← Back
Walk-up cooperative
430 WEST 46 STREET
MANHATTAN · BIN 1026467
💬 Discuss this project
1920Year Built
5Stories
C6Building Class
R8Zoning
8,175 sfGross Floor Area
10Units
Rent Stabilized3 Open Violations ▸
Walk-up cooperative · Owner of record: 430 W 46TH ST HSNG ETC · 2,510 sf lot · 3.26 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
430 WEST 46TH STREET HDFC %10K MGT2307/08/2026
430 W 46TH ST HSNG ETC203/22/2026
C/O HSC MANAGEMENT CORP 4303/22/2026
HSC MANAGEMENT103/22/2026
430 WEST 46ST HSNG ETC.103/22/2026
430 WEST 46 ST HSNG ETC203/22/2026
430 W 46 ST MSNG ETC103/22/2026
LAKHI GENERAL CONTRACTOR103/21/2026
STEEL SYSTEMS403/21/2026
LOVELY CONSTRUCTION203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PAUL PERDEK, PROF. ENG. PLLC408/20/2024
MSM ENGINEERING SERVICES, PLLC108/14/2024
ASHRAF CORP211/24/2021
CUONO ENGINEERING PLLC109/15/2021
Ewing Cole103/23/2021
GREEN DESIGN403/16/2021
ENTHINK ENGINEERS LLC106/29/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AE DESIGN SOLUTION1003/21/2026
CORNERSTONE CONSULTING203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ANDAMIO SCAFFOLDING LLCGeneral Contractor1807/08/2026
EVEREST SCAFFOLDING INCGeneral Contractor1007/08/2026
PRESERV BLD RESTOR MGT INGeneral Contractor1007/08/2026
SYED-NAQVI ALTAFElectrical103/21/2026
BORRESS, HOWARDElectrical103/21/2026
WILFRED JEFFREYElectrical103/21/2026
SYED-NAQVI, ALTAFElectrical103/21/2026
GREGORY PAPANTONIOUElectrical103/21/2026
PETERSON, TAYLORElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CHEN ENGINEERING SERVICES1826209/15/2021
Building Lifecycle
All (115)Filed (14)Permit Issued (22)Signed Off (11)Violation (60)Objection (2)Special Inspection (6)
09/02/2025
Violation issued (HPD, open)
B
11/07/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
M01095259-I1
11/07/2024
Signed off — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION
M00614339-I1
10/25/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY BETAMAX HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00627875-I1
10/25/2024
Signed off — Alteration
M01043782-I1
10/25/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY DEBRIS CHUTE AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01090230-I1
10/25/2024
Signed off — Alteration
M01090213-I1
10/16/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. LIVE LOAD 300 PSF
M00411798-I1
10/07/2024
Permit issued — Supported Scaffold
M00614339-I1-SF
09/27/2024
Violation issued (ECB, closed)
Unknown
08/20/2024
Filed — Alteration
INSTALLATION OF TEMPORARY DEBRIS CHUTE AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01090230-I1
08/20/2024
Permit issued — Protection and Mechanical Methods
M01090230-I1-PMM
08/16/2024
Filed — Alteration
M01090213-I1
08/16/2024
Permit issued — Protection and Mechanical Methods
M01090213-I1-PMM
08/14/2024
Filed — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
M01095259-I1
08/14/2024
Permit issued — Sidewalk Shed
M01095259-I1-SH
05/28/2024
Permit issued — Protection and Mechanical Methods
M01043782-I1-PMM
05/24/2024
Filed — Alteration
M01043782-I1
02/06/2024
Violation issued (ECB, closed)
Unknown
01/25/2024
Violation issued (ECB, closed)
Unknown
01/24/2024
Violation issued (ECB, closed)
Construction
01/08/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/10/2023
Permit issued — Supported Scaffold
M00614339-I1-SF
09/01/2023
Permit issued — Sidewalk Shed
M00411798-I1-SH
06/22/2023
