Roof9p · 5 filings · 20 docs
ArchitectureElectricalGeneralStructural
Issued Permit Scope
Antenna · General Construction · Supported Scaffold
INSTALL TEMPORARY 5 LEVELS OF PIPE SCAFFOLDING TO REPAIR THE EXISTING CHIMNEY AS PER PLANS, NO CHANGE IN USE OCCUPANCY OR EGRESS
On file for this project
3 documents
INSTALL CHIMNEY LINER AND TANK ENCLOSURE
On file for this project
6 documents
DISH WIRELESS- Installation of 3 new antenna sectors with 6 RRH units and 1 GPS unit on roof.. Install 1 new equipment cabinet on steel platform. Related service connection in basement. All in conformance with TPPN 5/98.
On file for this project
4 documents · 2 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 71p · 1 filing · 6 docs
Architecture
Issued Permit Scope
General Construction
INSTALL CHIMNEY LINER AND TANK ENCLOSURE
On file for this project
6 documents
Floor 61p · 1 filing · 6 docs
Architecture
Issued Permit Scope
General Construction
INSTALL CHIMNEY LINER AND TANK ENCLOSURE
On file for this project
6 documents
Floor 51p · 1 filing · 6 docs
Architecture
Issued Permit Scope
General Construction
INSTALL CHIMNEY LINER AND TANK ENCLOSURE
On file for this project
6 documents
Floor 41p · 1 filing · 6 docs
Architecture
Issued Permit Scope
General Construction
INSTALL CHIMNEY LINER AND TANK ENCLOSURE
On file for this project
6 documents
Floor 31p · 1 filing · 6 docs
Architecture
Issued Permit Scope
General Construction
INSTALL CHIMNEY LINER AND TANK ENCLOSURE
On file for this project
6 documents
Floor 21p · 1 filing · 6 docs
Architecture
Issued Permit Scope
General Construction
INSTALL CHIMNEY LINER AND TANK ENCLOSURE
On file for this project
6 documents
Floor 19p · 3 filings · 20 docs
ArchitectureEquipmentGeneralPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Sidewalk Shed · Structural
REPLACE, RELOCATE PLUMBING FIXTURES AT 1ST FLOOR REAR. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
On file for this project
11 documents · 1 drawing sheet
INSTALL CHIMNEY LINER AND TANK ENCLOSURE
On file for this project
6 documents
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER # 33 OF THE 2014 CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
3 documents
Cellar12p · 3 filings · 20 docs
ArchitectureMechanicalPlumbing
Issued Permit Scope
Boiler Equipment · General Construction · Plumbing
INSTALL NEW GAS SERVICE, METER AND PIPING.
On file for this project
9 documents
REPLACE BOILER AND OIL BURNER WITH BOILER AND GAS/OIL BURNER. REMOVE FUEL OIL TANK AND INSTALL REPLACEMENT FUEL OIL TANK. CHANGE GRADE OF FUEL OIL FROM #4 TO #2.
On file for this project
6 documents
INSTALL CHIMNEY LINER AND TANK ENCLOSURE
On file for this project
6 documents
Sub-Basement2 filings · 8 docs
Electrical
Issued Permit Scope
Antenna
DISH WIRELESS- Installation of 3 new antenna sectors with 6 RRH units and 1 GPS unit on roof.. Install 1 new equipment cabinet on steel platform. Related service connection in basement. All in conformance with TPPN 5/98.
On file for this project
4 documents
Decommission of existing Sprint site. Remove antennas and equipment from the roof. Service connection in basement. Initial installation approved under application #104721366
On file for this project
4 documents
Site & exterior10p · 2 filings · 9 docs
ArchitectureEquipmentGeneralMechanicalStructural
Issued Permit Scope
General Construction · Supported Scaffold
MASONRY REPAIR WORK, DECORATIVE STONE REPAIR WORK.
On file for this project
6 documents · 6 drawing sheets
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
On file for this project
3 documents · 6 drawing sheets