← Back
Two family converted from one family
432 MACON STREET
BROOKLYN · Bedford-Stuyvesant (East) · BIN 3046810
💬 Discuss this project
1889Year Built
2Stories
B3Building Class
R6BZoning
2,820 sfGross Floor Area
2Units
36 Open Violations ▸FDNY Report ↗
Two family converted from one family · 2,000 sf lot · 1.41 FAR built · Flood zone X
Locations of Work
ArchitectureElectrical
Roof3p · 1 filing · 9 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC108/12/2024
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CENTURION SOLAR ENERGYGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854108/12/2024
Building Lifecycle
All (59)Filed (1)Permit Issued (1)Violation (42)Objection (10)Special Inspection (5)
05/30/2025
Permit issued — Solar
B01092807-I1-SL
09/05/2024
Objection resolved — Addressed
08/27/2024
Objection resolved — Addressed
08/27/2024
Objection resolved — Addressed
08/27/2024
Objection resolved — Addressed
08/27/2024
Objection resolved — Addressed
08/15/2024
Objection raised — Other
08/15/2024
Objection raised — Scope
08/15/2024
Objection raised — Other
08/15/2024
Objection raised — Other
08/15/2024
Objection raised — Structural
08/12/2024
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONICGENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS OR OCCUPANCY.*
B01092807-I1
08/07/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
08/07/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
08/07/2024
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
08/07/2024
Special inspection requirement — Final
TOM PETERSEN
08/07/2024
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
09/25/2013
Violation issued (HPD, open)
B
09/25/2013
Violation issued (HPD, open)
B
09/25/2013
Violation issued (HPD, open)
B
09/25/2013
Violation issued (HPD, open)
B
09/25/2013
Violation issued (HPD, open)
B
09/25/2013
Violation issued (HPD, open)
A
09/25/2013
Violation issued (HPD, open)
A
12/01/2012
Violation issued (HPD, open)
B
12/01/2012
Violation issued (HPD, closed)
C
12/01/2012
Violation issued (HPD, closed)
C
12/01/2012
Violation issued (HPD, open)
C
12/01/2012
Violation issued (HPD, closed)
C
11/26/2012
Violation issued (HPD, open)
B
11/26/2012
Violation issued (HPD, open)
A
11/26/2012
Violation issued (HPD, open)
B
11/26/2012
Violation issued (HPD, open)
C
11/26/2012
Violation issued (HPD, open)
A
11/26/2012
Violation issued (HPD, open)
B
11/26/2012
Violation issued (HPD, open)
A
11/26/2012
Violation issued (HPD, open)
A
11/26/2012
Violation issued (HPD, open)
A
10/09/2012
Violation issued (HPD, open)
A
10/09/2012
Violation issued (HPD, open)
B
10/09/2012
Violation issued (HPD, open)
B
10/09/2012
Violation issued (HPD, open)
A
10/09/2012
Violation issued (HPD, open)
A
10/09/2012
Violation issued (HPD, open)
B
10/09/2012
Violation issued (HPD, open)
B
10/09/2012
Violation issued (HPD, closed)
C
10/09/2012
Violation issued (HPD, closed)
C
11/16/2011
Violation issued (HPD, open)
B
11/16/2011
Violation issued (HPD, open)
C
11/16/2011
Violation issued (HPD, open)
B
11/16/2011
Violation issued (HPD, open)
C
03/16/2011
Violation issued (HPD, open)
A
03/16/2011
Violation issued (HPD, open)
B
03/16/2011
Violation issued (HPD, open)
C
03/16/2011
Violation issued (HPD, open)
C
03/16/2011
Violation issued (HPD, open)
B
07/01/2010
Violation issued (ECB, closed)
Construction
09/12/2007
Violation issued (HPD, open)
B
09/05/2007
Violation issued (HPD, open)
B
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedCENTURION SOLAR ENERGY05/30/2025
1 project · most recent 06/06/2024
FiledStatusContractorScope
06/06/2024Permit IssuedBERGER QUALITY ELEC'L CON—
1 project · most recent 08/12/2024
FiledStatusContractorScope
08/12/2024Permit IssuedCENTURION SOLAR ENERGY7 panels, 2.98 kw, 147.13 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
08/07/2024Fire-Resistant Penetrations and JointsTOM PETERSENspecial
08/07/2024Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
08/07/2024Energy Code Compliance InspectionsTOM PETERSENprogress
08/07/2024FinalTOM PETERSENprogress
08/07/2024Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/24/2026B01092807-I1Request digital key ↗
▸Applications & Permits1
▸DOB NOWLPC Approval/Permit1
08/13/2026B01092807-I1Open ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/31/2026B01092807-I1Open ↗
08/31/2026B01092807-I1Open ↗
08/31/2026B01092807-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/31/2026B01092807-I1Open ↗
08/31/2026B01092807-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/24/2026B01092807-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/24/2026B01092807-I1Open ↗