Permit issued — Protection and Mechanical Methods
M00627875-I1-PM
05/18/2023
Violation issued (ECB, closed)
Construction
05/09/2023
Violation issued (ECB, closed)
Construction
03/17/2023
Violation issued (ECB, closed)
Construction
01/12/2023
Violation issued (ECB, closed)
Construction
10/12/2022
Permit issued — Supported Scaffold
M00614339-I1-SF
09/08/2022
Permit issued — Sidewalk Shed
M00411798-I1-SH
08/26/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/31/2022
Signed off — Alteration
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00056756-I1
03/22/2022
Violation issued (ECB, closed)
Construction
03/09/2022
Signed off — Alteration
TEMPORARY SHORING OF EXISTING FRAMING TO PERFORM REPAIR WORK ON EXISTING WESTERN WALL (BY OTHERS), INCLUDING: TEMPORARY STEEL BEAMS AND SHORE SYSTEMS FROM ROOF FRAMING DOWN TO CELLAR AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M00585417-I1
02/16/2022
Violation issued (HPD, closed)
I
02/16/2022
Violation issued (HPD, closed)
A
01/14/2022
Permit issued — Structural
M00585417-I1-ST
01/06/2022
Filed — Alteration
INSTALLATION OF TEMPORARY BETAMAX HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00627875-I1
11/24/2021
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION
M00614339-P1
11/10/2021
Signed off — Alteration
M00411801-I1
10/20/2021
Permit issued — Supported Scaffold
M00614339-I1-SF
10/19/2021
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION
M00614339-I1
09/20/2021
Objection raised — Energy
09/20/2021
Objection resolved — Addressed
09/15/2021
Filed — Alteration
TEMPORARY SHORING OF EXISTING FRAMING TO PERFORM REPAIR WORK ON EXISTING WESTERN WALL (BY OTHERS), INCLUDING: TEMPORARY STEEL BEAMS AND SHORE SYSTEMS FROM ROOF FRAMING DOWN TO CELLAR AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M00585417-I1
09/14/2021
Permit issued — Sidewalk Shed
M00411798-I1-SH
09/13/2021
Permit issued — Supported Scaffold
M00411801-I1-SF
08/30/2021
Special inspection requirement — Post-installed Anchors
HENLIA CHEN
08/30/2021
Special inspection requirement — Structural Stability – Alterations of existing buildings
HENLIA CHEN
08/30/2021
Special inspection requirement — Structural Steel - Details
HENLIA CHEN
08/30/2021
Special inspection requirement — Final
HENLIA CHEN
08/16/2021
Signed off — Alteration
M00391166-I1
07/21/2021
Violation issued (HPD, closed)
C
04/09/2021
Permit issued — Structural
M00391166-I1-ST
03/30/2021
Permit issued — Sidewalk Shed
M00056756-I1-SH
03/23/2021
Filed — Alteration
M00391166-I1
03/18/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/17/2021
Special inspection requirement — Final
Sunil Saigal
03/16/2021
Filed — Alteration
M00411801-P1
Latest 60 of 115 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupported ScaffoldSigned-offANDAMIO SCAFFOLDING LLC10/07/2024
DOB NOWProtection and Mechanical MethodsSigned-offPRESERV BLD RESTOR MGT IN08/20/2024
DOB NOWProtection and Mechanical MethodsSigned-offPRESERV BLD RESTOR MGT IN08/16/2024
DOB NOWSidewalk ShedSigned-offANDAMIO SCAFFOLDING LLC08/14/2024
DOB NOWProtection and Mechanical MethodsSigned-offPRESERV BLD RESTOR MGT IN05/28/2024
DOB NOWSupported ScaffoldSigned-offANDAMIO SCAFFOLDING LLC10/10/2023
DOB NOWSidewalk ShedSigned-offANDAMIO SCAFFOLDING LLC09/01/2023
DOB NOWProtection and Mechanical MethodsSigned-offPRESERV BLD RESTOR MGT IN06/22/2023
DOB NOWSupported ScaffoldSigned-offANDAMIO SCAFFOLDING LLC10/12/2022
