso Electrical I | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/12/2024 | Signed-off | Wallace Avenue Construction | Concrete, Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/07/2026 | Signed-off | Sunrun Installation Service | 20 panels, 9 kw, 210 roof_area_sqft |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/06/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/31/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/31/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 12/06/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/02/2024 | Certified Sprinkler (PL)-Sprinkler-Hydro | Certified | View ↗ |
| 08/20/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/20/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| 06/13/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| 06/07/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/23/2026 | Fire-Resistant Penetrations and Joints | Walid Abdulla | special |
| 07/23/2026 | Structural Stability – Alterations of existing buildings | Walid Abdulla | special |
| 07/23/2026 | Energy Code Compliance Inspections | Walid Abdulla | progress |
| 07/23/2026 | Final | Walid Abdulla | progress |
| 07/23/2026 | Air barrier - visual inspection | Walid Abdulla | energy_progress |