DOB NOWSidewalk ShedSigned-offANDAMIO SCAFFOLDING LLC09/08/2022
DOB NOWStructuralSigned-offPRESERV BLD RESTOR MGT IN01/14/2022
DOB NOWSupported ScaffoldSigned-offANDAMIO SCAFFOLDING LLC10/20/2021
DOB NOWSidewalk ShedSigned-offANDAMIO SCAFFOLDING LLC09/14/2021
DOB NOWSupported ScaffoldSigned-offANDAMIO SCAFFOLDING LLC09/13/2021
DOB NOWStructuralSigned-offPRESERV BLD RESTOR MGT IN04/09/2021
DOB NOWSidewalk ShedSigned-offANDAMIO SCAFFOLDING LLC03/30/2021
DOB NOWSidewalk ShedSigned-offEVEREST SCAFFOLDING INC10/14/2020
DOB NOWSupported ScaffoldSigned-offEVEREST SCAFFOLDING INC10/14/2020
DOB NOWSidewalk ShedSigned-offEVEREST SCAFFOLDING INC04/01/2020
DOB NOWSidewalk ShedSigned-offEVEREST SCAFFOLDING INC07/12/2019
DOB NOWSidewalk ShedSigned-offEVEREST SCAFFOLDING INC07/26/2018
DOB NOWSidewalk ShedSigned-offEVEREST SCAFFOLDING INC06/30/2018
BISOTISSUEDPRESERV BLD RESTOR MGT IN07/01/2024
BISOTISSUEDPRESERV BLD RESTOR MGT IN04/29/2024
BISOTISSUEDPRESERV BLD RESTOR MGT IN07/03/2023
BISOTISSUEDPRESERV BLD RESTOR MGT IN05/24/2023
BISOTISSUEDPRESERV BLD RESTOR MGT IN06/24/2022
BISOTISSUEDPRESERV BLD RESTOR MGT IN01/12/2022
BISOTISSUEDPRESERV BLD RESTOR MGT IN01/15/2021
BISPLISSUEDARIEL SERVICES INC09/06/2018
BISMHISSUEDP. SPINA CONSTRUCTION INC08/03/2018
BISEQISSUEDGUL & G CONTRACTING INC04/21/2017
BISEQISSUEDGUL & G CONTRACTING INC04/21/2017
BISPLISSUEDTMS PLMBG & HTG CORP10/18/2010
BISOTISSUEDDAVID TURNER ARCHITECT,PC09/08/2010
BISEQISSUEDLAKHI GENERAL CONTRACTOR07/16/2007
BISOTISSUEDLOVELY CONSTRUCTION CORP06/25/2007
4 projects · most recent 10/13/2020
General Wiring
FiledStatusContractorScope
10/13/2020CompleteBOROWIDE ELECT'L CONTR'S—
10/03/2019Permit IssuedCITI-WIDE ELECTRIC INCGeneral Wiring
06/27/2018CompleteBOROWIDE ELECT'L CONTR'S—
03/28/2018CompleteGILSTON BROTHERS ELECT'LGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 6
DateRequirementInspectorRole
08/30/2021Post-installed AnchorsHENLIA CHENspecial
08/30/2021Structural Stability – Alterations of existing buildingsHENLIA CHENspecial
08/30/2021Structural Steel - DetailsHENLIA CHENspecial
08/30/2021FinalHENLIA CHENprogress
03/17/2021FinalSunil Saigalprogress
06/26/2018FinalSunil Saigalprogress
▾Documents — 128 on file (BIS + DOB NOW)
▸Plans & Drawings14
▸DOB NOWPlans/Sketch9
09/06/2026M00056756-I1Request digital key ↗
09/03/2026M00614339-I1Request digital key ↗
09/03/2026M00614339-P1Request digital key ↗
Showing 3 of 9 on file for this type
▸DOB NOWPlans/Sketch - Supported Scaffold2
09/04/2026M00411801-I1Request digital key ↗
08/15/2026M00411801-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed2
09/04/2026M00411798-I1Request digital key ↗
09/04/2026M00411798-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Structural1
09/04/2026M00391166-I1Request digital key ↗
▸Applications & Permits19
▸BISWORK PERMIT APPLICATION10
04/30/2024140984120Open ↗
05/25/2023140984120Open ↗
01/15/2021140984120Open ↗
Showing 3 of 10 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION8
10/21/2025140984120Open ↗
04/04/2024140984120Open ↗
01/19/2022140984120Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWHPD Certification Letter or CPC Special Permit1
08/13/2026M00391166-I1Open ↗
▸Seals & Professional Certifications32
▸DOB NOWDPL-1: Design Professional Seal & Signature14
09/06/2026M00056756-I1Open ↗
09/04/2026M00411798-P1Open ↗
09/04/2026M00411798-I1Open ↗
Showing 3 of 14 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION4
08/03/2018123461636Open ↗
08/03/2018123461636Open ↗
07/26/2018123461636Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT4
07/26/2018123461636Open ↗
07/26/2018123461636Open ↗
05/09/2017123058724Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
07/26/2018123461636Open ↗
05/09/2017123058724Open ↗
05/09/2017123061934Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
08/30/2026M00585417-I1Open ↗
08/30/2026M00585417-I1Open ↗
08/30/2026M00585417-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature3
08/30/2026M00585417-I1Open ↗
08/29/2026M00056756-I1Open ↗
08/28/2026M00411801-I1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
12/28/2020140984120Open ↗
▸Trade Schedules & Equipment3
▸BISSCHEDULE B - PLUMBING1
08/04/2010120429312Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
07/26/2018123461636Open ↗
▸BISSELF-CERT PLUMBING NOTICE1
01/26/2011120429312Open ↗
▸Safety & Tenant Protection27
▸DOB NOWHPD-2: Clinton Special District Anti-Harassment Checklist14
09/06/2026M00056756-I1Open ↗
09/04/2026M00411798-I1Open ↗
09/04/2026M00411798-P1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWTenant Protection Plan5
09/04/2026M00411798-I1Open ↗
09/04/2026M00411798-P1Open ↗
08/13/2026M00391166-I1Open ↗
Showing 3 of 5 on file for this type
▸BISTenant Protection Plan and Notes3
07/26/2018123461636Open ↗
05/09/2017123058724Open ↗
05/09/2017123061934Open ↗
▸BISSRO MD ANTI-HARASSMENT CHECKLIST1
07/30/2018123461636Open ↗
▸BISTPP1: TENANT PROTECTION PLAN1
08/19/2024140984120Open ↗
▸BISCLINTON DISTRICT: ANTI-HARASSMENT CHECKLIST1
12/28/2020140984120Open ↗
▸BISHPD-2 - Clinton Special district Anti-Harassment Checklist1
08/31/2010120429312Open ↗
▸DOB NOWCertificate of No Harassment1
08/13/2026M00391166-I1Open ↗
▸Environmental & Asbestos5
▸BISASBESTOS: CERTIFICATION (DEP ACP5)4
12/28/2020140984120Open ↗
07/30/2018123461636Open ↗
05/09/2017123061934Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
09/04/2026M00391166-I1Open ↗
▸Energy Compliance4
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
08/03/2018123461636Open ↗
07/26/2018123461636Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
04/04/2024140984120Open ↗
12/28/2020140984120Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
04/04/2024140984120Open ↗
12/28/2020140984120Open ↗
▸Approvals, Objections & Sign-offs2
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
06/23/2015120429312Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
08/04/2010120429312Open ↗
▸Cost, Insurance & Ownership9
▸BISCOST AFFIDAVIT7
10/21/2025140984120Open ↗
04/04/2024140984120Open ↗
01/28/2022140984120Open ↗
Showing 3 of 7 on file for this type
▸BISCOST AFFIDAVIT ESTIMATE: (PW3)1
12/28/2020140984120Open ↗
▸BISHIC LICENSE OR AFFIDAVIT1
09/13/2010120429312Open ↗
▸Filing & Intake Forms9
▸BISEFILING COVER SHEET4
07/26/2018123461636Open ↗
05/09/2017123058724Open ↗
05/09/2017123061934Open ↗
Showing 3 of 4 on file for this type
▸BISBOROUGH INTAKE FORM2
04/30/2024140984120Open ↗
05/18/2023140984120Open ↗
▸BISADDITIONAL INFORMATION2
04/04/2024140984120Open ↗
03/09/2022140984120Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
12/28/2020140984120Open ↗
▸Other Documents2
▸DOB NOWMultiple Dwelling Special District Feasibility of Government Funded Rehabilitation1
09/06/2026M00056756-I1Open ↗
▸DOB NOWMultiple Dwelling Special District Notice to Community Board1
09/06/2026M00056756-I1Open ↗